State of Punjab - Subsection

Section 25(9) in The Punjab State Agricultural Marketing Board (Engineering Wing) Execution of Works Rules, 1979

(9)[. Monthly Statement of sanctioned estimates. - The Executive Engineer shall submit to the Superintendent Engineer, a statement showing the names of all estimates sanctioned by him during the month, together with the amount of each estimate. The Superintending Engineer shall submit a similar statement to the Chief Engineer which shall include all estimates sanctioned by the Executive Engineer as well as by him] [See Legislative Supplement Part III dated 23rd June, 1989.].Annexure IOmitted vide Punjab Notification dated 21.7.1998.Annexure IIOmitted vide Punjab Notification dated 21.7.1998.