Section 6(2)(a) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019
(a)Where an interconnected transmission system of other transmission licensee has not achieved the commercial operation as on the date of commercial operation of the transmission system (which is not before the SCOD of the interconnected transmission system) and the Commission has approved the date of commercial operation of such transmission system in terms of clause (2) of Regulation 5 of these regulations, the other transmission licensee shall be liable to pay the transmission charges of the transmission system in accordance with clause (5) of Regulation 14 of these regulations to the transmission licensee till the interconnected transmission system achieves commercial operation: