Union of India - Section

Section 6 in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019

6. Treatment of mismatch in date of commercial operation.

(1)In case of mismatch of the date of commercial operation of the generating station and the transmission system, the liability for the transmission charges shall be determined as under:
(a)Where the generating station has not achieved the commercial operation as on the date of commercial operation of the associated transmission system (which is not before the SCOD of the generating station) and the Commission has approved the date of commercial operation of such transmission system in terms of clause (2) of the Regulation 5 of these regulations, the generating company shall be liable to pay the transmission charges of the associated transmission system in accordance with clause (5) of Regulation 14 of these regulations to the transmission licensee till the generating station or unit thereof achieves commercial operation:
(b)Where the associated transmission system has not achieved the commercial operation as on the date of commercial operation of the concerned generating station or unit thereof (which is not before the SCOD of the transmission system), the transmission licensee shall make alternate arrangement for the evacuation from the generating station at its own cost, failing which, the transmission licensee shall be liable to pay the transmission charges to the generating company as determined by the Commission, in accordance with clause (5) of Regulation 14 of these regulations, till the transmission system achieves the commercial operation.
(2)In case of mismatch of the date of commercial operation of the transmission system and the transmission system of other transmission licensee, the liability for the transmission charges shall be determined as under:
(a)Where an interconnected transmission system of other transmission licensee has not achieved the commercial operation as on the date of commercial operation of the transmission system (which is not before the SCOD of the interconnected transmission system) and the Commission has approved the date of commercial operation of such transmission system in terms of clause (2) of Regulation 5 of these regulations, the other transmission licensee shall be liable to pay the transmission charges of the transmission system in accordance with clause (5) of Regulation 14 of these regulations to the transmission licensee till the interconnected transmission system achieves commercial operation:
(b)Where the transmission system has not achieved the commercial operation as on the date of commercial operation of the interconnected transmission system of other transmission licensee (which is not before the SCOD of the transmission system), the transmission licensee shall be liable to pay the transmission charges of such interconnected transmission system to the other transmission licensee or as may be determined by the Commission, in accordance with clause (5) of Regulation 14 of these regulations, till the transmission system achieves the commercial operation.