Section 6(1)(a) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019
(a)Where the generating station has not achieved the commercial operation as on the date of commercial operation of the associated transmission system (which is not before the SCOD of the generating station) and the Commission has approved the date of commercial operation of such transmission system in terms of clause (2) of the Regulation 5 of these regulations, the generating company shall be liable to pay the transmission charges of the associated transmission system in accordance with clause (5) of Regulation 14 of these regulations to the transmission licensee till the generating station or unit thereof achieves commercial operation: