Union of India - Subsection

Section 6(1) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019

(1)In case of mismatch of the date of commercial operation of the generating station and the transmission system, the liability for the transmission charges shall be determined as under:
(a)Where the generating station has not achieved the commercial operation as on the date of commercial operation of the associated transmission system (which is not before the SCOD of the generating station) and the Commission has approved the date of commercial operation of such transmission system in terms of clause (2) of the Regulation 5 of these regulations, the generating company shall be liable to pay the transmission charges of the associated transmission system in accordance with clause (5) of Regulation 14 of these regulations to the transmission licensee till the generating station or unit thereof achieves commercial operation:
(b)Where the associated transmission system has not achieved the commercial operation as on the date of commercial operation of the concerned generating station or unit thereof (which is not before the SCOD of the transmission system), the transmission licensee shall make alternate arrangement for the evacuation from the generating station at its own cost, failing which, the transmission licensee shall be liable to pay the transmission charges to the generating company as determined by the Commission, in accordance with clause (5) of Regulation 14 of these regulations, till the transmission system achieves the commercial operation.