State of Rajasthan - Act
Rajasthan Electricity Regulatory Commission (Generation of Electricity) Regulations, 2002
RAJASTHAN
India
India
Rajasthan Electricity Regulatory Commission (Generation of Electricity) Regulations, 2002
Rule RAJASTHAN-ELECTRICITY-REGULATORY-COMMISSION-GENERATION-OF-ELECTRICITY-REGULATIONS-2002 of 2002
- Published on 31 January 2003
- Commenced on 31 January 2003
- [This is the version of this document from 31 January 2003.]
- [Note: The original publication document is not available and this content could not be verified.]
1. Short title, Commencement and Scope.
2. Definitions.
- In these regulations, the words or expressions shall bear the same meaning as in the Rajasthan Powers Sector Reforms Act, 1999 and Rajasthan Electricity Regulatory Commission (Conduct of Business) Regulations, 2000.3. Consent of the Commission.
4. Furnishing of Information.
5. Procedure for grant of consent.
6. Compliance with rules and regulations.
7. Sale or wheeling of energy.
- Terms and conditions of sale of electricity to transmission or distribution licensee or for wheeling of energy on their system or sale of electricity to consumers shall be as mutually agreed by them except that the tariff for sale of electricity to consumers or for transmission of electricity shall be as determined by the Commission.8. Environmental clearances.
- The generating station shall abide by the emission standards set up by the Central/State Governments. The generator will obtain and keep valid all the required environmental and pollution clearances from the appropriate authority.9. Contravention of regulations.
- Notwithstanding any other action that Commission may take for contravention of any provision of these regulations, the Commission may, after issuing a show cause notice to the person concerned withdraw the consent granted under these regulations.Form AApplication Form for Grant of a consent under Rajasthan Electricity Regulatory Commission (Generation of Electricity) Regulations, 2002(Upto 1 M.W. Capacity)1. Name & address of the applicant.
2. Whether registered under Companies Act?
If yes a copy of Memorandum & Articles of Association be provided/enclosed.3. Details of existing connection taken from WNLs (if any)
4. Place & address where generating sets shall be installed.
5. Reasons for installing the proposed capacity of generating set(s) indicating whether it is stand by or will run regularly.
6. Details of proposed generating set(s)
7. Details of generating set (s) already installed (if any)
| S. No. | Capacity of set (s) | Specification of set (s) | Date of installation | |
| Rated | Derated | |||
| 1 | 2 | 3 | 4 | 5 |
1. Name & Address of the applicant.
2. Whether registered under Companies Act?
If yes, a copy of Memorandum & Articles of Association be provided/enclosed.3. Whether the generating station/CPP is required for existing or new proposed industry or sale to Licensee or consumer.
4. Type of Industry.
5. Location.
6. Details of existing connections taken from WNLs (if any)
7. Present & future power demand of the industry from Distribution Licensee.
8. Type of proposed plant
9. Capacity of proposed plant (M.W.)
10. Fuel to be used.
11. Total surplus power, over and above its own requirement.
12. Justification for setting up of CPP/ generating set.
13. Whether manufacturing process requires un-interrupted power supply?
Yes/No.14. Annual generating in Mwh envisaged (in M.U.)
15. Total annual energy requirement of the applicant (in M.U.)
16. Details of generating set (s) already installed (if any)
| S. No. | Capacity of set (s) | Specification of set (s) | Date of installation | |
| Rated | Derated | |||
| 1 | 2 | 3 | 4 | 5 |
1. Name & Address of the applicant.
2. Whether registered under Companies Act?
If yes, a copy of Memorandum & Articles of Association be provided/enclosed.3. Whether the generating station/CPP is required for existing or new proposed industry or sale to Licensee or consumer.
4. Type of Industry.
5. Location.
6. Details of existing connections taken from WNLs (if any)
7. Source of Supply of Fuel & its tie up.
8. Requirement of Fuel (MT).
9. Transportation of Fuel.
10. Zero Date.
11. Gestation Period (months).
12. Year of Commissioning.
13. Details of estimated Cost Incl. IDC.
Whether enviornment clearance obtained?if yes, copy of the same may be enclosed.14. Cost per M.W.
15. Generation Cost per Unit at Bus bar:
16. Present & Future Power demand of the industry from VVNL/Distribution Licencee.
17. Type of proposed plant
18. Capacity of proposed plant (M.W.)
Total capacity selected, keeping in view the19. Fuel to be used.
20. Total Surplus power, over and above its own requirement.
21. Justification for setting up of Generating Station/CPP.
22. Whether manufacturing process requires un-interrupted power supply? Yes/No
23. Whether the industry requires stringent tolerance in voltage & frequency?
24. Whether Generating Station/Captive plant is able to generate power at a price lower than the tariff charged by WNL/Distribution Licencee?
If yes furnish detailed calculation of cost of generation.25. If the capacity of the generating plant is higher than the contracted demand, please state reasons for such additional requirement.
26. If generating plant is proposed to be run in parallel with Grid.
27. Annual generation in Mwh envisaged (in Million units):
28. Total annual energy requirement of the applicant (in Million units):
29. New Project/Expansion of the existing generating plant (in case of phased programme of installation, year to year information be furnished):
30. Salient features relating to Technical details of Generator, Prime Mover. Exciter, Automatic Voltage Regulation, Protection, (to be separately attached):
31. Planned peak generation (in M.W.):
32. Any other relevant information for justification of the proposal.
Date :Place :SignatureName of the Applicant and designationEnclosures : Following documents are to be enclosed with the application.1. Demand draft of Rs.................towards processing fees.
2. Site map indicating location.
3. Technical particulars of Generating units.
4. Single line diagram (details of protection and interlocks should also be shown).
5. NOC/Renewal of NOC (if any) for CPP issued by Rajasthan Pollution Control Board.
6. Copy of approval from WNL, if any.
7. Details of calculation of cost of generation.
8. Consent from RVPN/VVNL for parallel operation of the plant (if any).
9. Memorandum & Articles of Association of the Company. (For companies registered under companies Act).
10. Undertaking.
11. Any other details (considered necessary by applicant).
Signature of the Applicant.UndertakingI/We under take to abide by the following conditions :1. That I/We shall maintain the Log Book in the form prescribed by the Commission.
2. That the supply arrangements from the Generating Set (s) shall be got checked and approved by the office of VVNL/ Licensee.
3. That I/We shall neither sell the energy generated by me/us nor shall supply the power/energy so generated even free of cost to others.
4. That the generating sets will not in any circumstances be in parallel with the power system of Licensee/VVNL without their permission.
5. That I/We shall operate the generating set(s) whenever called upon to do so by the Commission or Licensee for giving suitable relief to the Licensees system by meeting the demand of other consumers also.
6. I/We shall not run the generating set (s) in case my/our supply is dis-connected by Licensee for any violation of the rules or non-payment of electrical dues.
7. That the permission accorded by the Commission does not absolved me/us from obtaining any other approval necessary like the approval of the electrical inspector to the State Government etc.
8. I/We shall install the Generating Set(s) within a period of year(s) from the date of issue of sanction.
9. I/We shall send the monthly date of energy generation in the proforma prescribed by the Commission after commissioning of the generating set (s) to concerned authorities as directed by the Commission.
10. I/We shall comply/fulfil all the conditions stated above failing which the Commission will be free to withdraw this permission.
Place:Date:Signature....................Name:...........................Designation:....................Form 1Monthly/annual date of generationPeriod/month..........1. Name of generating company/ consent holder & address.
2. Location.
3. District.
4. Generation capacity installed.
5. Generation capacity in operation
| Generation Unit | Type (Steam/diesel/gas/hydro/wind) | Rated capacity, K.W. | Derated capacity since date K.W. | Date of commissioning |
| I. | ||||
| II. |
6. Peak Active generation, K.W.
7. Peak Reactive Generation, KVAr.
8. Peak Apparent Generation, KVA.
9. Gross Generation during the period, KWh.
10. Auxiliary Consumption during the period, KWh.
11. Net generation during the month/year, KWh.
12. Reactive energy generation during the period. KWArh.
13. Fuel consumption, (separately in respect of each fuel)
1. Name of Generating company/consent holder.
2. Date.
3. Rated Capacity K.W.
4. Derated capacity, KW.
5. Generation voltage, KV.
6. Other salient specifications, if any.
7. Date of commissioning.
8. (a) Fuel consumption for the day
| Unit No. 1 | Unit No. 2 | ||||
| Initial reading | Final reading | Consumption in lit/kg. # | Initial reading | Final reading | Consumption in lit/kg. |
8. (b) Units generated for the day
| Unit No. 1 | Unit No. 2 | ||||
| Initial reading | Final reading | Gross/net generation/consumption KWh | Initial reading | Final reading | Gross/net generation/consumption KWh |
9. Units generated, etc.
| Hrs. | Voltage | Ampere | Frequency | Power Factor | KW | KVAr | Kwh meter reading | KVARh meter reading | Remarks |
| 1/00HrsUnit-IUnit-II | |||||||||
| 2.00 Hrs.Unit-IUnit-II | |||||||||
| 24.00Unit-IUnit-II |
| Signature of Operator (s) | Signature of Supervisor | |
| Shift-1 | ||
| Shift-2 | ||
| Shift-3 |