[Cites 0, Cited by 0] [Section 58] [Entire Act]

State of Rajasthan - Subsection

Section 58(1) in Rajasthan Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2009

(1)The generating company may be required to demonstrate the declared capability of its generating station as and when asked by the State Load Despatch Centre. In the event of the generating company failing to demonstrate the declared capability, the capacity charges due to the generator shall be reduced as a measure of penalty.