[Cites 0, Cited by 0] [Section 15] [Entire Act]

Union of India - Subsection

Section 15(3) in Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009

(3)The long-term access agreement shall contain the date of commencement of long-term access, the point of injection of power into the grid and point of drawal from the grid and the details of dedicated transmission lines, if any, required.