Union of India - Section

Section 15 in Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009

15. Execution of Long-term Access Agreement.

- [(1) The applicant shall sign an agreement for long-term access with the Central Transmission Utility in case long-term access is granted by the Central Transmission Utility, in accordance with the provision as may be made in the detailed procedure.
(2)While seeking long-term access to an inter-State Transmission licensee, other than the Central Transmission Utility, the applicant shall sign a tripartite long-term access agreement with the Central Transmission Utility and the inter-State Transmission licensee.
(3)The long-term access agreement shall contain the date of commencement of long-term access, the point of injection of power into the grid and point of drawal from the grid and the details of dedicated transmission lines, if any, required.
(4)In case augmentation of transmission system is required, the long-term access agreement shall contain the time line for construction of the facilities of the applicant and the transmission licensee, the bank guarantee required to be given by the applicant and other details in accordance with the detailed procedure.] [Substituted by Notification No. L-1/(3)/2009-CERC, dated 9.1.2019 (w.e.f. 7.7.2009).]