36.
The norms of operation as given hereunder shall apply to thermal generating stations:| TPS-I | 72% |
| TPS-II Stage I & II | 75% |
| TPS-I (Expansion) | 80% |
| Bokaro TPS | 75% |
| Chandrapura TPS | 75% |
| Durgapur TPS | 74% |
| Assam GPS | 72% |