Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 14, Cited by 0]

Madhya Pradesh High Court

Mahakaushal Sugar And Power Industries ... vs The State Of Madhya Pradesh on 1 February, 2018

 HIGH COURT OF MADHYA PRADESH : JABALPUR

SINGLE BENCH : JUSTICE MS.VANDANA KASREKAR

             WRIT PETITION NO.16160/2017

          Mahakaushal Sugar & Power Industries Ltd
                              Vs.
                   State of M.P. and others

      Shri Rajesh Pancholi, learned counsel for the petitioner.
      Shri P.K. Kaurav, learned senior counsel with Shri
      Aditya Khandekar, learned counsel for respondents
      No.2, 3 and 5.
      Shri Anoop Nair, learned counsel for respondent No.6.


                             ORDER

(01/02/2018) The petitioner has filed the present writ petition for quashing of order dated 31/08/2017 as well as for directing the respondents to purchase electricity from petitioner's Bagasse based Co-generation Power Plant at Narsinghpur by executing the power purchase agreement in accordance with the tariff order of MPERC and also to pay compensation/damages and some other reliefs have also been prayed for.

2. Respondents No.2, 3 and 5 have also filed preliminary objection stating that the petitioner has a remedy of filing a dispute before the State Commission under Section 86 (f) of the Electricity Act, 2003 (hereinafter referred to as 'the Act of 2 2003'). Second preliminary objection which is taken by the respondents is that the petitioner is a member of the Sugar Association of M.P.. This association had filed a petition in pursuance of the order dated 29/05/2017 passed by the appellate tribunal for electricity in Appeal No.144/2017 under Section 86(1)(e) and (86(1)(b) in Petition No.29/2017 (Sugar Mills Association Madhya Pradesh Vs. M.P. Power Management Co. Ltd. before M.P. Electricity Regulatory Commission praying for the same relief and this fact has been deliberately suppressed by the petitioner in para-2 of the writ petition and, therefore, deserves to be dismissed on the ground of suppression of material facts. He relied upon the judgment passed by the Apex Court in the case of Gujarat Urja Vikas Nigam Ltd. Vs. Essar Power Ltd., reported in (2008) 4 SCC 755.

3. Learned counsel for the respondents argues that the word 'generating company' has been defined under Section 2(28) of the Electricity Act and as per this definition, 'generating company' means any company or body corporate or association which owns or operates or maintains a generating station. The word " licensee" is defined under 3 Section 2(39) of the Act which means a person who has been granted a licence under section 14. On the basis of these definitions, learned counsel for the respondents submits that the case of the petitioner, therefore, squarely falls under Section 86(1) (f) of the Act, therefore, the petitioner should have approached to the State Commission. He further submits that against the order passed by the M.P.E.R.C., the petitioner has remedy of filing an appeal to the appellate tribunal under Section 127 of the Act of 2003. Thus, as the petitioner is having statutory remedy, the present writ petition deserves to be dismissed on this count alone.

4. Learned counsel for the petitioner argues that the preliminary objection raised by the respondents regarding maintainability of the writ petition is misleading, flimsy and fallacious. Firstly, he submits that there has to be a written, proper and concluded written contract for which dispute can be adjudicated and sent for arbitration for decision. He submits that in the instant case there is no written executed contract and there is no relationship, as such in absence of agreement, MPERC gets jurisdiction only in respect of the disputes arising from the executed contract or old contract. 4 He also submits that in the present case as there is no written contract between the parties, therefore, in view of Section 2(b) of the Arbitration and Conciliation Act, 1996, the existence of written arbitration agreement is sine qua non for a dispute capable of adjudication by the arbitrator. So far as the judgment relied upon by learned counsel for the respondents in the matter of Gujarat Urja Vikas Nigam Ltd. (supra) is concerned, learned counsel for the petitioner submits that the said judgment would not be applicable in the present case as there is no concluded written contract between the parties. Learned counsel for the petitioner relied on the definition of generation station as given under Section 2(3) of the Act of 2003. He relied upon the judgment passed by the Apex Court in the case of Whirlpool Corporation vs Registrar Of Trade Marks, Mumbai & others reported in (1998) 8 SCC 1 and submits that the writ petition is maintainable.

5. Heard learned counsel for the parties on preliminary objections.

6. Section 86 of the Act of 2003 provides for functions of the State Commission. Clause (f) of sub-section (1) of 5 Section 86 provides for adjudicate upon the disputes between the licensees, and generating companies and to refer any dispute for arbitration. Word 'licensee' and 'generating company' is defined under Sections 2(28) and 2(39) which reads as under :

           "2(28)         "generating company" means
           any company or body corporate or
           association     or    body   of   individuals,

whether incorporated or not, or artificial juridical person, which owns or operates or maintains a generating station;

           2(39)          " licensee" means a person
           who has been granted a licence under
           section 14."



7. As per the said definition, generating company means a company which owns or operates or maintains a generating station. Licensee means a person who has been granted a licence under section 14 of the Act of 2003. The said definition does not refer that there should be a concluded contract or agreement between the parties. Any dispute 6 between the licensee and generating company can be referred to the State Commission and it does not mean that before referring the matter to the State Commission, there should be a concluded contract between the parties. The petitioner company has established their factory and, therefore, it comes under the definition of generating company. It is also to be noted that the Apex Court in the case of Gujarat Urja Vikas Nigam Ltd. (supra), in para 60 has held as under :

"60. In the present case, it is true that there is a provision for arbitration in the agreement between the parties dtd. 30.5.1996. Had the Electricity Act, 2003 not been enacted, there could be no doubt that the arbitration would have to be done in accordance with the Arbitration and Conciliation Act, 1996. However, since the Electricity Act, 2003 has come into force w.e.f. 10.6.2003, after this date all adjudication of disputes between licensees and generating companies can only be done by the State Commission or the arbitrator (or arbitrators) appointed by it.
After 10.6.2003 there can be no adjudication of dispute between licensees 7 and generating companies by anyone other than the State Commission or the arbitrator (or arbitrators) nominated by it. We further clarify that all disputes, and not merely those pertaining to matters referred to in clauses (a) to (e) and (g) to
(k) in Section 86(1), between the licensee and generating companies can only be resolved by the Commission or an arbitrator appointed by it. This is because there is no restriction in Section 86(1)(f) about the nature of the dispute."

8. As per this judgment, after coming into force of the Electricity Act, 2003, all adjudication of disputes between licensees and generating companies can only be done by the State Commission or by the Arbitrator appointed by it. After 10/06/2003 there can be no adjudication of dispute between licensees and generating companies by anyone other than State Commission. Thus, as per the said judgment, after 10/06/2003, all disputes are to be adjudicated by the State Commission. The judgment relied upon by learned counsel for the petitioner relates to appointment of arbitrator under the Arbitration and Conciliation Act in which written 8 agreement between the parties is essential. However, in the present case, there is no such requirement and any disputes between the licensee and generating company can be decided by the State Commission. In the present case, the petitioner is a generating company and respondents No.2, 3 and 5 are the licensees and, therefore, the dispute between them is covered under Section 86(1) (f) of the Act of 2003. Now, in the present case, it is also to be noted that the petitioner has already approached before the M.P.E.R.C., therefore, the association and the M.P. E.R.C. has already passed the order which is under challenged before the Tribunal. Thus, in view of aforesaid, as the petitioner has alternate remedy of raising dispute before the State Commission, this Court does not find any reason to interfere into the matter.

9. Accordingly, the writ petition is dismissed without any order as to cost.

(Ms. Vandana Kasrekar) JUDGE ts Digitally signed by TULSA SINGH Date: 2018.02.01 17:13:01 +05'30' 9