[Cites 0, Cited by 0] [Section 44] [Entire Act]

State of Rajasthan - Subsection

Section 44(3) in Rajasthan Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2009

(3)Where the tariff is being determined for stage or Unit of a generating station, the Generating Company shall adopt a reasonable basis for allocation of capital cost relating to common facilities and allocation of joint and common costs across all stages or Units, as the case may be:Provided that the Generating Company shall maintain an Allocation Statement providing the basis for allocation of such costs, and submit such statement to the Commission along with the application for determination of tariff.