Union of India - Subsection

Section 15(4) in Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-State Transmission and related matters) Regulations, 2009

(4)In case augmentation of transmission system is required, the long-term access agreement shall contain the time line for construction of the facilities of the applicant and the transmission licensee, the bank guarantee required to be given by the applicant and other details in accordance with the detailed procedure.] [Substituted by Notification No. L-1/(3)/2009-CERC, dated 9.1.2019 (w.e.f. 7.7.2009).]