[Cites 0, Cited by 0]
[Entire Act]
State of Tamilnadu - Section
Section 2 in Tamil Nadu Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2005
2. Definitions.
- (i) In these Regulations unless the context otherwise requires(a)'Act' means the Electricity Act 2003 (Central Act of 36 of 2003)(b)'Additional Capitalisation' means the capital expenditure actually incurred after the date of commercial operation of the generation station / transmission system and admitted by the Commission after prudence check subject to regulation 19;(c)'Authority' means Central Electricity Authority referred to in Section 70 of the Act;(d)'Allotted Transmission Capacity' means the power transfer in MW between the specified point of injection and point of drawal allowed to a long-term open access customer on the intra-state transmission system under the normal circumstances and the expression "allotment of transmission capacity" shall be construed accordingly;(e)'Auxiliary Energy Consumption' or 'AUX' in relation to a period means the quantum of energy consumed by auxiliary equipment of the Generating Station and transformer losses within the Generating Station, and shall be expressed as a percentage of the sum of gross energy generated at the generator terminals of all the units of the Generating Station;(f)'Availability' in relation to a thermal Generating Station for any period means the average of the daily average declared capacities (DCs) for all the days during that period expressed as a percentage of the installed capacity of the Generating Station minus normative auxiliary consumption in MW, and shall be computed in accordance with the following formula:N∑ (DC1)| Availability = 100000 x| i-1N x 1C(100 - AUXn)| Where, |
| PLF = 10000 x| ∑ (S.G1)N x 1Cx100 - AUXn)% where, |