Legal Document View

Unlock Advanced Research with PRISMAI

- Know your Kanoon - Doc Gen Hub - Counter Argument - Case Predict AI - Talk with IK Doc - ...
Upgrade to Premium
[Cites 17, Cited by 0]

Delhi High Court - Orders

Mr. Amrit Singh vs Bses Rajdhani Power Ltd. (Brpl) And Anr on 24 July, 2024

Author: Purushaindra Kumar Kaurav

Bench: Purushaindra Kumar Kaurav

                                    $~104
                                    *           IN THE HIGH COURT OF DELHI AT NEW DELHI
                                    +           W.P.(C) 10079/2024 & CM APPL. 41295/2024
                                                MR. AMRIT SINGH                                                                       .....Petitioner
                                                                                      Through:                 Mr.Rahul Bajaj and Mr.Amar Jain,
                                                                                                               Advs.

                                                                                      versus

                                                BSES RAJDHANI POWER LTD. (BRPL) AND ANR
                                                                                            .....Respondents
                                                             Through: Mr.Raghav Awasthi and Mr.Rishab
                                                                      Raj Jain, SC for R-1.

                                    CORAM:
                                    HON'BLE MR. JUSTICE PURUSHAINDRA KUMAR KAURAV
                                                      ORDER

% 24.07.2024

1. The petitioner has approached this Court praying for the following reliefs:-

"A. Pass an order issuing a writ, order or direction quashing and setting aside the Impugned Notice dated 21.07.2023 (Annexure P-10) and the consequent disconnection of electricity dated 19.08.2023.
B. Direct the Respondent No. 1 to restore the Petitioner‟s electricity connection and not disconnect the same in the future without a valid ground.
C. Pass any other order or direction which this Hon‟ble Court may deem fit in the interests of justice, equity and good conscience."

2. Shorn of unnecessary details, the property in question was entangled in a civil suit related to injunction and stay was operating in the said suit. Thereafter, when the petitioner made a request for a temporary electricity connection before the respondent-DISCOM, the same was rejected on the This is a digitally signed order.

The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 30/07/2024 at 20:39:30 ground that there was no NOC from co-owners of the property. Subsequently, the stay was vacated in the civil suit and the petitioner again made an application for a temporary electricity connection before the respondent-DISCOM and his application got accepted.

3. Thereafter, on 21.07.2023, respondent-DISCOM issued a fresh disconnection notice, disconnecting the electricity supply of the petitioner stating that the property is entangled in the civil dispute and in absence of any express orders from the Court, the respondent-DISCOM cannot restore the connection. Aggrieved thereto, the petitioner has approached this Court to ventilate his grievance.

4. Learned counsel for the petitioner submits that there was a stay operating against the petitioner, however, that stay stood vacated on 22.05.2023 and as of now, there is no legal impediment for the respondent- DISCOM to provide the electricity connection. He further submits that the right to air, water and electricity are the most essential fundamental rights and as per the provisions of the Electricity Act, 2003 (hereinafter 'Act of 2003'), more specifically in light of Section 43, once an occupier of the accommodated premises makes an application, the concerned DISCOM is under an obligation to immediately extend the electricity connection. He, therefore, submits that in the instant case, the sole reason for the denial of the electricity connection appears to be an ongoing civil dispute between the parties.

5. Learned counsel for the petitioner has also placed reliance on a decision of the Supreme Court in the case of Dilip v. Satish1, the decision of 1 2022 SCC OnLine SC 810 This is a digitally signed order.

The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 30/07/2024 at 20:39:30 this Court in the case of Sanjana v. BSES Yamuna Power Ltd.2, and the decision of the High Court of Gujarat in the case of Yogesh Lakhmanbhai Chovatiya v. PGVCL3. He, therefore, submits that the petitioner is not required to approach any other alternate mechanism, rather he can invoke the writ jurisdiction under Article 226 of the Constitution of India in case of encroachment of his fundamental rights.

6. I have thoughtfully considered the submissions made by learned counsel appearing for the parties.

7. So far as the principle laid down in the case of Dilip (supra), Sanjana (supra) and Yogesh Lakhmanbhai (supra) is concerned, there remains no dispute with regard to the proposition of law which has been stated in the aforesaid decision. In the decision relied upon by the learned counsel in the case of Sanjana (supra), the Court, while taking into consideration certain factual aspects as mentioned in paragraphs nos.8 and 9 therein, had come to the conclusion that the petitioner therein was found to be residing in House No.545 and she satisfied that the aforesaid aspect is not otherwise proved by any other contesting party and accordingly, directions were given.

8. At this juncture, it is significant to take note of the decision passed by this Court in the case of Ram Kishan v. N.D.P.L.4 While dealing with a dispute regarding an electricity bill, the Court in paragraph no.10, has recorded a note of caution in entertaining petitions where an alternate statutory remedy exists in the following words:-

'If this Court entertains writ petition regarding disputes relating to electricity, water, telephones bills, etc. even though there is an alternative remedy provided by the statute before some Forum, this 2 2021 SCC OnLine Del 4156 3 2022 SCC OnLine Guj 1086 4 2005 SCC OnLine Del 1281 This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 30/07/2024 at 20:39:31 Court will be flooded with lacs and lacs of such writ petitions and will be doing no other work except deciding such writ petitions'.

9. In paragraph nos.14 to 19 in the case of Ram Kishan (supra), it has been further held as under:-

"14. Learned Counsel for the appellant submitted that disputes regarding the tariff cannot be raised before the Forum or the Ombudsman as they are creatures of the statute. We are of the opinion that while the consumer cannot challenge the validity of the tariff before these bodies, the Forum and Ombudsman can certainly go into the question of interpretation of the tariff. There is a clear distinction between interpretation of a tariff and validity of a tariff.
15. Some electricity consumers may have the grievance that an exorbitant bill may be pressed against them with the threat of disconnection of electricity supply. We are of the opinion that both the Forum under Section 42(5) as well as Ombudsman under Section 42(6) have inherent powers of passing interlocutory orders pending the decision of the representation before them including interlocutory orders for stay of the bills apart from the specific power under Regulation 9(8) of the Regulations contained in the notification dated 11.3.2004.
16. As regards the representation before the Ombudsman under Section 42(6), there is a requirement of pre-deposit of 1/3rd of the amount assessed by the Forum in cash or by way of bank draft.
17. Learned Counsel for the appellant submitted that this may cause hardship but we are afraid we cannot interfere in this matter as the requirement of such pre-deposit before the Ombudsman amounts to delegated legislation, with which we cannot interfere.
18. Learned Counsel for the appellant then submitted that there is no mechanism to implement the orders of the Forum under Section 42(5) or Ombudsman under Section 42(6) and he has submitted that in many cases the orders of the Forum and Ombudsman are not complied with by the electricity department. This has been denied by the learned Counsel for the respondent, but in any case we clarify that it is implicit in Sections 42(5) and 42(6) that the orders of the Forum and Ombudsman have to be complied with by the parties (including the consumer as well as the electricity department) unless the said order has been stayed or set aside by this Court or the Supreme Court.
This is a digitally signed order.
The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 30/07/2024 at 20:39:31
19. The appeal is disposed of with liberty to the appellant to approach the Forum under Section 42(5) and the Ombudsman under Section 42(6), if he is aggrieved by the order of the Forum. We also make it clear that the Forum as well as Ombudsman can devise their own procedures and mechanisms for adjudication of the complaints of the consumers. However, we make it clear that although there is no specific provisions about the procedures to be followed by the Forum and Ombudsman, these authorities must follow the rules of the natural justice."

10. Admittedly, in the instant case, neither the petitioner has approached the Consumer Grievance Redressal Forum ['CGRF'] as envisaged under Section 42 (5) of the Act of 2003, nor he has approached the Ombudsman as provided under Section 42 (6) of the Act of 2003.

11. Undoubtedly, the grievance which has been put forth by the petitioner can still be examined by the CGRF in an effective manner. It is also equally well settled that a writ petition is a discretionary remedy which can be declined if there is an equally efficacious alternate remedy.

12. The aforesaid position of law has been settled by the Supreme Court in a series of judicial pronouncements. The decision of the Supreme Court in the case of M/S Radha Krishan Industries v. The State Of Himachal Pradesh5 vividly encapsulates the aforesaid position and the relevant extract of the said decision is culled out as under:-

"The principles of law which emerge are that:
(i) The power under Article 226 of the Constitution to issue writs can be exercised not only for the enforcement of fundamental rights, but for any other purpose as well;
(ii) The High Court has the discretion not to entertain a writ petition.

One of the restrictions placed on the power of the High Court is where an effective alternate remedy is available to the aggrieved person;

5

AIR 2021 SC 2114 This is a digitally signed order.

The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 30/07/2024 at 20:39:31

(iii) Exceptions to the rule of alternate remedy arise where (a) the writ petition has been filed for the enforcement of a fundamental right protected by Part III of the Constitution; (b) there has been a violation of the principles of natural justice; (c) the order or proceedings are wholly without jurisdiction or (d) the vires of a legislation is challenged;

(iv) An alternate remedy by itself does not divest the High Court of its powers under Article 226 of the Constitution in an appropriate case though ordinarily, a writ petition should not be entertained when an efficacious alternate remedy is provided by law;

(v) When a right is created by a statute, which itself prescribes the remedy or procedure for enforcing the right or liability, resort must be had to that particular statutory remedy before invoking the discretionary remedy under Article 226 of the Constitution. This rule of exhaustion of statutory remedies is a rule of policy, convenience and discretion; and

(vi) In cases where there are disputed questions of fact, the High Court may decide to decline jurisdiction in a writ petition. However, if the High Court is objectively of the view that the nature of the controversy requires the exercise of its writ jurisdiction, such a view would not readily be interfered with."

13. In the case of Maharashtra Electricity Regulatory Commission v. Reliance Energy Ltd.6, the Supreme Court held that since the Act of 2003 has created CGRF, all the individual grievances of consumers have to be raised before such forum only. While affirming the decision passed by this Court in Suresh Jindal v. BSES Rajdhani Power Ltd. &Ors.7 and Dheeraj Singh v. BSES Yamuna Power Ltd.8, wherein, it was held that the CGRF and the Ombudsman has the authority to pass an interim order as well, the Supreme Court further held that Sections 42(5) and 42(6) provide a complete machinery for redressal of grievances of the consumers. The Supreme Court in the said case remitted the matter back to the CGRF for adjudication on 6 (2007) 8 SCC 381 7 (2006) SCC OnLine Del 206 8 (2006) 127 DLT 525 (DB) This is a digitally signed order.

The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 30/07/2024 at 20:39:31 merits. The relevant paragraphs of the decision in Reliance Energy (supra) are extracted as under:-

"33. As per the aforesaid provision, if any grievance is made by a consumer, then they have a remedy under Section 42(5) of the Act and according to sub-section (5) every distribution licensee has to appoint a forum for redressal of grievances of the consumers. In exercise of this power the State has already framed the Maharashtra Electricity Regulatory Commission (Consumer Grievance Redressal Forum and Ombudsman) Regulations, 2003 (hereinafter referred to as "the 2003 Regulations") and created Consumer Grievance Redressal Forum and Ombudsman. Under these 2003 Regulations a proper forum for redressal of the grievances of individual consumers has been created by the Commission. Therefore, now by virtue of sub-section (5) of Section 42 of the Act, all the individual grievances of consumers have to be raised before this forum only. In the face of this statutory provision we fail to understand how could the Commission acquire jurisdiction to decide the matter when a forum has been created under the Act for this purpose. The matter should have been left to the said forum. This question has already been considered and decided by a Division Bench of the Delhi High Court in Suresh Jindal v. BSES Rajdhani Power Ltd. [(2006) 132 DLT 339 (DB)] and Dheeraj Singh v. BSES Yamuna Power Ltd. [Ed. : (2006) 127 DLT 525 (DB)] and we approve of these decisions. It has been held in these decisions that the forum and ombudsman have power to grant interim orders. Thus a complete machinery has been provided in Sections 42(5) and 42(6) for redressal of grievances of individual consumers. Hence wherever a forum/ombudsman have been created the consumers can only resort to these bodies for redressal of their grievances. Therefore, not much is required to be discussed on this issue. As the aforesaid two decisions correctly lay down the law when an individual consumer has a grievance he can approach the forum created under sub-section (5) of Section 42 of the Act.
34. In this connection, we may also refer to Section 86 of the Act which lays down the functions of the State Commission. Sub-section (1)(f) of the said section lays down the adjudicatory function of the State Commission which does not encompass within its domain complaints of individual consumers. It only provides that the Commission can adjudicate upon the disputes between the licensees and generating companies and to refer any such dispute for arbitration. This does not include in it an individual consumer. The proper forum for that is Section 42(5) and thereafter Section 42(6) read with the Regulations of 2003 as referred to hereinabove."

This is a digitally signed order.

The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 30/07/2024 at 20:39:31 [emphasis supplied]

14. Notably, the decision of this Court in the cases of Abhijit Anand v. Chairman Delhi Electricity Regulatory Commission9 and Ashok Yadav v. BSES Rajdhani Power Limited10 also aid to the similar position of law as has been rendered in the case of Ram Kishan (supra).

15. It is thus safely discernible from the aforementioned decisions that the submissions which have been made by the petitioner in the instant petition can also be looked into by the concerned authority which is provided under the Act of 2003.

16. In view of the aforesaid, leaving all contentions open to be raised before the appropriate authority, the Court is not inclined to entertain the instant petition and the same is dismissed alongwith pending applications.

17. At this stage, learned counsel for the petitioner prays that the concerned authority be directed to decide his application as expeditiously as possible.

18. In view of the facts and circumstances, the Court deems it appropriate to direct the concerned authority to decide the petitioner's application as expeditiously as possible.

PURUSHAINDRA KUMAR KAURAV, J JULY 24, 2024/MJ 9 W.P.(C) 7952/2024 10 W.P.(C) 9644/2023 This is a digitally signed order.

The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above. The Order is downloaded from the DHC Server on 30/07/2024 at 20:39:32