State of Rajasthan - Act
The Rajasthan Water Supply Rules
RAJASTHAN
India
India
The Rajasthan Water Supply Rules
Rule THE-RAJASTHAN-WATER-SUPPLY-RULES of 1967
- Published on 1 July 1967
- Commenced on 1 July 1967
- [This is the version of this document from 1 July 1967.]
- [Note: The original publication document is not available and this content could not be verified.]
1. Short title and extent.
2. Definitions.
3. Public Supply.
Part II – Private Supply
1. Cubical contents of the building to be built/rebuilt according to plan purposes of assessment of water charges are............. cft.
2. Meter is not available and will provided against payment of Rs. ....... by the applicant.
3. Meter is not available, charges may be made on the basis of cubical contents of the building.
4. The time required for carrying out the building work is approved/not approved. It should be upto............. only.
(clause not applicable to be struck off).Assistant Engineer.(To be Filled in Executive Engineer's Office)1. The applicant may be asked to deposit Rs. .......... for providing a meter.
2. Estimates demand for water charges calculated on the cubical contents comes to...............
3. Additional Security of Rs. ..........may be demanded.
SD/Water Rate Supdt.(Executive Engineer's Orders.)Form W-3ToThe Executive Engineer,Water Works.....................I have carried out the installation work in the House/premises belonging to Shri........... which is taken on rent by Shri........ and remit herewith the amount as detained under:-| Estimated amount | Rs. |
| Connection Fee | Rs. |
| Security | Rs. |
| Tape | Nos. |
| Showers | Nos. |
| _____________ | Nos. |
| Kindly issue necessary order for connection. |
| Executive Engineer | |
| Date | |
| Order No. ............... | for opening Connection No. |
| Issued on ............... |
| Overseer. | |
| Approval of application. | |
| AEN | Sanctioned against deposit. |
| Amount deposited as per Cr. No. | |
| Dated ............... | |
| Executive Engineer | |
| Drawn | Connection No.........given |
| on dated ............. | |
| File. | |
| Executive Engineer. | Assistant Engineer. |
| Executive Engineer |
1. Income Tax Clearance Certificate.
2. Certificate from the Bank regarding financial status.
3. Certificate of the technician.
I agree to abide by all rules and regulations.Yours faithfullySignature........Address..........Dated............Assistant Engineer's Report After InspectionAssistant EngineerExecutive Engineer's RecommendationExecutive EngineerSanctioning authorities Approval--------------------------------------------------Licence fee deposited as per C.R. No. ....... dated...........Cashier.All concerned to note.Executive EngineerDated.........Appendix IIWater Supply Regulations1. All work connected with the making, alteration, extension or repair of private connection shall be carried out, subject to the examination of Assistant Engineer by the person or persons whom the Department may, from time to time appoint as its licenced plumber or plumbers, who shall enter into an agreement with the Department for a period of one year.
2. No tap shall be allowed to project outside any premises nor shall any tap be fixed to such a position as to be available for use by the public or in close proximity to any, priky drain or other place where injuries gases are likely to be produced.
3. No connection shall be made by a licenced plumber between a communication pipe and supply pipe except in the presence of an office duly authorised in this behalf by the Assistant Engineer.
4. Every boiler for generating steam be supplied with water from a cistern and not directly from service pipe and every cistern shall be provided with bell value, detective or warning pipe and proper means of access and inspections.
5. The pipes and fittings of house service connections shall be exact duplicates of the samples deposited in the office of the Assistant Engineer, so that the part may be interchangeable and shall consist of five sections;
6. The dimensions of ferrule, interior pipes and taps for water shall be of the following relative sizes only, except when a connection is taken for supply in bulk.
| Diameter of ferrule | Diameter of pipes | Inside house | Size or taps or stop cock |
| Lower floor | Upper floor | ||
| Inches | Inches | Inches | Inches |
| – | – | – | – |
| – | – | – | – |
| – | – | – | – |