Section 6(1)(b) in Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2019
(b)Where the associated transmission system has not achieved the commercial operation as on the date of commercial operation of the concerned generating station or unit thereof (which is not before the SCOD of the transmission system), the transmission licensee shall make alternate arrangement for the evacuation from the generating station at its own cost, failing which, the transmission licensee shall be liable to pay the transmission charges to the generating company as determined by the Commission, in accordance with clause (5) of Regulation 14 of these regulations, till the transmission system achieves the commercial operation.