State of Andhra Pradesh - Section

Section 6 in Andhra Pradesh Electricity Regulatory Commission (Interim Balancing and Settlement Code) Regulation, 2006

6. Revenue of Wheeling Schedule.

- In case of any system constraint, the SLDC/DISCOM may modify the schedules of Open Access Generators, Scheduled Consumers and/or the OA Consumers, as the case may be, at any time in accordance with the Grid Code and the Open Access Regulation, which shall be conveyed to them. Compliance with the instructions of SLDC shall not be reckoned as a deviation by the concerned Generator/Consumer from the schedule. The Open Access Generator, Scheduled Consumer or OA Consumer, shall not, however, be entitled to revise a wheeling schedule during the course of a day.