State of Andhra Pradesh - Act
Andhra Pradesh Electricity Regulatory Commission (Interim Balancing and Settlement Code) Regulation, 2006
ANDHRA PRADESH
India
India
Andhra Pradesh Electricity Regulatory Commission (Interim Balancing and Settlement Code) Regulation, 2006
Act 2 of 2006
- Published on 1 January 2006
- Commenced on 1 January 2006
- [This is the version of this document from 1 January 2006.]
- [Note: The original publication document is not available and this content could not be verified.]
1. Short title, Commencement and interpretation.
2. Definitions.
- In this Regulation, unless the context otherwise requires:-3. Extent of Application.
- The Interim Balancing & Settlement Code set out in this Regulation shall apply to Open Access Generators, Scheduled Consumers and OA Consumers.4. Scheduling.
- 4.1 Each Open Access Generator, Scheduled Consumer and OA Consumer shall provide a Wheeling Schedule in the format as at Appendix - 1(a), to the SLD/D1SCOM for each fifteen (15) minute time block for a day, on a day-ahead basis by 10:00 a.m. on the day preceding the commencement of the first time block for which the wheeling of energy is scheduled, with a copy each to the State Transmission Utility (APTRANSCO) and the concerned DISCOM:Provided that an Open Access Generator, Scheduled Consumer and OA Consumer requiring to wheel electricity from more than one generating station with the interface points located at different locations (with separate metering at each entry point) shall provide separate wheeling schedule for the entry point(s) of each generating station:Provided also that the Wind-based or Mini-hydel Open Access Generators shall not be required to provide a day-ahead wheeling schedule and the actual electricity injected by them shall be deemed to be the scheduled energy.5. Allocation of Capacity by OA Generators.
- 5.1 The sum total of the Capacity allocations by an OA Generator for any time block to all the Scheduled Consumers and OA Consumers shall not exceed the available capacity from his generating plant being not higher than the installed capacity or contracted Open Access capacity, whichever is lower.6. Revenue of Wheeling Schedule.
- In case of any system constraint, the SLDC/DISCOM may modify the schedules of Open Access Generators, Scheduled Consumers and/or the OA Consumers, as the case may be, at any time in accordance with the Grid Code and the Open Access Regulation, which shall be conveyed to them. Compliance with the instructions of SLDC shall not be reckoned as a deviation by the concerned Generator/Consumer from the schedule. The Open Access Generator, Scheduled Consumer or OA Consumer, shall not, however, be entitled to revise a wheeling schedule during the course of a day.7. Meter Reading, Energy Accounting and Settlement.
- 7.1 SLDC shall undertake the accounting of energy for each time block on monthly basis with the assistance of the Energy Billing Centre (EBC) of the State Transmission Utility (STU) in respect of the Open Access Generators, Scheduled Consumers and the OA Consumers who are connected to the transmission system, In respect of the Open Access Generators, Scheduled Consumers and the OA Consumers who are connected to the distribution system, it is the EBC that shall be responsible for energy accounting and settlement in co-ordination with the DISCOMs.8. Settlement of Energy/demand at exit Point in Respect of Scheduled Consumer.
- 8.1 The Scheduled energy (in kWh) at exit point shall be calculated for each time block from the scheduled capacity (kW) at the Exit point, as provided in the wheeling schedule, by multiplying it with the period of time block in hours.9. Settlement of Energy at exist point in Respect of OA Consumers.
- 9.1 The Scheduled Energy at Exist point of an OA Consumer shall be calculated from the Scheduled capacity from an OA Generator at the Exist point for each time block as provided in clause 8.1 above.10. Settlement for OA Generators at Entry Point.
- 10.1 The excess drawals of energy and demand by Scheduled Consumers on account of under-generation by the Generator for each time block, shall be deemed to have been drawn from the DISCOM. The energy and demand charges for such excess drawls shall be paid for by the Scheduled Consumer in accordance with the proviso to clause 8.3 and as per clause 8.4 respectively.11. Levy of Surcharge and Additional / Surcharge.
- Each Open Access Generator, Scheduled Consumer and OA Consumer shall, in addition to the tariff and other charges mentioned in the preceding clauses, also be required to pay, wherever applicable, the surcharge in accordance with the provisions of the Open Access Regulation as also the applicable additional surcharge, if any, under Section 42 (4) of the Act.12. Banking.
- 12.1 No generators other than the Wind and Mini Hydel power generators shall be allowed the facility of banking the electricity generated by them:Provided that in the case of existing users of wheeling facility, the energy already banked as per the subsisting agreements as on the date of coming into force of this Regulation, shall be allowed to be wheeled as hithertofore till the expiry of the balance period available for utilization of the banked energy:Provided, however, that in the case of generators whose cases are pending appeals in the Honble High Court of Andhra Pradesh and/or the Honble Supreme Court, this provision shall be applicable subject to the final decision of the High Court and/or the Supreme Court, as the case may be.13. Dispute Resolution.
- All disputes and complaints shall be referred to the SLDC for resolution, which shall not decide a matter without first affording an opportunity to the concerned parties to represent their respective points of view. The decisions of the SLDC shall be binding on all parties.14. Issue of Orders and Practice Directions.
- Subject to the provisions of the Act. the A.P. Electricity Reform Act, 1998, and this Regulation, the Commission may, from time to time, issue orders and practice directions in regard to the implementation of this Regulation, the procedure to be followed and other matters, which the Commission has been empowered by this Regulation to specify or direct.15. Power To Remove Difficulties.
- In case of any difficulty in giving effect to any of the provisions of this Regulation, the Commission may be general or special order, issue appropriate directions to Open Access Generators, Scheduled Consumers, OA Consumers, Transmission Licensee(s), Distribution licensee(s) etc., to take suitable action, not being inconsistent with the provisions of the Act, which appear to the Commission to be necessary or expedient for the purpose of removing the difficulty.16. Saving.
- Nothing contained in this Regulation shall affect the rights and privileges of the Consumers under any other law for the time being in force, including the Consumer Protection act, 1986 (68 of 1986).17. Power to Amend.
- The Commission may from time to time and, vary, alter, suspend, modify, amend or repeal any provisions of this Regulation.Appendix - 1 (A)Format for the Day-ahead Wheeling Schedule for each 15 minute time block of the day| Date: | Declared capacity for the day |
| Name of the Generator; | {| |
| Time block | Available Capacity |
| DISCOM | Name of the Consumer | Voltage level of Exist point | Time Blocks | Allocated capacity at Entry point Kw | Net capacity at Exit point kW |
| Date: | Declared capacity for the day |
| Name of the Generator: Z in SPDCLEntry point voltage: 132 kV | {| |
| Time block | Available Capacity |
| DISCOM | Name of the consumer | Voltage level of Exit point | Time Blocks | Allocated capacity at Entry point kW | Net capacity at Exit point kW |
| 1. Sch. Consr. | 11 kW | 1 to 96 | 1,000 | 830.80 | |
| SPDCL | 2 Sch. Consr. | 132 kV | 1 to 96 | 2,000 | 1900.00 |
| 3. OA Consr. | 33kV | lto 96 | 1,000 | 893.40 | |
| Total for SPDCL | |||||
| 1. Sch. Consr. | 11 kV | 1 to 96 | 1,000 | 827.20 | |
| CPDCL | 2. Sch.Consr. | 33 kV | 1 to 96 | 3,000 | 2676.60 |
| 3. OA Consr. | 132 kV | 1 to 96 | 5,000 | 4750.00 | |
| Total for CPDCL | |||||
| 1. Sch. Consr. | llkV | 1 to 96 | 1,000 | 821.00 | |
| NPDCL | 2. OA Consr. | 33 kV | 1 to 96 | 2,000 | 1778.60 |
| Total for NPDCL | |||||
| 1. Sch. Consr. | 11 kV | 1 to 96 | 1,600 | 818.90 | |
| EPDCL | 2. OA Consr. | 33 kV | 1 to 96 | 3,000 | 2636.70 |
| Total for EPDCL | |||||
| Grand Total | 20,000 | 17983.20 |
| Transmission losses = 5%Distribution losses up to the Voltage level of exist point | (Percentage) |
| Voltage | SPDCL | CPDCL | NPDCL | EPDCL |
| 33kV 5.66 | 5.66 | 5.78 | 6.07 | 7.11 |
| 11 kV 11.92 | 11.92 | 12.28 | 12.90 | 13.11 |
| LT 20.44 | 20.44 | 20.50 | 23.05 | 21.30 |