State of Rajasthan - Subsection

Section 18(6) in Rajasthan Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2009

(6)The capital cost may include capitalised initial spares for a maximum of first five years of operation as follows:
(a)upto 2.5% of original capital cost in case of coal based/ lignite fired generating stations,
(b)upto 4.0% of original capital cost in case of gas turbine/ combined cycle generating stations,
(c)upto 1.5% of original capital cost in case of hydro-generating stations and
(d)upto 1.5% of original capital cost in case of transmission and distribution licensees.