captive Power plants excluding power plants based on Renewable Energy Sources. 2. Definitions.
(1) "Act" means the Electricity Act, 2003. (2) "Captive Power Plant ... captive users. (c) It shall be the obligation of the captive users to ensure that the consumption by the Captive Users at the percentages mentioned
Licensee including deemed licensee. (2) Open access consumer. (3) Captive consumer of a Captive Power Plant of installed capacity one MW and above. 3. Definitions ... Captive Power Plant' or CPP shall have meaning as assigned in RERC (Tariff for sale of power by captive power plants to Distribution licensee) Regulations
these regulations unless the context otherwise requires; (I) 'Captive Power Plants' or CPP shall have meaning as assigned in RERC (Tariff for CPP) Regulations ... Distribution licensee including deemed licensee; (2) Open access consumer; (3) Captive Power Plant of installed capacity 1 MW and above. 4. Renewable Energy Obligation
years (g) Wind energy / solar & other RE power project: 25 years (h) Biomass power project: 20 years (72) "User" means a transmission or distribution ... Commission shall determine the tariff of a Generating Company, except Captive Power Plants (CPP) and Renewable Energy Power Plants, or Licensee covered under a multi
further by short term bilateral sale; (iv) Sale through power exchange. Provided, the generator selling power to Distribution Licensee may make an application ... consumer who sources power both by captive generation and Discom to the extent of captive power supply subject to availability of transmission and/or distribution
Proposed Commercial Operation Date (COD)
:
7.
Power Plant proposed to be set up for
:
a) Captive use
:
b) Sale to RVPN/DISCOM on approved rate ... facility for the proposed plan
:
2.
Interfacing scheme proposed
:
3.
For captive power plant
i)
Present consumption of Electricity.
:
a) From Vidyut Vitaran Nigam
Proposed Commercial Operation Date (COD) : 7. Power Plant proposed to be set up for:-
(a) Captive use : (b) Sale to RVPN/DISCOM on approved rate ... facility for the proposed plan : 2. Interfacing scheme proposed : 3. For captive power plant
(i) Present consumption of Electricity : (a) From Vidyut Vitaran Nigam
SLDC; (o) `Seller' or `Supplier' means a person, SGS including a captive power plant (CPP), supplying electricity; (p) `State Energy Accounts' (SEA) means monthly State
Nuclear, Wind and Solar Power Stations, or (III) Run of River Hydro Power Stations without storage facility, and hydro power stations of Rajasthan Rajya Vidyut ... state ABT, as the case may be: Provided, in respect of captive power plants (CPP) the rated capacity of the generating station, will
tariff for sale of electricity by a generating company or a Captive Power Plant [CPP] to a distribution licensee, determined by the Commission for supply ... Conditions of Tariff), Regulations, 2004 or Rajasthan Electricity Regulatory Commission (Captive Power Plants), Regulations, 2007 or adopted under Section 63 of the Electricity