Delhi Electricity Regulatory Commission (Grant of Consent for Captive Power Plants) Regulations, 2002
DELHI
India
Delhi Electricity Regulatory Commission (Grant of Consent for Captive Power ... Regulations, 2002
Rule DELHI-ELECTRICITY-REGULATORY-COMMISSION-GRANT-OF-CONSENT-FOR-CAPTIVE-POWER-PLANTS-REGULATIONS-2002 of 2002
Published on 21 June 2002
Commenced
Section 13 in Delhi Electricity Regulatory Commission (Grant of Consent for Captive Power Plants) Regulations, 2002
13. Savings.
- Nothing in these regulations shall be deemed ... existing CPP Sir, The undersigned has set up/operates a Captive power Plant (CPP). In this regard, the following details are furnished for kind information
Section 3 in Delhi Electricity Regulatory Commission (Grant of Consent for Captive Power Plants) Regulations, 2002
3. General.
- (i) No person, other than those authorised ... Electricity Act or Supply Act shall install or operate a captive power plant in the National Capital Territory of Delhi. Provided that CPP with
Section 2 in Delhi Electricity Regulatory Commission (Grant of Consent for Captive Power Plants) Regulations, 2002
2. Definitions.
- In these regulations unless the context otherwise ... shall mean Delhi Vidyut Board, its predecessor or successor entities. (iv) "Captive Power Plant (CPP)" shall mean the power plant set up/proposed
Section 4 in Delhi Electricity Regulatory Commission (Grant of Consent for Captive Power Plants) Regulations, 2002
4. Procedure for Grant/Renewal of Consent for Captive
Section 7 in Delhi Electricity Regulatory Commission (Grant of Consent for Captive Power Plants) Regulations, 2002
7. Metering.
- (i) The CPP shall install two electronic
Section 6 in Delhi Electricity Regulatory Commission (Grant of Consent for Captive Power Plants) Regulations, 2002
6. General.
- (i) In case, generating capacity
Section 1 in Delhi Electricity Regulatory Commission (Grant of Consent for Captive Power Plants) Regulations, 2002
1. Short title, commencement and Interpretation.
- (i) These regulations ... shall be called Delhi Electricity Regulatory Commission (Grant of Consent for Captive Power Plants) Regulations, 2002. (ii) These regulations shall come into force
Section 11 in Delhi Electricity Regulatory Commission (Grant of Consent for Captive Power Plants) Regulations, 2002
11. Fines for non-compliance or violation.
- Non-compliance
Section 9 in Delhi Electricity Regulatory Commission (Grant of Consent for Captive Power Plants) Regulations, 2002
9. Environmental and Pollution Clearance