protect it from wood destroying elements, such as, fungus, borers, termites etc. After treatment, wood is subjected to seasoning i.e. drying of timber, which ... Part II-1981). The preservative is specially recommended in heavy termite and marine borers infected areas and in cooling tower timbers when soft
soils, setting out of buildings, excavation of trenches, plinth courses precautions against termites, damp proof courses; super structure - thickness of walls, scaffoldings stone versus brick
bold letters "only for use in terminate control in buildings includings wood, termite control in agriculture as per approved Table claims by the Registration Committee
import, manufacture and use of Lin are Gamma BHC) except for termite control in buildings including wood, termite control in agriculture as per the approved
person shall import, manufacture or use Lindane except- (i) for termite control in buildings including wood; (ii) for termite control in agriculture
Nagar 13.0., Banga1ore--58() 032.
PW2 was dealing with pesticides and anti termite
chemicals, During the year 199?, FCI had eaiied for
tenders for supply ... ltVr.=-_df~_
aforestated anti termite. The af;)re:_§;ta;.te'ed1e»<;u'afi
petitioner found some of the records and documents were eaten by
termites. Only the record for the year 2013 (half eaten by termites) could ... information:-
"i. To furnish
a) List of Notary Register damaged by termite,
b) list of those survived termite attack.
c) partially damaged register
contract, the
contractor/petitioner herein is bound to carry out Anti-Termite Treatment (ATT),
through an approved specialist agency and the same should be effective ... first respondent raised a claim before the Arbitrator that Anti Termite
Treatment given by the petitioner was found ineffective, as a result, the building
1186/17 2
godown, when it was revealed that serious termite attack was
there and no proper measures were taken by the appellant ... Manager
also conducted an enquiry, who submitted Exhibit P2 report
confirming the termite attack. It was accordingly, that Exhibit
P3 memo of charges was issued
alia
prescribes that the contractor should possess required valid
electrical license, Anti-termite license for execution of building
electrification works and should have executed similar ... with third party when
the bidders did not have valid Anti-termite license and
electrical license and such relaxation was granted uniformly