| Sl. No. |
Section of the act empowering grant of exemption |
Class of factory |
|
Nature of exempted work |
|
Extent of exemption |
|
Conditions |
| 1 |
2 |
3 |
|
4 |
|
5 |
|
6 |
| 1. |
64 (2)(a) and 64(3) |
All Factories |
|
Urgent repairs |
|
Sections 51, 52, 54, 55, 56 and 61 |
|
(a) Written notice to the Inspector ofFactories describing briefly the nature of urgent repairs andthe probable period of their duration shall be sent withintwenty-four hours from the commencement of the work on urgentrepair.
|
| |
|
|
|
|
|
|
|
(b) If the Inspector is of opinion that anywork being carried on in a factory as urgent repairs is noturgent repairs the Inspector shall serve on the Manager an orderto that effect and the Manager shall in respect of such work notallow any worker to work in contravention of the provisions ofSections 51, 52, 54, 55 and 56 and shall comply with Section 61.
|
| |
|
|
|
|
|
|
|
(c) No worker shall be employed on such workfor more than-
|
| |
|
|
|
|
|
|
|
(i) ten consecutive days without a holiday fora whole day,
|
| |
|
|
|
|
|
|
|
(ii) fifteen hours on any one day; |
| |
|
|
|
|
|
|
|
(iii) thirty-nine hours during any threeconsecutive days; or
|
| |
|
|
|
|
|
|
|
(iv) sixty-six hours during each period ofseven consecutive days; and
|
| |
|
|
|
|
|
|
|
(d) a statement showing the total number ofhours worked each day in the week by each worker shall be sentto the Inspector within thirty-six hours after the completion ofthe work.
|
| 2. |
64(2)(b) and 64 (3) |
All factories other than those on continuous process |
|
1. Work in the machine shop, the smithy or thefoundry or in connection with the mill gearing, the electricdriving or lighting apparatus, the mechanical or electricallights or the steam or water pipe or pumps of a factory.
|
|
Sections 51, 54, 55, 56 and 61 |
|
The limits of work inclusive of overtime shallnot exceed those mentioned in Sub-section (4) of Section 64.
|
| |
|
|
|
2. Work-of examining or repairing any machineryor other part of the plant which is necessary for carrying onthe work in factory.
|
|
|
|
|
| |
|
|
|
3. Work in boiler houses and engine rooms, suchas lighting fires in order to raise steam or generate gaspreparatory to the commencement of regular work in the factory.
|
|
|
|
|
| 3. |
62(2)(c) and 64 (3) |
All factories |
|
Work performed by drivers, on lighting,ventilating and humidifying apparatus. Work performed by firepump-men.
|
|
Sections 51, 54, 55, 56, 56 and 61 |
|
The limits of work inclusive of overtime shallnot exceed those mentioned in Sub-section (4) of Section 64.
|
| 4. |
64 (2)(d) and 64 (3) |
Oil tank installation |
|
Work performed by workers in connection withpumping operations
|
|
Section 51, 52, 54, 55, 56 and 61 |
|
Ditto |
| 5. |
64(2)(b) |
Ditto |
|
Work performed by furnacement and firemen |
|
Sections 51, 54, 55 and 56 |
|
Ditto |
| 6. |
64 (2)(d) |
Public electricity supply factories generatingelectricity in any manner and those engine rooms and boilerdepartments generating electricity in any manner for their ownuse employing workers on shift
|
|
Operation maintenance of(i) Prime moversand auxiliaries, generators, transformers and switch gears;(ii)Boilers and auxiliaries.
|
|
Sections 51, 52, 54, 55 and 56 |
|
(a) The workers shall be allowed to work onshifts of not longer than eight hours durations
|
| |
|
|
|
|
|
(b) No such worker shall be employed more thanfourteen consecutive days without a compensatory rest period ofat least twenty hours at one time.
|
| |
|
|
|
|
|
|
(c) No such worker shall be employed so as towork in excess of any of the limits specified in Sub-section (4)of Section 61 :
|
| |
|
|
|
|
|
|
|
Provided that in the absence of a worker whohas failed to report for duty, a shift worker may be allowed towork to whole or part of a subsequent shift on condition that -
|
| |
|
|
|
|
|
|
|
(i) the next shift of the shift worker shallnot commence before a period of 15 hours has elapsed after thespecified stopping time of the shift to which the workerbelongs;
|
| |
|
|
|
|
|
|
|
(ii) the circumstances under which the workeris required to work in the subsequent shift shall be notedimmediately in the remarks column of the register of adultworkers.
|
| |
|
|
|
|
|
|
|
(d) No worker shall be allowed to work morethan 56 hours in any one week except when employed as in provisoto Clause (c) above, but he shall not be allowed to work formore than 64 hours in any one week.
|
| 7. |
64(2)(d) |
Electrical receiving stations and substationsor in any factory the department of the factory receiving anddistributing electrical energy for the use of the factory
|
|
Operation and maintenance of transformer andtheir auxiliaries including receiving and distribution,switch-gear, lighting arresters, synchronous and othercondensers and rotary and static condensers.
|
|
Sections 51, 52, 55 and 56 |
|
Ditto |
| 8. |
64(2)(d) |
Distilleries |
|
Work on the extraction for sugar from variousbases, fermentation of sugar juice and distillation of fermentedwash
|
|
Ditto |
|
Ditto |
| 9. |
64(2)(d) |
Sugar Factories |
|
Operation beginning with receiving andweighment of cane and ending with bagging of sugar where thereis vaccum pan system
|
|
Ditto |
|
Ditto |
| 10. |
64(2)(d) |
Iron and Steel Factories |
|
Operation of blast furnaces, steel meltingfurnaces Linz and Donawitz Converters, rolling mills and suchother work which must proceed concurrently with such operationsand must be for technical reason carried on continuouslythroughout the day.
|
|
Ditto |
|
Ditto |
| 11. |
64(2)(d) |
Coke-oven Plants |
|
Operation of cock-ovens |
|
Ditto |
|
Ditto |
| 12. |
64(2)(d) |
By product Plants |
|
Recovery and treatment of by-products |
|
Ditto |
|
Ditto |
| 13. |
64 (2)(d) |
Paper Factories |
|
Work performed by male adult workers on bamboopreparing plant, digester, strainers and washers, beaters, papermaking machines, super calendar, acid plant, soda recoveryplant, pumping plant, electrolysis plant and bleaching plant,work of lime reburning, gas producer plant, fibre recovery andwater clarifier
|
|
Sections 51, 52, 55 and 56 |
|
No worker shall be allowed to work more than 56hours in any one week except when employed as in proviso toClause (c) above, but he shall not be allowed to work for morethan 64 hours in any one week
|
| 14. |
64 (2)(d) |
Cement Factories |
|
All works on continuous process units |
|
Ditto |
|
Ditto |
| 15. |
64(2)(d) |
Aluminium Factories |
|
All works on continuous process units |
|
Ditto |
|
Ditto |
| 16. |
64(2)(d) |
Refractories and Potteries |
|
Workers or polishers in all potteries, mixing,moulding, drying, setting and operations of kinds including gasproducer
|
|
Ditto |
|
Ditto |
| 17. |
64(2)(d) |
Chemical Factories |
|
All works on continuous process |
|
Ditto |
|
Ditto |
| 18. |
64(2)(d) |
Vegetable oil hydrogeneration factories |
|
The work viz., refining, bleaching, filteringgeneration of hydrogen, hydrogenerating deodourising processesalso compression of oxygen and the cylinder filling
|
|
Ditto |
|
Ditto |
| 19. |
64(2)(d) |
Ice Factories |
|
Work on the manufacturing/handling of ice |
|
Ditto |
|
Ditto |
| 20. |
64(2)(d) |
Glass Factories |
|
Work of charging and attending to the post ortanks, attending sheet glass, making machines and fullyautomatic other glass making machines and firing the furnace
|
|
Ditto |
|
No worker shall be allowed to work more thanfifty-six hours in any one week except when employed as inproviso to Clause (c) above, but he shall not be allowed to workfor more than 64 hours in any one week.
|
| 21. |
64(2)(d) |
Oxygen Factories |
|
Engine and plant drivers, oilers and filling ofcylinders
|
|
Sections 51, 52, 54, 55 and 56 |
|
Ditto |
| 22. |
64(2)(d) |
Acetyline Factories |
|
Generation of gas filling of cylinders |
|
Ditto |
|
Ditto |
| 23. |
64(2)(d) |
Water works and pumping stations |
|
All works |
|
Sections 51, 52, 54, 55 and 56 |
|
Ditto |
| 24. |
64(2)(d) |
Ferro-alloys Factories |
|
Operation on electric furnaces |
|
Ditto |
|
Ditto |
| 25. |
64(2)(d) |
Oil Mills |
|
All works on continuous process |
|
Section 55 |
|
The workers shall be allowed to work on shiftsof not longer than 8 hours' durations.
|
| 26. |
64(2)(d) |
Flour Mills |
|
All works |
|
Ditto |
|
Ditto |
| 27. |
64(2)(d) |
Rubber Type Factories |
|
All works on curing process |
|
Sections 55 and 56 |
|
The limits of work inclusive of overtime shallnot exceed those mentioned in Sub-section (4) of Section 64.
|
| 28. |
64(2)(i) and 64(3) |
Newspaper Printing Factories |
|
Workers engaged in printing of newspapers whoare held up on account of breakdown of machinery
|
|
Sections 51, 54, 56 and 61 |
|
Ditto |
| 29. |
64(2)(i) and 64(3) |
All Factories |
|
Loading and unloading of Railway Wagons,trucks, or lorries
|
|
Sections 51, 52, 54, 55, 56 and 61 |
|
The limits of work inclusive of overtime shallnot exceed those mentioned in Sub-section (4) of Section 64.
|
| 30. |
64(2)(b) and 64(3) |
Ordinance Factories and the work connected withtesting of its products
|
|
The work viz., firing gun recovery of firedshells and demolition of blind
|
|
Sections 51, 52, 55, 56 and 61 |
|
Ditto |
| 31. |
64(2)(h) |
All factories other than those on continuousprocess
|
|
Workers engaged in engine rooms and boilerhouses, workers attending to power plant machinery andtransmission machinery
|
|
Section 51 and 52 |
|
No worker shall be employed on such work formore than ten consecutive days without a holiday for a whole day
|
| 32. |
64 (2)(k) |
Printing Presses |
|
Printing of Ballot Papers for Parliament andAssembly Elections
|
|
Section 51, 52, 54, 55 and 56 |
|
The limits of work inclusive of overtime shallnot exceed those mentioned in Sub-section (4) of Section 64.
|