State of Punjab - Act
Approval of Periphery Policy Report and other Allied Matters
PUNJAB
India
India
Approval of Periphery Policy Report and other Allied Matters
Rule APPROVAL-OF-PERIPHERY-POLICY-REPORT-AND-OTHER-ALLIED-MATTERS of 2006
- Published on 20 January 2006
- Commenced on 20 January 2006
- [This is the version of this document from 20 January 2006.]
- [Note: The original publication document is not available and this content could not be verified.]
1.
1.
The Chandigarh Periphery Controlled area was created with the twin objectives of ensuring a planned future expansion of the New Capital City and to prevent mushrooming of unplanned construction around it. The Punjab New Capital (Periphery) Control Act, 1952 accordingly aimed at regulating the use of land and preventing unauthorized and unplanned urbanization in a 16 kilometre periphery.2. The Committee
:3.
The Deliberations - Broad Policy Framework :4.
Recommendations:Given the above approach and considering the ground realities, existing status of the Periphery, emerging problems of unregulated and unauthorised development, need for promoting planned development and eliminating unauthorised and illegal constructions, the Committee, proposes to address various issues on the following lines :-7.
Conclusion:The Committee had to balance and optimise between divergent and often conflicting demands and requirements. For instance, the purist view of freezing the Periphery as agricultural was contradictory to the very reasonable demand to allow for the expansion of the 'abadi dehs' or for permitting housing in a planned manner. Similarly, although institutions and leisure facilities have been recommended, the norms of FAR and built-up area, have been pegged on the lower side.Conversion charges were also deemed necessary to raise resources for the overall development of the Periphery, although the Committee was acutely conscious that it may add to overall project cost. While the Committee recommends strict compliance with the up-to-date Outline Master Plan of S.A.S. Nagar, it also suggests the speedy formulation of an Over-arching Periphery Development Plan for the entire region. Nevertheless, pending finalization of the latter, the Committee recommends that limited change of land use may be permitted as per the recommendations contained in this Report.Even though existing constructions have been proposed to be regularised on purely humanitarian grounds, the Committee has strongly recommended a zero tolerance enforcement and regulatory regime, in the Post-Policy Phase. However, enforcement of the regulatory regime would only be sustainable in the long run if total Area Planning of the Periphery is taken up in right earnest and brought to its logical conclusion at the earliest.The prescription proposed by the Committee is to be viewed as a comprehensive package, which needs to be comprehensively implemented. The Committee sincerely hopes that it would have addressed the concerns of all the stakeholders in a judicious, balanced and practical manner. It is now for the State Government to consider, approve and implement both the regulatory and development aspects of this policy in prescribed time frames.Annexure AGuidelines For Permitting Planned and Organized Residential Development in the PeripheryPlanned residential development shall be permitted in the Periphery only in :-2. "Residential" development may include :
3. The developer shall obtain a regular licence from the Competent Authority under the Punjab Apartment and Property Regulation Act, 1995. External Development Charges (EDC), Conversion Charges and Licence Fee shall be payable as per the approved/notified rates, unless specifically exempted by the Competent Authority. The recommendations of the Committee are at Annexure D.
4. Development Norms :
1. Subject to the other conditions mentioned hereinafter, setting up of Farmhouses, institutions, infrastructure relating to recreational and leisure activities, including sports shall be permitted in the Periphery Controlled Area, except in the:-
2. The institutions to be permitted would generally be associated with education, including medical education, research, art and culture. Sports infrastructure could be confined to recognized games and sporting activities, whereas recreation and leisure infrastructure may include amusement parks, open-air theatres, theme parks etc. but not shopping malls, cinema halls, multiplexes and the like.
3. The minimum area required for any of these activities would be as described in the chart at the end of this Annexure. However, if at any stage, the total area of site falls below the stipulated limit, the permission granted shall automatically lapse and building, if any, constructed shall be deemed to be illegal and unauthorized.
4. Land shall be in the shape of a single compact unit, held in single or joint ownership of natural or artificial juridical persons, or combination thereof.
5. The institutional and recreational sites shall have an independent access from a public road having a minimum width of 40 feet. In case of sites not abutting a public road, a connecting passage of not less than 40 feet width (which would be used as public thoroughfare) shall be mandatory. If access is required to be taken from a National/State Highway, it shall be taken through a service lane to be developed at the expense of the applicant. However, in case of Farmhouses, an independent access from a revenue "rasta" or public road shall suffice.
6. The building shall have a minimum setback of 200 feet from the National/State Highway and at least 100 feet from any other metal led road. The minimum setback on other sides shall be equivalent to the height of the building.
7. No sub-division of the land would be subsequently permitted.
8. Adequate provision for parking shall be made within the site.
9. Minimum Area and Development Norms :
| Building Type | Minimum size (acres) | Floor-Area Ratio (FAR) | Ground Coverage (% age) | No. of storyes | Height (feet) | Hard Surface (% age) |
| Farm Houses | 2.5 | 4.00% | 2.00% | 2 | Single (18) | 10.00% |
| Double (28) | ||||||
| Institutions | 5* | 30.00% | 15.00% | 3 | 38 | 30.00% |
| Recreational activities | 10** | 5.00% | 3.00% | 2 | 28 | 10.00% |
| Sports activities | 10 | 2.00% | 1.00% | 2 | 28 | 5.00% |
| Sr. No. | Type of Category | Residential (Plotted) | Residential (Group Housing) | Commercial | ||||||
| Abutting on | Abutting on | Abutting on | ||||||||
| NH | SH/Sector Road | Other Road | NH | SH/Sector Road | Other Road | NH | SH/Sector Road | Other Road | ||
| 1 | EDC | 15.09 | 15.09 | 15.09 | 60.36 | 60.36 | 60.36 | 60.36 | 60.36 | 60.36 |
| (FAR 1.50) | (FAR 1.50) | (FAR 1.50) | (FAR 1.50) | (FAR 1.50) | (FAR 1.50) | |||||
| 2 | Conversion Charges | 6 | 5 | 4 | 9 | 7.5 | 6 | 48 | 40 | 32 |
| 3 | Licence Fee | 2 | 2 | 2 | 4 | 4 | 4 | 150 | 150 | 150 |
| (FAR 1.50) | (FAR 1.50) | (FAR 1.50) | (FAR 1.50) | (FAR 1.50) | (FAR 1.50) | |||||
| Total | 23.09 | 22.09 | 21.09 | 73.36 | 71.86 | 70.36 | 258.36 | 250.36 | 242.36 | |
| Per Sq. Yd. | Rs. 477 | Rs. 456 | Rs. 436 | Rs. 1516 | Rs. 1485 | Rs. 1454 | Rs. 5338 | Rs. 5173 | Rs. 5007 |
| Industrial | Recreational | Institutional | ||||||
| Abutting on | Abutting on | Abutting on | ||||||
| NH | SH/Sector Road | Other Road | NH | SH/Sector Road | Other Road | NH | SH/Sector Road | Other Road |
| 30.18 | 30.18 | 30.18 | 15.09 | 15.09 | 15.09 | 15.09 | 15.09 | 15.09 |
| *(FAR 1.00) | *(FAR 1.00) | *(FAR 1.00) | *(FAR 1.00) | *(FAR 1.00) | *(FAR 1.00) | *(FAR 1.00) | *(FAR 1.00) | *(FAR 1.00) |
| 6 | 5 | 4 | 6 | 5 | 4 | 6 | 5 | 4 |
| 0.5 | 0.5 | 0.5 | 0.5 | 0.5 | 0.5 | 0.5 | 0.5 | 0.5 |
| *(FAR 1.00) | *(FAR 1.00) | *(FAR 1.00) | *(FAR 1.00) | *(FAR 1.00) | *(FAR 1.00) | *(FAR 1.00) | *(FAR 1.00) | *(FAR 1.00) |
| 36.68 | 35.68 | 34.68 | 21.59 | 20.59 | 19.59 | 21.59 | 20.59 | 19.59 |
| Rs. 758 | Rs. 737 | Rs. 717 | Rs. 446 | Rs. 425 | Rs. 405 | Rs. 446 | Rs. 425 | Rs. 405 |
2. *Rates for EDC and Licence Fee increase proportionately for higher FAR.
3. 25% of External Development Charges (EDC) shall be payable upfront and balance 75% in 6 equated bi-annual instalments with 10% compound interest. Penal interest for delayed payment at the rate of 18% per annum shall also be charged.
4. The charges have been proposed by keeping Sector (250 acres approx.) as a unit of development.
5. For mixed land use, proportionate charges for different categories shall apply.
Annexure D-IIExternal Development Charges for S.A.S. Nagar as per Master Plan prepared by CTP, Punjab| Sr. No. | Particulars | Area/Length/No. | Estimated Cost (Rs. in crores) |
| 1 | Master roads : | ||
| (a) R-1, R-2, R-3 | 130 K.M. | 369 | |
| (b) High level road bridges | 6 No. | 24 | |
| (c) Fly overs | 6 No. | 150 | |
| (d) Rail over Bridge, Rail under Bridge | 7 No. | 14 | |
| 2 | Master Horticulture : | ||
| (a) Road Side Plantation | 130 K.M. | 3 | |
| (b) Dev. of Parks | 1473.11 arce | 25 | |
| 3 | Master Electrical : | ||
| (a) H.T. lines | 2023.42 acre | 770 | |
| (b) Street lights | 130 | ||
| (c) Electrical grid sub-station | 400 | ||
| 4 | Master P.H. Services : | ||
| (a) Sullage sewer | 2023.42 acre | 150 | |
| (b) Water Supply | 2023.42 acre | 200 | |
| (c) Water works and supply from Kajauli | 23.90 acre | 200 | |
| (d) Sewerage Treatment Plant | 70.00 acre | 50 | |
| Disposal channel and laying | |||
| Estate Irrigation System | |||
| 5 | Master Storm water disposal : | ||
| (a) Storm Drainage | 2023.42 acre | 170 | |
| (b) Flood Control | - | 50 | |
| (c) Rain harvesting structures | - | 50 | |
| 6 | Master Public Facilities : | ||
| (a) Sports Complex | 90 | ||
| (b) Police Station | 60 | ||
| (c) Educational Buildings | 220 | ||
| (d) Government Health Centres | 45 | ||
| (e) Government Hospitals | 275 | ||
| (f) Fire Stations | 45 | ||
| (g) Community Center | 65 | ||
| (h) Recreational Facilities | 55 | ||
| (i) Bus Terminus | 70 | ||
| (j) Solid Waste Disposal | 75 | ||
| 3755 | |||
| 7 | Infrastructural utilities land cost | 4873 @ 0.41 Crore per Acre | 2000 |
| 5755 | |||
| 8 | Escalation as per inflation rate @ 7% on Rs. 3755 lacs | 262.85 | |
| 9 | Unforseen @ 5% on Rs. 4017.85 lacs | 200.89 | |
| 10 | Project Management charges @ 10% on Rs. 4218.74 lacs | 421.87 | |
| 11 | Capitalised maintenance for 10 years : | ||
| (a) Road Works | 100 | ||
| (b) Running and maintenance for electrical work | 188 | ||
| (c) Running and maintenance of P.H. works | 500 | ||
| (d) Maintenance for Horticulture works | 30 | ||
| Grand Total : | 7458.61 | ||
| Say : | 7460 Crores | ||
| Total Area : 28987.21 Acres | |||
| Say : 29000 Acres | |||
| Cost per gross Acre = 25.72 lacs |
2. Mass Rapid Transit System cost amounting to Rs. 3450 crores approx. has not been added at this stage.
3. Land cost component will be as per actual cost of acquisition including any subsequent enhancements allowed by Courts.
Area as per proposed Master Plan of S.A.S. Nagar| (A) Saleable Area (in Acres) : | ||
| (a) Plotted | 10200 | |
| (b) Group Housing | 3000 | |
| (c) Commercial | 1431 | |
| (d) Industrial | 5314 | |
| (e) Institutional | 1159 | |
| (g) Mixed Land Use | 2710 | |
| (g) Railway Line/Truck Terminus | 300 | |
| 24114 | ||
| (B) Infrastructural Utilities Land Area (in Acres) : | ||
| (a) Roads | 2023.42 | |
| (b) Recreational | 1243.11 | |
| (c) Sewerage Treatment Plant | 70 | |
| (d) Water Treatment Plant | 23.9 | |
| (e) Bus Terminus | 68 | |
| (f) Golf Course | 230 | |
| (g) Hospital | 55.78 | |
| (h) Institutional | 1159 | |
| 4873.21 | ||
| Grand Total (A+B) : | 28987.21 Acres | |
| Say : | 29000 Acres |
| Sr. No | Type of Category | Residential (Plotted) | Residential (Group Housing) | Commercial | ||||||
| Abutting on | Abutting on | Abutting on | ||||||||
| NH | SR/Sector Road | Other Road | NH | SR/Sector Road | Other Road | NH | SR/Sector Road | Other Road | ||
| 1 | EDC | 18.84 | 18.84 | 18.84 | 78.46 | 78.46 | 78.46 | 78.46 | 78.46 | 78.46 |
| 2 | Conversion Charges | 6.07 | 4.86 | 4.05 | 6.07 | 4.86 | 4.05 | 48.56 | 40.47 | 32.38 |
| 3 | Licence Fee | 4 | 4 | 4 | 5 | 5 | 5 | 200.00 (FAR 1.75) | 200.00 (FAR 1.75) | 200.00 (FAR 1.75) |
| 4 | Service Charges (Fund used for enforcement purpose) | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 |
| 5 | Scrutiny Fee to examine colony plans/documents etc. | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 |
| Total | 29.71 | 28.5 | 27.69 | 90.33 | 89.12 | 88.31 | 327.82 | 319.73 | 311.64 | |
| (Rs. 734 per sq.mtr.) | (Rs. 704 per sq.mtr.) | (Rs. 684 per sq.mtr.) | (Rs. 2232 per sq.mtr.) | (Rs. 2202 per sq.mtr.) | (Rs. 2182 per sq.mtr.) | (Rs. 8100 per sq.mtr.) | (Rs. 7900 per sq.mtr.) | (Rs. 7700 per sq.mtr.) |
| Industrial | Recreational | Institutional | ||||||
| Abutting on | Abutting on | Abutting on | ||||||
| NH | SR/Sector Road | Other Road | NH | SR/Sector Road | Other Road | NH | SR/Sector Road | Other Road |
| 43.23* (FAR 1.25) | 43.23* (FAR 1.25) | 43.23* (FAR 1.25) | NA | NA | NA | 18.84 | 18.84 | 18.84 |
| 0.49 | 0.49 | 0.49 | 0.49 | 0.49 | 0.49 | 4.05 | 3.24 | 2.4 |
| 0.5 | 0.5 | 0.5 | NA | NA | NA | NA | NA | NA |
| 0.4 | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 |
| 0.4 | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 | 0.4 |
| 45.02 | 45.02 | 45.02 | ||||||
| (Rs. 1112 per sq.mtr.) | (Rs. 1112 per sq.mtr.) | (Rs. 1112 per sq.mtr.) |