State of Odisha - Section

Section 9 in The Professional Examination of Power Engineers for Thermal Generation Regulations, 1988

9.

(1)The examination shall be conducted by a Committee to be constituted each Calendar year by the Member (Generation), O.S.E.B. and shall consist of-
(a) General Superintendent, Talcher Thermal Power Station President
(b) One General Manager Member
(c) One Dy. General Manager/ Superintending Engineer (El.) Member
(d) One Superintending Engineer (Telecommunication) Member
(e) Secretary, O.S.E.S. Member
(2)The President shall submit the report of the Committee with his observations and recommendations to the Member (Generation), O.S.E.B. who shall decide as to which Engineer shall be deemed to pass the test and shall publish their names-
(a)In the case of first appointment, an Engineer shall be employed in such a manner as to afford him to gain experience to pass the examination. He shall undergo training at least for 8 working days in a Stores Subdivision and at least 7 working days in any field Subdivision. While in training, besides maintenance of Cash Account of a Subdivision, he shall personally check Measurement Books, prepare bills, Contractor Ledger and other Sub-divisional registers, etc. Thereafter he sell spend a period of 15 days in Accounts Cell where with the assistance of an Accountant he shall compile the accounts of at least one month besides maintenance of other connecting records in Accounts Cell.
(b)No Engineer shall be permitted to appear for the examination until he has undergone the training prescribed in Sub-regulation (a) aforesaid and in addition, has been satisfactorily reported to by the Manager and the Deputy General Manager under whom he is serving with regard to his physical energy and efficiency in practical work and his capacity to manage his subordinates.
Note. - A special report on the above points shall be submitted to the General Superintendent, Talcher Thermal Power Station when an Engineer applies for permission to appear in the examination.