adjustment subject to several conditions
which are reproduced below.
"The approved (FPPCA) formula is subject to following
conditions:
(i) The basic nature of FPPCA ... Commission in this tariff order shall be the basis of
calculating FPPCA charges.
(iii) Incremental cost of power purchase due to deviation
in respect
have
been passed under the Fuel and Power Purchase Cost
Adjustment (FPPCA), actually it is not FPPCA
determined under the Formula and on the other ... State Commission has got the discretion to allow the
ad-hoc FPPCA provisionally in the course of any year
either on suo-moto
State Commission passed the
Fuel and Power Purchase Cost Adjustment (FPPCA)
order for the years ... learned counsel for the State
Commission, the Appellant has not challenged the
FPPCA order dated 31.1.2008 vide which the State
Page 6 of 33
Appeal
determined with better accuracy to reduce the impact of FPPCA and APR of ensuing year in future tariff. 2.1.14 - Notwithstanding anything to the contrary contained ... repealed regulations. 2.1.15 - The truing up of the ARR under APR and FPPCA for the year 2009-10 and 2010-11, for which order
with proper supporting document and also subject to prudence check. However, during FPPCA calculation, in case where applicant cannot provide actual data of different fuel ... mixing proportion of the fuel received in the year for which FPPCA is under calculation. (vi) Demurrage charge of railway rake, being commercial terms
determined with better accuracy to reduce the impact of FPPCA and APR of ensuing year in future tariff. 2.1.14 - Notwithstanding anything to the contrary contained ... repealed regulations. 2.1.15 - The truing up of the ARR under APR and FPPCA for the year 2009-10 and 2010-11, for which order
Appellant filed an application for Fuel and
Power Purchase Cost Adjustment ("FPPCA") to claim
the enhanced cost of fuel and power purchase ... under the 2007 Regulations on
22.09.2008. The State Commission decided the FPPCA
application by its order dated 27.5.2009. In this order
the State Commission made
payment of a sum
ofRs.1,19,06,413/- towards FPPCA charges in three installments
within fifteen days. In the meantime, the BIFR vide ... from disconnecting power
connection of the company consequent to non-payment of FPPCA
charges till the next date of hearing. Thereafter another bill was
issued
previous year, arrear on account of adjustment due to Annual Performance Review , FPPCA, etc. of a generating company or a licensee, as the case ... annually for the year under consideration for the each notified grade. For FPPCA the actual UHV as per audited report will be considered but generally
Commission with regard to fuel and power purchase
cost adjustment charges ( FPPCA) for the period
October, 2008 to March, 2009 and April, 2009 to
September