State Commission can ask the Licensee/Electricity
Board to recover the FPPCA charges without review and truing up
when the licensee is not generating rather
adjustment subject to several conditions
which are reproduced below.
"The approved (FPPCA) formula is subject to following
conditions:
(i) The basic nature of FPPCA ... Commission in this tariff order shall be the basis of
calculating FPPCA charges.
(iii) Incremental cost of power purchase due to deviation
in respect
have
been passed under the Fuel and Power Purchase Cost
Adjustment (FPPCA), actually it is not FPPCA
determined under the Formula and on the other ... State Commission has got the discretion to allow the
ad-hoc FPPCA provisionally in the course of any year
either on suo-moto
case may be, under this
Act"
..........................................
16.2 Thirdly, the FPPCA in terms of section 62
(4) is required to be specified in the
Regulations ... case and as a result where there is
no regulation providing for FPPCA the
Commission cannot lay down any
formula in a tariff order. When
State Commission passed the
Fuel and Power Purchase Cost Adjustment (FPPCA)
order for the years ... learned counsel for the State
Commission, the Appellant has not challenged the
FPPCA order dated 31.1.2008 vide which the State
Page 6 of 33
Appeal
incremental cost on account of Fuel and Power Purchase Cost Adjustment (FPPCA) in accordance with the formula and related terms and conditions ... Commission shall also specify the categories of Consumers for recovery of the FPPCA charge
determined with better accuracy to reduce the impact of FPPCA and APR of ensuing year in future tariff. 2.1.14 - Notwithstanding anything to the contrary contained ... repealed regulations. 2.1.15 - The truing up of the ARR under APR and FPPCA for the year 2009-10 and 2010-11, for which order
cost and power purchase cost namely fuel and power purchase cost adjustment (FPPCA) charges shall be as under:
FPPCA (Paise ... shall be taken into consideration. Terms and conditions for application of the FPPCA formula (1) The basic nature of FPPCA is 'adjustment' i.e. passing
with proper supporting document and also subject to prudence check. However, during FPPCA calculation, in case where applicant cannot provide actual data of different fuel ... mixing proportion of the fuel received in the year for which FPPCA is under calculation. (vi) Demurrage charge of railway rake, being commercial terms
part thereof-20 units per month
Fuel and Power Purchase Cost Adjustment (FPPCA) charges will be extra as applicable. (iv) DS-III (Metered)
Energy charges ... units/flat per month Additional KW-20 units/flat per month
FPPCA will be charged extra as applicable. 2.0 Non Domestic Service (NDS) - Applicability - Applicable