Section 73H(4) in Maharashtra Factories Rules, 1963
(4)Additional Special Precautions. - (i) The heating of the process, if required, shall not be carried out by immersion or other types of heaters deriving energy from electricity.(ii)The steam heating coils placed in the lower part of the vessel shall never be kept uncovered or allowed to be heated dry. A substantial amount of the liquid shall be ensured in the vessel after each operation to insure this:Provided that in case employing out of vessels filled with high melting products, the steam shall be stopped/disconnected to the heating coils, before draining process is started to ensure that the heating coils are free of steam before they are uncovered.(iii)Steam shall be supplied through a pressure reducing valve and a safety valve correctly set to ensure that the critical temperature of the process is not exceeded.(iv)A suitable rupture disc shall be provided on the vessel in addition to the usual spring-loaded safety valve. The pipe duct leading away from the rupture disc shall be taken out of the work-room shall be straight and without any bends in order to minimise resistance at the time of blowing and to avoid any chance of a secondary vapour/air explosion.(v)The vent line of the vessel shall carry a flame-arrestor.(vi)Breaking of vacuum, if the process is done under vacuum, on account of consideration of special hazards inherent in the process, shall be done only with nitrogen, other suitable inert gas or steam. Compressed air 'connection to the manifolds of the vessel equipment shall be avoided.(vii)There shall be an automatic cut-off device of steam supply or other heating devices as well as of further feed to the vessel set to operate, no sooner the critical temperature is reached, beyond which the reaction, if any, in the vessels is likely to get out of control or reach run-away stage.(viii)There shall be arrangement such that it would be possible to introduce quickly, preferably chilled water or at least ordinary cool water circulation in the steam or other hearing coils, no sooner the hearing element is cut-off or separate coils or jackets for this purpose shall be provided for the vessel.(ix)An alarm system shall be provided linked to the pressure indicator of the vessel, so that automatically an audible warning will be given as soon as the pressure exceeds the present safe limit.(x)There shall be provided an automatic arrangement such that if the mechanical agitation, where so provided, fails on account of failure of motive power or due to broken shaft, broken blades, failing of blades or such other contingencies, the supply of steam or other heating devices as well as further feed of material would stop automatically.