Union of India - Subsection
Section 7(1) in Central Electricity Authority (Installation and Operation of Meters) Regulations, 2006
| Sl. No. | Stages | Main meter | Check meter | Stand by meter |
| A. | Generating Station | On all outgoing feeders. | On all outgoing feeders. | (i) High Voltage (HV) side of Generator Transformers(ii) High Voltage(HV) side of all Station Auxiliary Transformers |
| Sl.No. | Stages | Main Meter | Check Meter | Stand by Meter |
| B. | Transmission and Distribution System | At one end of the line between the sub-stations of the same licensee, and at both ends of the line between sub-stations of two different licensees. Meters at both ends shall be considered as main meters for respective licensees | - | There shall be no separate standby meter. Meter installed at other end of the line in case of two different licensees shall work as standby meter. |
| C. | Inter-Connecting Transformer (ICT) | High Voltage (HV) side of ICT. | - | Low Voltage (LV) side of ICT. |
| D. | Consumer directly connected to the Inter-State Transmission System or Intra-State Transmission System who have to be covered under ABT and have been permitted open access by the Appropriate Commission or Any other system not covered above | As decided by the Appropriate Commission. |