Gsb Construction Pvt.Ltd. vs Jabalpur Devlopment Authy. on 6 November, 2023
Author: Sanjay Dwivedi
Bench: Sanjay Dwivedi
1
IN THE HIGH COURT OF MADHYA
Purbanchal Trade And Industries Ltd vs Gsb Constructions Pvt Ltd & Ors on 27 March, 2023
Author: Chandra Dhari Singh
Bench: Chandra Dhari Singh ... PURBANCHAL TRADE AND INDUSTRIES LTD ..... Plaintiff
Through: Mr. Vipul Goel, Advocate
versus
GSB CONSTRUCTIONS PVT LTD & ORS. ..... Defendants
Through: Counsel for the defendants
(Appearance
Gsb Construction Pvt.Ltd. vs Jabalpur Devlopment Authy. on 17 April, 2023
Author: Maninder S. Bhatti
Bench: Maninder S. Bhatti
1
IN THE HIGH COURT ... MADHYA PRADESH
AT JABALPUR
WP No. 4430 of 2008
(M/S GSB CONSTRUCTION PVT.LTD. Vs JABALPUR DEVLOPMENT AUTHY. AND OTHERS)
Dated
Purbanchal Trade And Industries Ltd vs Gsb Constructions Pvt Ltd & Ors on 12 January, 2023
Author: Chandra Dhari Singh
Bench: Chandra Dhari Singh ... PURBANCHAL TRADE AND INDUSTRIES LTD ..... Plaintiff
Through: Ms.Radhika Goel, Advocate
versus
GSB CONSTRUCTIONS PVT LTD & ORS. ..... Defendants
Through: Mr.Shree Prakash Sinha
Gsb Construction Pvt.Ltd. vs Jabalpur Devlopment Authy. on 9 February, 2023
Author: Maninder S. Bhatti
Bench: Maninder S. Bhatti
1
IN THE HIGH COURT ... MADHYA PRADESH
AT JABALPUR
WP No. 4430 of 2008
(M/S GSB CONSTRUCTION PVT.LTD. Vs JABALPUR DEVLOPMENT AUTHY. AND OTHERS)
Dated
Gsb Construction Pvt.Ltd. vs Jabalpur Devlopment Authy. on 10 July, 2023
Author: Sanjay Dwivedi
Bench: Sanjay Dwivedi
1
IN THE HIGH COURT OF MADHYA ... PRADESH
AT JABALPUR
WP No. 4430 of 2008
(M/S GSB CONSTRUCTION PVT.LTD. Vs JABALPUR DEVLOPMENT AUTHY. AND OTHERS)
Dated : 10-07-2023
That
Feasibility Report, the
Granular Sub-Base Material (in short, „the GSB‟) was available at the
maximum distance of 190 Kms, and assuming that ... Tribunal
erroneously quantified the claim with respect to additional
transportation charges for GSB taking the lead distance of 134 Km on
the basis of average
scarifying the existing carriageway and rolling the
scarified materials before laying the GSB layer.
5. Apparently, the said instruction was passed on to the
petitioner ... same was possible only after the
scarification was done and before the GSB layer was laid. Anyhow,
it is admitted that the petitioner was subsequently
Dimag
Singh, 26, Ganna Society Market, Khatauli- It
pertains to GSB Work & WMM work for ROB-55,
Mewla Bridge, Meerut. The facts of this ... Developers Limited, Meerut is related to laying of
GSB 115 MM and laying of W.M.M 125 MM Abu Nala
Bridge Meerut.
Thus
April May Avg. June July Aug Sept Avg.
(per (per
month) month)
GSB