Infrastructure Pvt vs Jalore Jaswantpura Bot Project Pvt on 26 February, 2024
9-arbapl-7724-2023.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY ... Infrastructue Pvt. ...Petitioner
V/s.
Jalore Jaswantpura Bot Project Pvt. ...Respondent
----
None for the Applicant.
Mr. Karan Bhide a/w. Mr. Kartikey Kaushik
Infrastructure Pvt vs Jalore Jaswantpura Bot Project Pvt on 27 February, 2024
2024:BHC-OS:3105
902-arbapl-7724-2023.doc
IN THE HIGH COURT ... Infrastructure Pvt. Ltd., .. Applicant.
v/s.
Jalore Jaswantpura Bot Project Pvt. Ltd., .. Respondent.
None for the Applicant.
Mr. Kartikay Kaushik i/b. Dave & Girish
Infrastructure Pvt vs Jalore Jaswantpura Bot Project Pvt on 5 June, 2023
Author: Bharati Dangre
Bench: Bharati Dangre
1/1 M ARBAP ... Infrastructure Pvt. Ltd. .. Applicant
Versus
Jalore Jaswantpura BOT Project Pvt. .. Respondent
Ltd.
WITH
ARBITRATION APPLICATION (L) NO.7727 OF 2023
Sandeep Hirani & Anr. .. Applicants
Infrastructure Pvt vs Jalore Jaswantpura Bot Project Pvt on 11 August, 2023
Author: Bharati Dangre
Bench: Bharati Dangre
Board Sr.No.:-55
IN THE HIGH ... Infrastructure Pvt ....PETITIONER
V/S
Jalore Jaswantpura Bot Project Pvt ....RESPONDENT
None for Applicant.
Mr. Karan Bhide, Counsel a/w. Ms. Hritika Bongale
Infrastructure Pvt vs Jalore Jaswantpura Bot Project Pvt on 19 July, 2023
Author: Bharati Dangre
Bench: Bharati Dangre
Board Sr.No.:-0
IN THE HIGH ... Infrastructure Pvt ....PETITIONER
V/S
Jalore Jaswantpura Bot Project Pvt ....RESPONDENT
CORAM : HON'BLE SMT. JUSTICE BHARATI DANGRE
J
DATE : 19th July
Infra Holdings Ltd - Project codes 1a to
1q
For all the projects of DLF group with project codes
1a to 1q, for which experience ... statutory auditors of the SPV (the project company)
under which these projects have been executed.
For project codes
with a
Class A Electrical Contractor towards execution
of the tendered BOT project.
5 The Bidder should have achieved a
minimum turnover ... 2014 23:48:10 :::
{10}
wp784314.odt
BOT project.
(4) The bidder should have achieved a
minimum turn over of Rs.25 crores
with a
Class A Electrical Contractor towards execution
of the tendered BOT project.
5 The Bidder should have achieved a
minimum turnover ... 2014 23:48:13 :::
{10}
wp784314.odt
BOT project.
(4) The bidder should have achieved a
minimum turn over of Rs.25 crores
appellant. 5.6. The appellant has
stated that the work of BOT projects is handled
by only five divisions of the appellant and the
remaining ... undertake any
(4 of 5)
[ITA-74/2017]
work relating to BOT projects. Therefore,
payment to and provision for employees of these
five divisions
Objection
Certificate (“NOC”) to the MPRTC for the proposed BOT
project. Also, the Deputy Director, Town and Country
Planning granted approval to the MPRTC ... reports, the State
Government, MPRTC and IDA stated that the said BOT
project was in public interest and justified the
Notification dated 11th