1. Operative Period.
- The Scheme shall come into effect from the date of issuance of this order and shall remain in force up to 31st March 2019.2. Definitions.
- (i) "Agri-marketing" means business that derives most of its revenue from agriculture and may cover processing, manufacturing and distribution of agricultural products;".1. the first sale bill of the goods manufactured related to the investment made under the Scheme; or
2. the first bill of commercial transaction related to the investment made under the Scheme; or
3. the first receipt of deposit of fee/ charges etc. for providing any service with respect to facilities set up related to investment under the Scheme; or
Provided that investment made in development of an industrial park, it shall mean the date of handing over of possession to the first unit in the park.1. the first sale bill of the goods manufactured after completion of expansion; or
2. the first bill of commercial transaction after completion of expansion; or
3. the first receipt of deposit of fee/ charges etc. for providing any service with respect to facilities set up after completion of expansion:
Provided that investment made in development of an industrial park, it shall mean the date of handing over of possession to the first unit in the park.3. Applicability of the Scheme.
- 3.1 Subject to clause 3.3 below, the Scheme shall be applicable to the following classes of enterprise(s) and investment, excluding investment mentioned in Annexure-I, appended to the Scheme:(i)New and existing enterprises making investment for setting up new units;(ii)Existing enterprise making investment for expansion; and(iii)Sick enterprises making investment for its revival:provided that the enterprise shall commence commercial production or operation during the operative period of the Scheme.3A. Option to certain enterprise for selection of category.
- Where an eligible enterprise falls under both the categories i.e. manufacturing enterprise and service enterprise, it shall have to opt for benefits in any one of the following two categories, namely:4. Benefits to Manufacturing Enterprises.
- An eligible manufacturing enterprise other than the enterprises as mentioned in part A of annexure IV appended to the scheme and the enterprises engaged in manufacturing of cattle feed/ poultry feed/ fish feed shall be granted benefits and incentives as given below:5. Benefits to Service Enterprises.
- An eligible service enterprise shall be granted benefits and incentives as given below:6. Special Provisions for Women, Scheduled Castes, Scheduled Tribes and Persons with Disability Enterprise.
- Eligible Women/ Schedule Caste (SC)/ Schedule Tribe (ST) / Person with disability (PwD) enterprises shall in addition to the benefits specified in other clauses of the Scheme, be eligible to avail the following additional benefits:7. Benefits to Enterprises in Backward and Most Backward Areas.
- An eligible enterprise, other than a cement manufacturing enterprise, making investment in a backward area or a most backward area shall be granted the same benefits as would have been applicable if the enterprise was located elsewhere in the state but the period of benefit, except for interest subsidy, shall be extended to ten years.Provided that the State Government may, on the recommendation of the State Empowered Committee (SEC), grant to a manufacturing enterprise, other than a cement manufacturing enterprise and a service enterprise making an investment in a backward area, such benefits as mentioned in clauses 7.2 and 7.3 respectively, which are applicable for investments in most backward areas, with a view to attract investment in the backward area.7. [1.1 An eligible enterprise, other than a cement manufacturing enterprise, making investment in a backward area shall be granted the following additional benefits in addition to the benefits under clause 7.1 above:
(i)Additional investment subsidy of 15% of the VAT and CST, which have become due and have been deposited by the enterprise for a period of seven years;(ii)50% exemption from payment of Electricity Duty; and(iii)50% exemption from payment of conversion charges payable on change of land use; and(iv)0.5% special interest subsidy, if enterprise is eligible for interest subsidy under the scheme.8. Power to Grant Customized Package.
- Notwithstanding anything contained in the Scheme, the State Government, on the recommendation of State Empowered Committee (SEC), may grant a customized package under section 11 of the Rajasthan Enterprises Single Window Enabling and Clearance Act, 2011, to the following manufacturing enterprises, other than cement manufacturing enterprises:(a)Enterprises investing more than Rs. 100 crore or providing minimum employment to 200 persons, in most backward areas as notified under the Scheme; or(b)Enterprises investing more than Rs. 200 crore or providing minimum employment to 250 persons, in backward areas as notified under the Scheme; or(c)Enterprises investing more than Rs. 400 crore or providing employment to more than 400 persons, in general area; or(d)Enterprises investing more than Rs. 100 crore and using the mineral mentioned in Annexure-III appended to the Scheme, as main raw material; or(e)Enterprises investing Rs. 100 crore or more, or providing employment to at least 250 persons, in Agro-processing and Agri-marketing sector; or(f)Enterprises investing more than Rs. 100 crore and providing employment to more than 200 persons in Bio-Technology sector.9. Benefits to Manufacturing Enterprises in Thrust Sectors.
- 9.1. Notwithstanding anything contained in the Scheme, the State Government may grant a special package of incentives and exemptions, which may be over and above the incentives and exemptions under Clauses 4 to 7 to a manufacturing enterprise in a thrust sector in addition to the thrust sectors mentioned in sub-clause 9.3 to 9.189. [17.5 100% exemption from payment of conversion charges under sub-rule (2-A) of Rule 8 of the Rajasthan Land Revenue (Conversion of Agricultural Land for Non-agricultural Purposes in Rural Areas) Rules, 2007 for setting up of Agro-Processing and Agri-Marketing Enterprise whose project is sanctioned before 31st March, 2019 under the Rajasthan Processing and Agri-Marketing Promotion Policy, 2015.] [Inserted by Rajasthan Notification No. F. 12(105) FD/Tax/2014-Part-I-54, dated 9.11.2016 (w.e.f. 8.10.2014).]
9A. Benefits To Service Enterprise In Thrust Sector.
- 9A.1 Service enterprises in the sectors mentioned hereunder shall be allowed benefits as mentioned in the relevant sector, in addition to benefits mentioned in clauses 5, 6 and 7, if applicable.9A.
2. IT Sector. - 9A.2.1 Enterprises making a minimum investment of twenty five lac rupees in the IT sector shall be granted 5% interest subsidy on the term loan taken from State Financial Institutions/Financial Institution/Bank recognized by Reserve Bank of India for making investment in service related to IT sector, for a period of five years or up to the period of repayment of loan, whichever is earlier, from the date of commencement of commercial operation, subject to a maximum of five lac rupees per annum i.e. twelve calendar months, on the conditions as laid down in clause 10.9 of the Scheme;
9A.
9A.
3. Bio-technology Sector. - 9A.3.1 Enterprises making a minimum investment of rupees twenty five crore in the Biotechnology sector shall be granted the following benefits:
10. Provisions Related to Benefits.
- 10.1. Maximum Extent of Subsidy: The maximum amount of subsidy (investment subsidy + employment generation subsidy + additional Investment subsidy) in any period shall not exceed the amount of VAT and CST due and paid in that period. Moreover, for the enterprises other than those making investment in the Backward Area and Most backward Area the total amount of subsidy paid shall not exceed the eligible fix capital investment as approved by the appropriate Screening Committee.11. Procedure for Claiming Incentives.
- Claims for Exemption from Stamp Duty and/or Conversion Charges:11.1.1The enterprise making investment for setting up of a new enterprise or for expansion or for revival of Sick Industrial Enterprise under the Scheme, shall submit a duly completed application in Form-I, appended to the Scheme, for availing exemption from Stamp duty/ Conversion Charges, along with a project report duly certified by a Chartered Accountant and a self-attested declaration in support of the facts of the application], to the Member Secretary of the appropriate Screening Committee. In case of revival of sick industrial enterprise, the enterprise shall also submit an undertaking that it shall provide employment to the extent of 50% in the first two years, of the maximum level of employment attained in the preceding 3 years from the date of its declaration as a sick industrial enterprise, followed by 100% employment within five years.11.1.2The Member Secretary of the appropriate Screening Committee, on receipt of such application shall register the application and shall examine the applicability of the scheme for applicant enterprise, and in case he is of the view that,-(i)the scheme is applicable to the applicant enterprise he shall register the application and issue an entitlement certificate in Form-II, appended to the Scheme, immediately but not later than seven days, unless specifically extended for reasons to be recorded in writing. The certificate so issued shall be valid for two years or up to the date of expiry of the operative period of the Scheme, whichever is earlier. However, in case the Member Secretary of the appropriate Screening Committee is of the opinion that the entitlement certificate could not be utilized by the applicant investor due to reasons largely beyond his control, validity of the certificate can further be extended, for two years or up to the date of expiry of the operative period of the Scheme whichever is earlier; and(ii)the scheme is not applicable to the applicant enterprise, he shall pass an order in Form IX-A appended to the Scheme and shall forward the same to the applicant enterprise. The Member Secretary shall inform the enterprise to appear before the Screening Committee on the date on which such order is placed before the Appropriate Screening Committee for approval.11.1.3The Member Secretary of the appropriate Screening Committee shall forward copies of the entitlement certificate in Form-II, appended to the Scheme, to the concerned Department / authority immediately. Thereupon, the stamp duty and/or conversion charges would be exempted to the extent as provided in clause 4 and 5 of the Scheme.11.1.4The Member Secretary of the appropriate Screening Committee shall place the application in Form-I, and the exemption certificate issued by him in Form-II or order in Form IX A, as the case may be, before the appropriate Screening Committee for approval in the next meeting of such committee. The committee shall examine the case and if it is found that:(i)the Entitlement certificate so issued or the order so passed is proper, it shall approve the same;(ii)the order so passed is erroneous, it shall direct the Member Secretary to grant the entitlement certificate; and(iii)the certificate so issued/order so passed is erroneous and prejudicial to the interest of the State Government, it shall revoke the same, after affording an opportunity of being heard to the beneficiary enterprise.12. Procedure for Disbursement of Subsidy.
- For disbursement of investment subsidy, the enterprise to which an entitlement certificate under the Scheme has been issued shall inform this fact by submitting the detail thereof, electronically through the official website of the Commercial Taxes Department in the manner as provided therein, to the Assistant Commissioner/ Commercial Taxes Officer of the area where the enterprise is registered with the Commercial Taxes Department.12.1.2Such beneficiary enterprise, after submitting the quarterly return(s), shall furnish information regarding claim of investment subsidy through the official website of the Commercial Taxes Department in the manner as provided therein.12.1.3The officer concerned, on the receipt of such information shall pass an order for sanction cum disbursement of investment subsidy electronically through the official website of the Commercial Taxes Department, within thirty days from the receipt of such application, for each quarter, in form VAT-37B, subject to availability of budget provisions.12.1.4The said sanction in Form VAT-37B shall be forwarded to the concerned Treasury Officer for deposit of subsidy amount for the subsequent tax period(s) of the applicant by way of adjustment through treasury Book Transfer (BT).12.1.5The Treasury Officer shall take necessary steps to pass adjustment order Book Transfer (BT) without any delay and shall forward two copies of duly adjusted Form VAT-37B to the Assistant Commissioner/ Commercial Taxes Officer. A copy of same shall also be forwarded to the office of the Accountant General. The Assistant Commissioner/ Commercial Taxes Officer shall forward a copy of Form VAT-37B to the applicant as a proof of disbursement of subsidy.12.1.6Any order passed under this clause by the Assistant Commissioner/ Commercial Taxes Officer shall be subject to the provisions of the Rajasthan Value Added Tax Act, 2003, the Central Sales Tax Act, 1956 and rules made there under. The provisions of Recovery and Appeal in the said Act(s) shall apply mutatis mutandis for such orders.12.
4A.
2. For disbursement of subsidy, the enterprise after having received the Entitlement Certificate shall apply on annual basis in the Form- XXIIA appended to the Scheme.
12.
4A.
3. The application for disbursement of interest subsidy shall be accompanied by certificate of concerned bank/financial institution, certifying the repayment of Principal Amount and Interest by the enterprise in the quarter. The bank will also certify if there is any default in repayment of Principal Amount/Interest.
12.
4A.
4. Commissioner Industries or any officer authorized by him shall pass an order for sanction of subsidy on quarterly basis. Subsidy will be disbursed to the enterprise through demand draft /pay order/cheque/by remittance into the bank account of the enterprise.
12.
4A.
5. Commissioner Industries shall maintain the information related to eligible Investment, subsidy disbursed and period availed/ balance in Form- XXIII appended to the Scheme.
13. Provisions for E-Governance.
- All Government Departments responsible for the grant of benefits under the Scheme shall endeavor to enable electronic delivery of services under the Scheme in a time bound manner.13A. Transfer of benefits in case of transfer of business.
- 13A.1 When the ownership of a unit of an enterprise availing benefit of the scheme is entirely transferred in any manner, then the remaining benefits of such unit under the scheme, if any, shall be transferred to the transferee enterprise.13A.
2. For availing such remaining benefits, the transferee enterprise shall submit a duly completed application in Form-VIIA appended to the scheme, to the Member Secretary of the appropriate Screening Committee along with proof of transfer of ownership of unit and original Entitlement Certificate(s) issued to the transferor enterprise, within ninety days of such transfer.
13A.
3. The Member Secretary of the appropriate Screening Committee shall register the application and place the completed application before the appropriate Screening Committee within forty five days from the receipt of application unless specifically extended for reasons to be recorded in writing.
13A.
4. Where the application has been filed beyond the time period as provided in clause 13A.2 above, the appropriate Screening Committee having been satisfied with the genuineness of cause of delay may condone the delay in filing of the application from the prescribed date of application.
13A.
5. In case the committee approves the transfer of ownership, the Member Secretary shall amend the entitlement certificate(s) by making an endorsement in the said certificate(s) as under;
"The benefits under this certificate is hereby transferred to M/s ............................, and the said enterprise is entitled to avail the benefits mentioned in this certificate for a period from ...... to ......".13A.
6. After such endorsement, the Member Secretary shall forward it to all concerned immediately but not later than fifteen days from the date of decision taken by the committee in its meeting, unless specifically extended for reasons to be recorded in writing.
13A.
7. Where the committee is of the opinion that the transferee enterprise is not eligible to avail the remaining benefits of the Scheme, it shall provide an opportunity of being heard to such enterprise and shall record the reasons of rejection. The decision of the committee shall be communicated in Form-XXXIV, appended to the Scheme, by the Member Secretary of the appropriate screening committee to the enterprise and all concerned immediately but not later than thirty days from the date of decision taken by the committee in its meeting, unless specifically extended for reasons to be recorded in writing.
14. Terms and Conditions.
- 14.1 The enterprise availing benefits under the Scheme shall comply with all statutory laws and regulations of the State of Rajasthan applicable to the enterprise. Non-compliance may entail cancellation/ withdrawal of the benefits under the Scheme.15. Breach of Condition.
- In case of breach of any of the condition mentioned anywhere in the Scheme, the benefits availed under the Scheme, shall be withdrawn by the appropriate Screening Committee and on its recommendation the concerned Department shall recover the benefits availed by the enterprise along with interest @ 18% per annum from the date from which the benefits have been availed.16. Authority for Implementation/Interpretation.
- All the related Departments shall implement the Scheme. The Industries Department shall act as the nodal coordinating, monitoring and implementing Department. Any matter pertaining to interpretation of any clause of the Scheme shall be referred to the Government of Rajasthan in the Finance Department. The decision of Finance Department in such matters shall be final.17. Rectification of a Mistake.
- 17.1 Rectification by State Level Screening Committee or District Level Screening Committee:17.1.1With a view to rectify any mistake apparent on record, the State Level Screening Committee may either suo motu or on an application in this behalf, may rectify any order passed by it or the District Level Screening Committee.Explanation. - A mistake shall include an order which was valid when it was made and is subsequently rendered invalid by an amendment of the scheme having retrospective operation or by a judgment of the Supreme Court, or the Rajasthan High Court.17.1.2No application for rectification shall be filed under clause 17.1.1 after the expiry of a period of three years from the date of the order sought to be rectified.17.1.3An application under clause 17.1.1 shall be presented to the member secretary of the State Level Screening Committee. The Member Secretary shall place such application before the State Level Screening Committee within forty five days from the receipt of the application unless specifically extended for reasons to be recorded in writing.17.1.4The State Level Screening Committee shall dispose of such application within a period of one hundred eighty days from the date of submission of the application.17.1.5No order of rectification shall be made after the expiry of four years from the date of the order sought to be rectified.17.1.6An order of rectification which has the effect of reducing the benefits of an enterprise in any way, shall not be made without affording it an opportunity of being heard.18. Appeal.
- 18.1 The State Level Screening Committee shall be empowered to hear and decide appeals against the orders of District Level Screening Committee.18A. Review by State Level Screening Committee (SLSC).
19. Revision by the State Government.
20. Review or Modification of Scheme.
- The State Government in the Finance Department, in consultation with Industries Department reserves the right to review or modify the Scheme as and when needed in public interest.However, Forms appended to the Scheme may be modified, changed, added or deleted by Finance Department as and when needed for the sake of convenience in implementation of the Scheme.Annexure-IInvestment not eligible for benefits of subsidies and/or exemptions under the Rajasthan Investment Promotion Scheme-20141. Investment for manufacturing Tobacco products, Pan Masala containing tobacco and Gutka.
2. [ ***] [Deleted 'Investment in all kinds of edible oil extracting or manufacturing industry including ghanies, expellers except solvent extraction plants with Oil Refineries.' by Rajasthan Notification No. F. 12(14) FD/Tax/2017-125, dated 8.3.2017 (w.e.f. 8.10.2014).]
3. Investment for manufacturing and bottling of potable liquor and beer.
4. Investment in stand-alone bottling or packaging plants including stand-alone bottling/ packaging plants for potable liquor, beer, drinking water or aerated drinks.
5. Investment made for manufacturing of such goods as may be specified by the State Government, in the Finance Department.
6. Investment made in Vegetable milling units other than those mentioned in Part B of Annexure IV.
7. Investment made in beef meat processing Units.
8. Investment made in processing units discharging toxic effluent without having effluent treatment plant.
9. Investment made in Production of cereals/pulses/seeds except as provided specifically in the Rajasthan Agro-processing and Agri-Marketing Promotion Policy, 2015; and
10. Investment made in activities related to splitting of pulses.
Annexure-IIScreening Committee under Clause 2(xxxi) of the Scheme| S.No. | Category of Enterprise | Screening Committee | Status |
| 1. | MSME | District Level Screening Committee (DLSC) | |
| (a) District Collector | Chairman | ||
| (b) Concerned Branch Manager of RFC in theDistrict | Member | ||
| (c) Concerned Senior Regional Manager/RegionalManager of RIICO in the District | Member | ||
| (d) Deputy/Assistant Commissioner, CommercialTaxes/Commercial Taxes Officer of Commercial Taxes Department | Member | ||
| (e) Officer not below the rank of executiveengineer, as nominated by Secretary, Energy | Member | ||
| (f) Secretary of relevant Krishi Upaj MandiSamiti (In case of exemption from Mandi Fee) | Member | ||
| (g) General Manager DIC | Member-Secretary | ||
| 2. | Large Enterprises and Service Enterprises | State Level Screening Committee (SLSC) | |
| (a) Principal Secretary, Industries | Chairman | ||
| (b) Secretary, Finance (Revenue) | Member | ||
| (c) Secretary, Energy | Member | ||
| (d) Commissioner, Investment & NRIs (BIP) | Member | ||
| (e) Commissioner, Commercial Taxes | Member | ||
| (f) CMD, RFC | Member | ||
| (g) MD, RIICO | Member | ||
| (h) Director, Agriculture Marketing Board (Incase of exemption from Mandi Fee) | Member | ||
| (i) Commissioner, Industries | Member-Secretary |
| S.No. | Name of Mineral | S.No. | Name of Mineral | |
| 1. | Jasper | 10. | Talc/Soapstone/Steatite | |
| 2. | Calcite | 11. | Quartzite | |
| 3. | Selenite | 12. | Manganese | |
| 4. | Ochre | 13. | Natural Gas utilized | |
| 5. | Phosphorite (Rock Phosphate) | 14. | Felspar | |
| 6. | Lead & Zinc | 15. | Copper Concentrate | |
| 7. | Wollastonite | 16. | Barytes | |
| 8. | Gypsum | 17. | Iron Ore | |
| 9. | Silver |
| S. No. | Description of activities |
| PART A | |
| Post-Harvest crop activities | |
| 1. | Preparation of crops for primary markets, i.e.,cleaning, trimming, grading, disinfecting |
| 2. | Ripening of Fruits & vegetables |
| 3. | Seed processing for propagation |
| 4. [ [Substituted by Rajasthan Notification No. F. 12(105) FD/Tax/2014-Part-I-54, dated 9.11.2016 (w.e.f. 8.10.2014).] | Packaging of Fruits, Vegetables &horticulture productsproducts inculding medicinal/aromatic plants, herabal plants and minorforest products] |
| 5. | Warehousing refrigerated |
| PART B | |
| (a) Manufacturing and Processing of Animalproducts mentioned below | |
| 1. | Processing and preserving of meat/meat products |
| 2. | Processing, preservation and canning of Poultrymeat |
| 3. | Processing and preserving of fish, and canningof fish and products thereof |
| 4. | Artificial dehydration of fish |
| 5. | Radiation preservation of fish and similar food |
| 6. | Production of fishmeal for human consumption oranimal feed |
| (b) Manufacturing and Processing of Agriproducts mentioned below | |
| 1. | Processing and preserving of fruits andvegetables, Canning of fruits and vegetables |
| 2. | Processing of Flowers |
| 3. | Artificial dehydration of fruits and vegetables |
| 4. | Radiation/steam sterilization, of fruits &vegetables and other agricultural commodities |
| 5. | Manufacture of fruit and vegetable juices ortheir concentrates, squashes and powder |
| 6. | Manufacture of sauces, jams, jellies |
| 7. | Manufacture of pickles, chutney etc |
| (c) Manufacturing of cereal breakfastobtained by roasting or swelling of cereal grains | |
| 1. | Manufacturing of starch, starch products andMalt |
| 2. | Processing of medicinal/Aromatic plants andminor forest products |
| 3. | Processing of spices and condiments |
| 4. | Flour Mill units manufacturing Atta, Maida, Sujiand Besan, if the investment is more than rupees two crore |
| 1. | Name of the applicant Enterprise | ||
| 2. | Address of the applicant Enterprise | ||
| e-mail Address | |||
| 3. | Constitution ofEnterprise:Proprietorship/Partnership/Company/Society, etc. | ||
| 4. | Whether Board of Directors (in case of company)has passed resolutions to authorize undersigned to do everythingnecessary for exemption (if yes, attach copies) | ||
| 5. | Basis of enterprise being an enterprise underNew/Expansion/Sick industrial enterprise | ||
| 6. | Goods manufactured/Services provided (or goodslikely to be manufactured/Services likely to be provided) | ||
| 7. | Exemption/Subsidy previously availed | ||
| (1) Under RIPS - 2010 | |||
| (2) Under RIPS - 2003 | |||
| (3) Under any other Scheme (Please Specify) | |||
| 8. | Total investment (as per project report) | ||
| 9. | Total Number of workers (or likely to beengaged) | ||
| 10 | For the units going under Expansion | ||
| (a) Investment in Existing Unit | |||
| (b) Investment made under Expansion | |||
| (c) Increase in Investment | |||
| 11. | In case of Sick industrial enterprise maximumlevel of employment attained in the preceding 3 years from thedate of declaration as a sick industrial enterprise | ||
| 12. | Status of Rajasthan State Pollution ControlBoard's approval | ||
| Approval No. | Approval Date | ||
| Consent to establish obtained | |||
| Consent To Operate obtained | |||
| 13. | Exemption applied for | ||
| 1. Stamp Duty | Yes/No | ||
| 2. Conversion Charges | Yes/No | ||
| 3. Land Tax | Yes/No | ||
| 4. Luxury Tax | Yes/No | ||
| 5. Electricity Duty | Yes/No | ||
| 6. Entertainment Tax | Yes/No | ||
| 7. Mandi Fee | Yes/No | ||
| 8. Entry Tax | Yes/No | ||
| 14 | Whether the enterprise is in thrust sector | Yes/No | |
| If yes, please give name of the Thrust Sector |
1. Copy of Project Report
2. Self attested declaration in support of facts of the application
3. Proof of investment
4. Copies of Challan of EPF/ESI/Insurance Policy
5. [proof of deposit of VAT/CST] [Substituted 'Proof of Deposit of VAT/CST/SGST' by Rajasthan Notification No. F. 12(14) FD/Tax/2017-125, dated 8.3.2017 (w.e.f. 8.10.2014).]
6. Copy of resolution
7. Others (Please Specify)
Form - II[See clause 11.1.2]Entitlement Certificate[For Exemption from Stamp Duty and/or Conversion Charges](Under Rajasthan Investment Promotion Scheme - 2014)Book No.S.No.It is certified that M/s............................................. whose application for the project ............................................................... at .................................................................... (address), has been registered at No ................. dated ............................., and based on his declaration, he is entitled to avail exemptions as under:| S.No. | Name of Exemption | Extent of Exemption | Notification No. and Date |
| (i) | Exemption from the Stamp Duty | ||
| (ii) | Exemption from Conversion Charges |
1. M/s ......................
2. Concerned Department
Member Secretary*The relevant authority of Government of Rajasthan responsible for administering these duties and/or levies, suo motu or on being informed otherwise, shall recover the amount so exempted along with interest @ 18% per annum, in case of any violation of the provisions contained in the Rajasthan Investment Promotion Scheme, 2014, by the bearer of this Certificate.Form - III[See clause 11.2.2]Provisional Entitlement Certificate[For Exemption from Land Tax](Under Rajasthan Investment Promotion Scheme - 2014)Book No.S.No.It is certified that M/s............................................. whose application for the project ..................................................................... at ............................................................... (address), has been registered at No................................ dated............................., and based on his declaration, he is entitled to provisionally avail exemption as under| S.No. | Name of Exemption | Extent of Exemption | Notification No. and Date |
| (i) | Exemption from Land Tax |
1. M/s ......................
2. Concerned Department
Member Secretary*The relevant authority of Government of Rajasthan responsible for administering these duties and/or levies, suo motu or on being informed otherwise, shall recover the amount so exempted along with interest @ 18% per annum, in case of any violation of the provisions contained in the Rajasthan Investment Promotion Scheme, 2014, by the bearer of this Certificate.Form - IV[See clause 11.2.4]Permanent Entitlement Certificate[For Exemption from Land Tax](Under Rajasthan Investment Promotion Scheme - 2014)Book No.S.No.It is certified that on the recommendation made by the State/District Level Screening Committee in its meeting dated................ M/s.......................................................... is entitled to avail exemption as under:| S.No. | Name of Exemption | Extent of Exemption | Notification No. and Date |
| (i) | Exemption from Land Tax |
1. M/s ......................
2. Concerned Department
Member Secretary*The relevant authority of Government of Rajasthan responsible for administering these duties and/or levies, suo moto or on being informed otherwise, shall recover the amount so exempted along with interest @ 18% per annum, in case of any violation of the provisions contained in the Rajasthan Investment Promotion Scheme, 2014, by the bearer of this Certificate.Form - V[See clause 11.3.4]Entitlement Certificate(Under Rajasthan Investment Promotion Scheme - 2014)(For Exemption from Luxury Tax/ Electricity Duty/ Entertainment Tax/ Mandi Fee/ Entry Tax)Book No.S.No.It is certified that M/s ............................................... whose application for the project ....................................................................................................at ...................... has commenced commercial production/operation from ....................... (date), is entitled to avail exemptions as under:| S.No. | Category of Enterprise | Extent of Exemption | Period of Exemption | Notification No. and date |
| 1 | 2 | 3 | 4 | 5 |
| 1 | Exemption from Luxury Tax | |||
| 2 | Exemption from Electricity Duty | |||
| 3 | Exemption from Entertainment Tax | |||
| 4 | Exemption from Mandi Fee | |||
| 5 | Exemption from Entry Tax on capital goods orequipment, as approved by the appropriate screening committee | Brought in to the local Area before the date ofcommencement of commercial production / operation, or for......years |
1. M/s ......................
2. Concerned Department
Member Secretary*The relevant authority of Government of Rajasthan responsible for administering these duties and/or levies, suo moto or on being informed otherwise, shall recover the amount so exempted along with interest @ 18% per annum, in case of any violation of the provisions contained in the Rajasthan Investment Promotion Scheme, 2014, by the bearer of this Certificate.Note. - 1. This certificate is liable to amendment/ suspension/ revocation, if' obtained on misrepresentation or concealment of facts or by fraud or on breach of any of the terms and conditions, mentioned in the relevant notification.2. This certificate may be revoked by the issuing authority in case the applicant violates any of the conditions of the Scheme.
Form - VI[See clause 11.4.1](For New Enterprise or Sick industrial enterprise)Application for grant of Entitlement Certificate for Subsidy(Under Rajasthan Investment Promotion Scheme - 2014)| 1 | Name of the Applicant Enterprise | ||
| 2 | Address of the Applicant Enterprise | ||
| E-mail address | |||
| 3 | Registration No. with Commercial TaxesDepartment (TIN) | ||
| 4 | Location of factory, in case of ManufacturingEnterprise | ||
| 5 | Constitution of enterprise:Proprietorship/Partnership/Company/Society etc. | ||
| 6 | Whether Board of Directors (in case of company)has passed resolutions to authorize undersigned to do everythingnecessary for exemption (if yes, attach copies) | ||
| 7 | Goods manufactured/Service provided | ||
| 8 | Basis of enterprise being an enterprise underNew enterprise/Sick industrial enterprise | ||
| 9 | Date of commencement of commercialproduction/operation | ||
| 10 | Exemption/Subsidy previously availed | ||
| (1) Under RIPS - 2010 | |||
| (2) Under RIPS- 2003 | |||
| (3) Under any other Scheme (Please Specify) | |||
| 11 | Total investment made in fixed assets (as perproject report) | ||
| (i) Price paid for land | |||
| (ii) cost of factory sheds and other industrialbuildings | |||
| (iii) Price paid for new plant and machinery | |||
| (iv) other investment made in fixed assetsessential for production of the unit | |||
| (v) Amount paid for technical know-how fees ordrawing fees paid to foreign collaborators or foreign suppliersor paid to laboratories recognized by the State Government or theGovernment of India | |||
| 12 | For the units going under Expansion | ||
| (a) Investment in Existing Unit | |||
| (b) Investment made under Expansion | |||
| (c) Increase in Investment | |||
| 13 | In case of sick industrial enterprise maximumlevel of employment attained in the preceding 3 years from thedate of declaration as a sick industrial enterprise | ||
| 14 | Total Number of workers (or likely to beengaged) | ||
| 15 | Whether the enterprise is in thrust sector | Yes/No | |
| If yes, please give name of the thrust Sector | |||
| 16. | Status of Rajasthan State Pollution ControlBoard's approval | ||
| Approval No. | Approval Date | ||
| Consent to establish obtained | |||
| Consent To Operate obtained |
1. Proof of investment
2. Copy of project report
3. Copies of Challan of EPF/ESI/Insurance Policy,
4. [Proof of Deposit of VAT/CST, if any] [Substituted 'Proof of Deposit of VAT/CST/SGST' by Rajasthan Notification No. F. 12(14) FD/Tax/2017-125, dated 8.3.2017 (w.e.f. 8.10.2014).]
5. Certificate of Chartered Accountant regarding valuation
6. Self-attested declaration in support of facts of the application
7. Copy of resolution
Form - VII[See clause 11.4.1](For Enterprises making investment on expansion)Application for Grant of Entitlement Certificate for Subsidy(Under Rajasthan Investment Promotion Scheme - 2014)| 1 | Name of the Applicant Enterprise | |||
| 2 | Address of the Applicant Enterprise | |||
| e-mail address | ||||
| 3 | Registration No. with Commercial TaxesDepartment (TIN) | |||
| 4 | Location of factory, in case of ManufacturingEnterprise | |||
| 5 | Constitution of enterprise:Proprietorship/Partnership/Company/Society, etc. | |||
| 6 | Whether Board of Directors (in case of company)has passed resolutions to authorize undersigned to do everythingnecessary for exemption (if yes, attach copies) | |||
| 7 | Exemption/Subsidy previously availed | |||
| (1) Under RIPS - 2010 | ||||
| (2) Under RIPS - 2003 | ||||
| (3) Under any other Scheme (Please Specify) | ||||
| 8 | Total investment made in fixed assets (as perproject report) | |||
| (i) Price paid for land | ||||
| (ii) Price paid for new plant and machinery | ||||
| (iii) Investment made in fixed assets other thanabove (i) to (ii) | ||||
| (iv) Amount paid for technical knowhow a fees ordrawing fees paid to foreign collaborators or foreign suppliersor paid to laboratories recognized by the State Government or theGovernment of India | ||||
| (v) Others, if any | ||||
| 9 | Total Number of workers (or likely to beengaged) | |||
| 10 | For the units going under Expansion | |||
| (a) Investment in Existing Unit | ||||
| (b) Investment made under Expansion | ||||
| (c) Increase in Investment | ||||
| (d) Period during which Expansion executed: | From ...To... | |||
| (e) Number of employees Pre-Expansion | ||||
| (f) Number of employees Post-Expansion | ||||
| 11 | Date of commencement of commercial productionafter completing Expansion: | |||
| 12 | Whether the enterprise is in thrust sector | Yes/No | ||
| If yes, please give name of the thrust Sector | ||||
| 13 | Status of Rajasthan State Pollution ControlBoard's approval | |||
| Approval No. | Approval Date | |||
| Consent to establish obtained | ||||
| Consent to Operate obtained | ||||
| To be filled in caseof Expansion: Details of amount of investment, in the threeConsecutive years immediately preceding to the year of expansion(Rs in lakh) | In the Year Immediately preceding to the year ofexpansion | In the Second Year Immediately preceding to theyear of expansion | In the Third Year Immediately preceding to theyear of expansion | |
1. Proof of investment
2. Copy of project report
3. Copies of Challan of EPF/ESI/Insurance Policy,
4. [Proof of Deposit of VAT/CST, if any] [Substituted 'Proof of Deposit of VAT/CST/SGST' by Rajasthan Notification No. F. 12(14) FD/Tax/2017-125, dated 8.3.2017 (w.e.f. 8.10.2014).]
5. Certificate of Chartered Accountant regarding valuation
6. Self attested declaration in support of facts of the application
7. Copy of resolution
8. Others, Please specify
"Form - VIIA[See clause 13A.2](For Transfer of remaining benefits of the transferor enterprises)Application for Amendment in Entitlement Certificate(Under Rajasthan Investment Promotion Scheme - 2014)| 1. | Name of the Transferee Enterprise | |||||||
| Address of the Transferee Enterprise | ||||||||
| e-mail address | ||||||||
| Registration No. with Commercial TaxesDepartment (TIN) | ||||||||
| Location of unit transferred | ||||||||
| Constitution of Transferee enterprise :Proprietorship/ Partnership/ Company/ Society etc. | ||||||||
| Whether Board of Directors (in case of company)has passed resolution to authorize applicant to do everythingnecessary (if yes, attach copies) | ||||||||
| 2. | Name of the Transferor Enterprise | |||||||
| Address of the Transferor Enterprise | ||||||||
| e-mail address | ||||||||
| Registration No. with Commercial TaxesDepartment (TIN) | ||||||||
| Constitution of Transferor enterprise :Proprietorship/ Partnership/Company/ Society etc. | ||||||||
| 3 | Exemption Allowed to Transferor Enterprise: | |||||||
| Name of exemption | Entitlement Certificate No. | Date of Issuance of Entitlement Certificate | Extent of Exemption | Period of Exemption | Period up to which exemption has been availed | |||
| From | To | From | To | |||||
| Electricity Duty | ||||||||
| Luxury Tax | ||||||||
| Entry Tax | ||||||||
| Land Tax | ||||||||
| Mandi Fee | ||||||||
| 4 | Subsidy allowed to the Transferor Enterprise | |||||||
| Name of Subsidy | Entitlement Certificate No. | Date of Issuance of Entitlement Certificate | EFCI/Maximum extent of subsidy | Period of subsidy | Period up to which subsidy has been claimed | Amount up to which subsidy has been claimed | ||
| From | To | From | To | |||||
| Investment Subsidy | ||||||||
| Employment Generation Subsidy | ||||||||
| Additional Subsidy | ||||||||
| Interest Subsidy | ||||||||
| Capital subsidy on Zero Liquid dischargetreatment Plant | ||||||||
| 5. | Reimbursement of VAT | |||||||
| Name of Reimbursement | Entitlement Certificate No. | Date of Issuance of Entitlement Certificate | EFCI/Maximum extent of Reimbursement | Period of subsidy | Period up to which Reimbursement has beenclaimed | Amount up to which Reimbursement has beenclaimed | ||
| From | To | From | To | |||||
| On Purchase of Plant,Machinery or equipment | ||||||||
| On purchase of Raw Material |
1. Proof of Transfer of business
2. Copy (ies)of Entitlement Certificate
3. Others, Please specify]
Form - VIII[See clause 11.4.5]Entitlement Certificate for Subsidy(Under Rajasthan Investment Promotion Scheme - 2014)| 1. | Book No | |
| 2. | S. No. | |
| 3. | Name of the applicant with status | |
| 4. | Principal place of business | |
| 5. | Branches or other place of business, if any | |
| 6. | Date of the meeting of State/District LevelScreening Committee in which eligibility for subsidy wasdetermined: | |
| 7. | Amount of eligible fixed capital investment | |
| 8. | Basis for eligibility under RIPS | |
| (a) New Enterprise | ||
| (b) Expansion | ||
| (c) Sick Industrial Unit | ||
| 9. | Whether the enterprise is: | |
| (i) Women/SC/ST/Person with disability (PwD) | Yes/No | |
| (ii) located in backward area | Yes/No | |
| (iii) located in most backward area | Yes/No | |
| (iv) related to thrust area | Yes/No | |
| If yes, specify the thrust area | ||
| 10. | In case of expansion/Revival of sickenterprise: Eligible amount of subsidy:Maximum amount ofadditional tax (VAT+CST) payable and deposited after expansion orrevival, as the case may be, over and above the maximum annualtax (VAT+ CST) payable for any of the three years immediatelypreceding to the year of expansion. | |
| 11. | In case of expansion: Eligible Number ofemployees for Employment Generation Subsidy(Number ofemployees appointed under expansion which are above the existingemployees) | |
| 12. | In case of Revival of sick industrialenterprise: Eligible Number of employees for EmploymentGeneration Subsidy(Number of employees appointed over andabove the maximum employment level attaining during the precedingthree years from the date of its declaration as sick industrialenterprise.) |
2. This certificate may be revoked by the issuing authority in case the applicant violates any of the conditions of the Scheme.
3. The relevant tax authority for the time being is..............................
Place :Date :(Signature with Seal)Member SecretaryState/District Level Screening Committee[Form - IX [Substituted by Rajasthan Notification No. F. 12(14) FD/Tax/2017-125, dated 8.3.2017 (w.e.f. 8.10.2014).]][See clause 12.2.1]Application for Disbursement of Employment Generation Subsidy(Under Rajasthan Investment Promotion Scheme - 2014)ToThe Assistant Commissioner/Commercial Taxes OfficerCircle .........................Period: From ...............To ...............| 1. | Name of the applicant Enterprise | |
| 2. | Address of the applicant Enterprise | |
| e-mail address | ||
| 3. | Registration No. with Commercial TaxesDepartment - TIN | |
| 4. | Entitlement Certificate No. | |
| 5. | Subsidy Applied For the Year (Period) | |
| 6. | Amount of Tax due for the Year [(VAT+CST)] | |
| 7. | Amount of Tax deposited for the Year[(VAT+CST)] | |
| 8. | 50% of Tax deposited | |
| 9. | Whether the enterprise is: | |
| Women/SC/ST/Person with disability (PwD) | Yes/No | |
| located in backward area | Yes/No | |
| located in most backward area | Yes/No | |
| related to thrust area | Yes/No | |
| If yes, specify the thrust area | ||
| 10. | Investment Subsidy availed/applied for the year | |
| 11. | Total Number of employees in New Enterprise or TotalNumber of employees in New Unit in case the existing enterprise has madeinvestment for setting up to new unit | |
| 12. | Total Number of employees appointed under expansionwhich are above the existing employees, in case of expansion. | |
| 13. | Total Number of employees appointed over and above themaximum employment level attaining during the preceding three yearsfrom the date of its deceleration as sick industrial enterprise, in caseof revival of sick enterprise | |
| 14. | Numbers of Women/SC/ST/PersonWith Disability (PwD) employees | |
| To be filled enterprise located in backward or mostbackward area | ||
| (i) Bonafide residents of Rajasthan | ||
| (ii) Others | ||
| 15. | Numbers of employees other than Women/SC/ST/PersonWith Disability (PwD) | |
| To be filled enterprise located in backward or mostbackward area | ||
| (i) Bonafide residents of Rajasthan | ||
| (ii) Others | ||
| 16. | Employment Generation Subsidy for employees atS.No. 14 | |
| To be filled enterprise located in backward or mostbackward area | ||
| (i) For Bonafide residents of Rajasthan | ||
| (ii) For Others | ||
| 17. | Employment Generation Subsidy for employees atS.No. 15 | |
| To be filled enterprise located in backward or mostbackward area | ||
| (i) For Bonafide residents of Rajasthan | ||
| (ii) For Others | ||
| 18. | Total Employment Generation Subsidy claimed by theenterprise (16+17) | |
| (i) For Bonafide residents of Rajasthan | ||
| (ii) For Others | ||
| 19. | Total amount of subsidy (10+18) | |
| 20. | Tax period(s) in which the subsidy is to bedeposited | |
| 21. | Amount of eligible fixed capital investment | |
| 22. | Total amount of subsidy recived up to the precedingquarter |
1. Copy of Challan for the amount of contribution of EPF and/or ESI or copy of insurance policy obtained for medical treatment of employees, along with list of employees.
2. Proof of deposit of Tax (VAT/CST)
Form - IX A[See clause 11.1.2]Order for rejection of Application for Exemption from Stamp Duty and/or Conversion Charges(Under Rajasthan Investment Promotion Scheme -2014 New/Service sector/Expansion)Office of the Member Secretary State/ District Level Screening CommitteeTo| 1. | Name of the applicant Enterprise | |
| 2. | Address of the applicant Enterprise | |
| 3. | e-mail address | |
| 4. | TIN |
| 1. | Name of the applicant Enterprise | |
| 2. | Address of the applicant Enterprise | |
| 3. | e-mail address | |
| 4. | TIN |
1. M/s ......................
2. Concerned Department
Member SecretaryForm - XI[See clause 11.3.5]Order for rejection of Claim of Exemption from Luxury Tax/Electricity Duty/Entertainment Tax/Mandi Fee/Entry Tax(Under Rajasthan Investment Promotion Scheme - 2014 New/Service sector/Expansion)Office of the Member Secretary State/District Level Screening CommitteeTo| 1. | Name of the applicant Enterprise | |
| 2. | Address of the applicant Enterprise | |
| 3. | e-mail address | |
| 4. | TIN |
1. M/s ......................
2. Concerned Department
Member SecretaryForm - XII[See clause 11.4.6]Order for rejection of Claim of Investment Subsidy/Employment Generation Subsidy(Under Rajasthan Investment Promotion Scheme -2014 New/Service sector/Expansion/)Office of the Member Secretary State/District Level Screening CommitteeTo| 1. | Name of the applicant Enterprise | |
| 2. | Address of the applicant Enterprise | |
| 3. | e-mail address | |
| 4. | TIN |
1. M/s ......................
2. Concerned Department
Member SecretaryForm - XIII[See clause 11.4.1]Certificate of Valuation by Chartered AccountantWe hereby certify that M/s...................................................................................................................................................................................................................................... has made investment and has acquired the following assets:Details of Investment made in Fixed Assets:| S.No. | Description | Amount |
| 1. | Cost of land including documentation charges | |
| 2. | Cost of land development (Leveling or fillingcosts) | |
| 3. | Cost of factory sheds and other industrialbuildings | |
| 4. | Cost of plant and machinery | |
| 5. | Cost of technical know-how a fees or drawingfees paid to foreign collaborators or foreign suppliers or paidto laboratories recognized by the State Government or theGovernment of India | |
| 6. | Cost of other miscellaneous fixed assets | |
| 7. | Cost of pollution control devices | |
| Total |
| S.No. | Description | Investment in existing enterprise | Additional investment |
| 1. | Cost of land including documentation charges | ||
| 2. | Cost of land development (Leveling or fillingcosts) | ||
| 3. | Cost of factory sheds and other industrialbuildings | ||
| 4. | Cost of plant and machinery | ||
| 5. | Cost of technical knowhow fees or drawing feespaid to foreign collaborators or foreign suppliers or paid tolaboratories recognized by the State Government or the Governmentof India | ||
| 6. | Cost of other miscellaneous fix assets | ||
| 7. | Cost of pollution control devices | ||
| Total |
| 1. | Name of the applicant enterprise | ||
| 2. | Registration No. (TIN) | ||
| 3. | Address of the applicant enterprise | ||
| 4. | E-mail address | ||
| 5. | Branches or other place of business, if any | ||
| 6. | Date (proposed date if not commenced) ofcommencement of commercial production/operation | ||
| 7. | Amount of investment (proposed if investment notmade) in plant and machinery or equipment within the State | ||
| 8. | Number of years in which the investment will bemade | ||
| 9. | Status of Rajasthan State Pollution ControlBoard's approval | ||
| Approval No. | Approval Date | ||
| Consent to establish obtained | |||
| Consent To Operate obtained |
| 1. | Name of the applicant enterprise | ||
| 2. | Registration No. (TIN) | ||
| 3. | Address of the applicant enterprise | ||
| 4. | E-mail address | ||
| 5. | Location of desalination plant | ||
| 6. | Branches or other place of business, if any | ||
| 7. | Total Dissolved Solids (TDS) per million (ppm)before desalination | ||
| 8. | Total Dissolved Solids (TDS) per million (ppm)after desalination | ||
| 9. | Date of commencement of commercial Production | ||
| 10. | Amount of investment in Desalination Plantwithin the State | ||
| 11. | Status of Rajasthan State Pollution ControlBoard's approval | ||
| Approval No. | Approval Date | ||
| Consent to establish obtained | |||
| Consent to Operate obtained |
| 1. | Name of the Enterprise | |
| 2. | Registration No. (TIN) | |
| 3. | Address of the enterprise | |
| 4. | E-mail address | |
| 5. | Branches or other place of business, if any | |
| 6. | Location of investment and name of project | |
| 7. | Date of commencement of commercialproduction/operation | |
| 8. | Estimated amount of investment in plant andmachinery or equipment |
| 1. | Name of the Enterprise | |
| 2. | Registration No. (TIN) | |
| 3. | Address of the enterprise | |
| 4. | E-mail address | |
| 5. | Branches or other place of business, if any | |
| 6. | Location of Desalination Plant | |
| 7. | Date of commencement of commercial production | |
| 8. | Amount of investment | |
| 9. | Total Dissolved Solids (TDS) per million (ppm)before desalination | |
| 10. | Total Dissolved Solids (TDS) per million (ppm)after desalination |
| 1. | Name of the applicant Enterprise | |
| 2. | Address of the applicant Enterprise | |
| 3. | e-mail address | |
| 4. | TIN |
1. M/s ......................
2. Concerned Department
Member SecretaryForm - XVIII[See clause 12.3.1]Application for Reimbursement of VAT by Manufacturing or Service Enterprise other than Textile Sector(Under Rajasthan Investment Promotion Scheme - 2014)To,The Commissioner,Industries Department,Udyog Bhawan, Tilak Marg, Jaipur| 1. | Name of the applicant enterprise | |||
| 2. | Address of the applicant enterprise with e-mailaddress | |||
| 3. | Registration No. with Commercial TaxesDepartment - TIN | |||
| 4. | Eligibility Certificate number and date | |||
| 5. | Period (year) for which reimbursement of VAT hasbeen claimed | |||
| 6. | Purchase Value | Plant and Machinery | Equipment | Membrane |
| 7. | Amount of VAT paid | Plant and Machinery | Equipment | Membrane |
| 8. | Amount of claim of reimbursement of VAT | Plant and Machinery | Equipment | Membrane |
| 9. | Details of Bank | |||
| (a) Name of Bank in which reimbursement of taxis sought | ||||
| (b) Name of the Branch | ||||
| (c) Account Type | ||||
| (d) Account Number | ||||
| (e) IFSC Code of the Branch | ||||
| (f) MICR of the Branch |
| S No | Name of the selling dealer | TIN | Name of commodity | Detail of invoice (s) | |||
| Number | Date | Amount | Tax | ||||
| 1. | Name of the Enterprise | ||||
| 2. | Address:Office:Factory:Tele No.:Fax No. :Email: | ||||
| 3. | Constitution of the Enterprise (Please attachthe relevant document) | Proprietorship/Partnership/Company/Society/others | |||
| 4. | VAT registration No. (TIN) | ||||
| 5. | Location of Unit for which Interest Subsidy isclaimed | ||||
| 6. | Whether the project is New or Expansion ofexisting enterprises or Revival of sick enterprises | ||||
| 7. | (a) Date of commencement of commercialproduction | ||||
| (b) EM No. & Date (MSMED Act Part-II)(attach copy) | |||||
| (c) IEM Acknowledgement No. & Date (attachcopy) | |||||
| 8. | (a) Activity/process in value chain | ||||
| (b) Item of production (manufacturing) | |||||
| (c) Investment in Plant & Machinery asspecified in TUF scheme | |||||
| 9. | Rate of interest Subsidy applicable | 5% | 6% | 7% | Any other: .....% |
| 10. | (a) Please give details of Total Investment &term loan Amount:For New Unit:For Expansion Unit:ForRevival of sick enterprise:(Whichever is applicable) | Total Investment (In Rs.) | Term loan Amount (In Rs.) | ||
| 11. | For the units going under Expansion(a)Investment in Existing Unit | Rs......................... (In lakh) | |||
| (b) Investment made under Expansion | Rs......................... (In lakh) | ||||
| (c) Increase in Investment | .........................................% | ||||
| 12. | Cost of project as approved by Bank/financialInstitution (In figures & in words both) | ||||
| 13. | Term loan Sanctioned for investment (includinginvestment in Plant & Machinery specified under TUFS)(a)Name of Financial Institution/Bank, (Unique code of suchbanks/financial institutions) | ||||
| (b) Rate of Interest, Period and Quantum of loansanctioned | |||||
| (c) Sanction letter No. & Date (attach copy) | |||||
| 14. | First disbursement of loan(a) Date | ||||
| (b) Amount (In Rs.) | |||||
| 15. | Details of Cost ofProject & Actual investment for new Unit/Expansion of anexisting enterprise or Revival of Sick enterprise (please attachCA Certificate.)(Rs. in lakh) | ||||
| PROJECTED | ACTUAL | ||||
| (a) Land | |||||
| (b) Building | |||||
| (c) Plant & Machinery/Equipment(asspecified in TUF scheme) | |||||
| (d) Machinery for effluent treatment plant | |||||
| (e) Others: (specify if any) | |||||
| TOTAL: | |||||
| 16. | Means of Finance | (Rs. in lakh) | |||
| PROJECTED | ACTUAL | ||||
| (a) Promoter's Contribution | |||||
| (b) Term Loan | |||||
| (c) Internal Resources | |||||
| (d) Deposits | |||||
| (e) Others | |||||
| TOTAL | |||||
| 17. | (a) Whether any Subsidy benefits underRIPS-2003/RIPS-2010 applied or availed | Yes/No | |||
| (b) If yes, please give details thereof | |||||
| 18. | Details of New Plant & Machinery (TUF)acquired & Installed(a) New Plant & Machinery(1)Indigenous Plant & Machinery(2) Imported Plant &Machinery | Rs.Rs. | |||
| (b) Secondhand Plant & Machinery (TUF)details(1) Indigenous Plant & Machinery(2) ImportedPlant & Machinery | Rs.Rs. | ||||
| TOTAL [18 a + 18 b] | |||||
| 19. | Eligible Fixed Capital InvestmentPlant &Machinery/Equipment: (as specified in TUF scheme) | ||||
| 20. | Rate of interest subsidy available under TUFScheme | ||||
| 21. | Status of Rajasthan State Pollution ControlBoard's approval | ||||
| Approval No. | Approval Date | ||||
| Consent to establish obtained | |||||
| Consent to Operate obtained | |||||
| 22. | Details of any other Interest Subsidy granted by | Percentage of Interest Subsidy | Specify the Scheme | ||
| (a) State Government | |||||
| (b) Government of India | |||||
| 23 | Whether any Government dues are outstanding ornot? If Yes, give details thereof | ||||
| 24 | Whether any court case? If Yes Give detailsthereof |
| 1. | Name of the Enterprise | ||||
| 2. | Address:Office:Factory:Tel No:Fax No:E-mail: | ||||
| 3. | Constitution of the Enterprise (Please attach the relevant document) | Proprietorship / Partnership Company/Society/others | |||
| 4. | VAT registration No. (TIN) | ||||
| 5. | Location of Unit for which Interest Subsidy is claimed | ||||
| 6. | Whether the project is new or Expansion of existingenterprises or Revival of sick enterprises | ||||
| 7. | Date of commencement of commercial production | ||||
| 8. | (a) Activity/process in value chain | ||||
| (b) Goods to be manufactured (in case of manufacturing) | |||||
| (c) Services likely to be rendered (in case of serviceenterprise) | |||||
| 9. | Rate of interest subsidy available | 5% | 6% | 7% | Any other……% |
| 10. | Please give details of Total Investment & term loanAmount: | Total Investment (In Rs.) | Amount of Term loan (In Rs.) | ||
| For New Unit: | |||||
| For Expansion of existing Unit: | |||||
| For Revival of sick enterprise: | |||||
| 11. | For the units going under | ||||
| Expansion(a) Investment in Existing Unit | Rs……………………………….(In lakh) | ||||
| (b) Investment made under Expansion | Rs……………………………….(In lakh) | ||||
| (c) Increase in Investment | …………………………………….% | ||||
| 12. | Cost of project as approved by Bank/financial Institution (Infigures & in words both) | ||||
| 13. | (a) Amount of term loan Sanctioned for investment | ||||
| (b) Name of Financial Institution / Bank, (Unique code of suchbanks/financial institutions) | |||||
| (c) Rate of Interest, Period and Quantum of loan Sanctioned | |||||
| (d) Sanction letter No. & Date (attach copy) | |||||
| 14. | First disbursement of loan (a) Date | ||||
| (b) Amount (In Rs.) | |||||
| 15. | Details of Cost of Project & Actual investment for newUnit / Expansion of an existing enterprise or Revival of Sickenterprise (please attach CA Certificate.) (Rs. in Lakh) | ||||
| PROJECTED | ACTUAL | ||||
| (a) Land: | |||||
| (b) Building: | |||||
| (c) Plant & Machinery: | |||||
| (d) Technical know-how etc. | |||||
| (e) Others: (specify if any) | |||||
| Total: | |||||
| 16. | Means of Finance | (Rs. In Lakhs) | |||
| PROJECTED | ACTUAL | ||||
| (a) Promoter's Contribution: | |||||
| (b) Term Loan | |||||
| (c) Internal Resources: | |||||
| (d) Deposits: | |||||
| (e) Others | |||||
| TOTAL: | |||||
| 17. | (a) Whether any Subsidy benefits under RIPS-2003 / RIPS-2010applied or availed | Yes/No | |||
| (b) If yes, please give details thereof | |||||
| 18. | Status of Rajasthan State Pollution Control Board’sapproval | ||||
| Approval No. | Approval Date | ||||
| Consent to establish obtained | |||||
| Consent To Operate obtained | |||||
| 19. | Details of any other Interest Subsidy granted by | Percentage of Interest Subsidy | Specify the Scheme | ||
| (a)State Government | |||||
| (b) Government of India | |||||
| (c) any undertaking, corporation or company owned orcontrolled by the State Government, | |||||
| 20. | Whether any Government dues are outstanding or not? If Yes, Give details thereof | ||||
| 21. | Whether any court case? If Yes, Give details thereof |
| 1. | Name of the Enterprise | |
| 2. | VAT Registration No. (TIN) | |
| 3. | Address of the enterprise | |
| 4. | E-mail address | |
| 5. | Name, designation & contact details of the Authorized Person | |
| 6. | Location of unit entitled for benefit under this certificate | |
| 7. | Eligible Fixed Capital Investment(a)Purchase value of Plant & Machinery specified under TUFScheme | |
| (b) Purchase value of Machinery for effluent treatment plant | ||
| TOTAL [7 (a) + 7 (b)] | ||
| 8. | Term loan Sanctioned for eligible investment(a)Name of Financial Institution/Bank | |
| (b) Rate of Interest, Period and Quantum of loan sanctioned | ||
| 9. | Rate of interest subsidy available under TUF Scheme to the enterprise from Government of India | |
| 10. | Rate of interest subsidy available under Special customized package for Textile Sector Enterprises - 2013. Maximum up to [8(b)-9] | |
| 11. | Date of Commencement of commercial production |
| 1. | Name of the Enterprise | |
| 2. | VAT Registration No. (TIN), if any | |
| 3. | Address of the enterprise | |
| 4. | E-mail address | |
| 5. | Name, designation & contact details of the Authorized Person | |
| 6. | Location of unit entitled for benefit under this certificate | |
| 7A. | Eligible Fixed Capital Investment | |
| (a) Purchase of land: | ||
| (b) Purchase/ construction of new factory sheds and other new industrial buildings; | ||
| (c) Purchase/ construction of new plant and machinery or equipment; | ||
| (d) Other investment made in new fixed assets essential for production of the unit as approved by the Screening Committee; and | ||
| (e) Technical know-how fees or drawing fees paid in lump-sum to foreign collaborators or foreign suppliers or paid to laboratories recognized by the State Government or the Government of India. | ||
| Total 17A(a)+7A(b)+ 7A(c)+7A(d)+7A(e)] | ||
| 8. | Term loan Sanctioned for eligible investment(a) Name of Financial Institution/Bank | |
| (b) Rate of Interest, Period and quantum of loan sanctioned | ||
| 9. | Date of Commencement of commercial production/operation. |
3. If the enterprise becomes defaulter, it will not get interest subsidy for the default period and such defaulting period will be deducted from eligible period as specified in 1 above.
4. In case of breach of any of the condition mentioned anywhere in the scheme/ customized package. if any, the benefits availed under the scheme/ customized package, if any, shall be withdrawn and recovered along with interest (4 18% per annum from the date from which the benefits have been availed.
This certificate may be revoked by the issuing authority unilaterally in case the applicant violates any of the conditions of the scheme or customized package, if any issued in favour of enterprise, without any notice.Place :Date :(Signature with Seal)Member SecretaryState Level Screening Committee/District Level Screening Committee"Form-XXII[See clause 12.4.2]Application for Disbursement of Subsidy by the Textile Sector EnterpriseTo,The Commissioner,Industries Department,Rajasthan, Jaipur| 1. | Name of the Enterprise | |
| 2. | Address of the Enterprise | |
| 3. | E-mail address | |
| 4. | Name, designation & contact details of the Authorized Person | |
| 5. | Entitlement Certificate Number | |
| 6. | Interest Subsidy Applied for the Quarter (Period) | |
| 7. | Amount of Interest Paid to the Financial Institution/Bank for the quarter | |
| 8. | Amount of Interest Subsidy under the TUF Scheme for the Quarter from Government of India | |
| 9. | Eligible Amount of Interest Subsidy under the Package (As per calculation sheet attached) | |
| 10. | Maximum Amount Eligible under the Package | |
| 11. | Total amount of Subsidy received up to the Preceding Quarter | |
| 12. | Bank Certificate as mentioned in clause 12.4.3 of the scheme is attached | Yes/No |
| 13. | Details of Bank | |
| (a) Name of Bank in which disbursement of subsidy is sought | ||
| (b) Name of the Branch | ||
| (c) Account Type | ||
| (d) Account Number | ||
| (e) IFSC Code of the Branch | ||
| (f) MICR of the Branch |
| 1. | Name of the Enterprise | |
| 2. | Address of the Enterprise | |
| 3. | E-mail address | |
| 4. | Name, designation & contact details of the Authorized Person | |
| 5. | Entitlement Certificate Number and Date | |
| 6. | Date of commencement of commercial production | |
| 7. | Period for which the Interest Subsidy has applied for | |
| 8. | Amount of Interest Paid on term loan to the Financial Institution/Bank for the period for which Interest Subsidy has applied | |
| 9. | Rate of Interest payable to Financial Institution/Bank on term loan | |
| 10. | Interest @5% [(5/rate of interest) x Interest paid] | |
| 11. | Maximum Amount of subsidy per annum allowed under the scheme /customized package, if any. | |
| 12. | Eligible amount of subsidy[ Minimum of 10 and 11] | |
| 13. | Bank Certificate as mentioned in clause 12.4A.3 of the Scheme is attached | Yes/No |
| 14. | Details of Bank | |
| (a) Name of Bank in which disbursement of subsidy is sought | ||
| (b) Name of the Branch | ||
| (c) Account Type | ||
| (d) Account Number | ||
| (e) IFSC Code of the Branch | ||
| (f) MICR of the Branch |
| 1. | Name of the beneficiary enterprise | |
| 2. | No. and date of entitlement certificate | |
| 3. | Investment made in Plant & Machinery asspecified in TUF Scheme | |
| 4. | Rate of Interest payable to FinancialInstitution/Bank | |
| 5. | Rate of Interest being reimbursed by Governmentof India under TUF Scheme | |
| 6. | Rate at which interest subsidy is allowed underentitlement certificate | |
| 7. | Date of commencement of commercial production |
| 1. | Name of the beneficiary enterprise | |
| 2. | No. and date of entitlement certificate | |
| 3. | Amount of Term Loan | |
| 4. | Rate of Interest payable to FinancialInstitution/Bank | |
| 5. | Rate at which interest subsidy is allowed underentitlement certificate | |
| 6. | Date of commencement of commercial production |
| S.No. | Year | Quarter | Employment provided during the quarter | Employment provided up to the quarter | Interest Subsidy disbursed for the quarter | Interest Subsidy disbursed up to the quarter |
| 1. | 2. | 3. | 4. | 5. | 6. | 7. |
| 1. | I | 1st | ||||
| 2. | I | 2nd | ||||
| 3. | I | 3rd | ||||
| 4. | I | 4th | ||||
| 5. | II | 1st | ||||
| 6. | II | 2nd | ||||
| 7. | II | 3rd | ||||
| 8. | II | 4th | ||||
| 9. | III | 1st | ||||
| 10. | III | 2nd | ||||
| 11. | III | 3rd | ||||
| 12. | III | 4th | ||||
| 13. | IV | 1st | ||||
| 14. | IV | 2nd | ||||
| 15. | IV | 3rd | ||||
| 16. | IV | 4th | ||||
| 17. | V | 1st | ||||
| 18. | V | 2nd | ||||
| 19. | V | 3rd | ||||
| 20. | V | 4th |
| 1. | Name of the Enterprise | ||
| 2. | Address:Office:Factory:Tele No. :FaxNo. : Email: | ||
| 3. | Constitution of the Enterprise(Please attachthe relevant document) | Proprietorship/Partnership/Company/Society/others | |
| 4. | VAT registration No. (TIN) | ||
| 5. | Location of Unit for which Interest Subsidy isclaimed | ||
| 6. | Location of zero liquid discharge based effluenttreatment plant | ||
| 7. | Whether the project is New or Expansion of existingenterprises or Revival of sick enterprises. | ||
| 8 | Date of commencement of commercial production | ||
| 9 | Please give details of Total Investment & termloan Amount:For New Unit:For Expansion Unit:ForRevival of sick enterprise:(Whichever is applicable) | Total Investment (In Rs.) | Term loan Amount (In Rs.) |
| 10 | For the units going under Expansion(a)Investment in Existing Unit | Rs......................... (In lakh)” | |
| (b) Investment made under Expansion | Rs......................... (In lakh) | ||
| (c) Increase in Investment | .........................................% | ||
| 11 | Details of Cost of Project & Actual investmentfor New Unit/Expansion of an existing enterprise or Revival ofSick enterprise: (please attach CA Certificate.) (Rs. in lakh) | ||
| PROJECTED | ACTUAL | ||
| (a) Land | |||
| (b) Building | |||
| (c) Plant & Machinery/Equipment(asspecified in TUF scheme) | |||
| (e) Others (specify if any) | |||
| TOTAL: | |||
| 12 | (a) Whether any Subsidy benefits underRIPS-2003/RIPS-2010 applied or availed | Yes/No | |
| (b) If yes, please give details thereof | |||
| 13 | Details of Investment made in zero liquid dischargebased effluent treatment plant | Rs. | |
| 14 | Status of Rajasthan State Pollution Control Board'sapproval | ||
| Approval No. | Approval Date | ||
| Consent to establish obtained | |||
| Consent to Operate obtained |
2. Any financial transactions/expenditure statements submitted by the enterprise must be signed by the authorized signatory of the enterprise and certified by the Chartered Accountant.
Form-XXV[See clause 11.7. 5]Eligibility Certificate for Capital Subsidy on zero liquid discharge based Effluent Treatment PlantNo.Date:| 1. | Name of the Enterprise | |
| 2. | Registration No. (TIN) | |
| 3. | Address of the enterprise | |
| 4. | E-mail address | |
| 5. | Branches or other place of business, if any | |
| 6. | Eligible Cost of zero liquid discharge basedeffluent treatment plant | |
| 7. | Maximum Eligible Amount of Subsidy |
| 1. | Name of the applicant enterprise | |
| 2. | Address of the applicant enterprise with e-mailaddress | |
| 3. | Registration No. with Commercial TaxesDepartment-TIN | |
| 4. | Eligibility Certificate number and date | |
| 5. | Maximum Eligible Amount of Subsidy as perEligibility Certificate | |
| 6. | Subsidy claimed | |
| I installment/II installment | ||
| 7. | Details of Bank | |
| (a) Name of Bank in which disbursement ofsubsidy is sought | ||
| (b) Name of the Branch | ||
| (c) Account Type | ||
| (d) Account Number | ||
| (e) IFSC Code of the Branch | ||
| (f) MICR of the Branch |
| (1) | Name of the Enterprise | |||
| (2) | AddressOfficeFactoryTele No.FaxNo.Email | |||
| (3) | Constitution of the Enterprise (Please attachthe relevant document) | Proprietorship/Partnership/Company/Society/others | ||
| (4) | VAT registration No. (TIN) | |||
| (5) | Location of Unit for which Interest Subsidy isclaimed | |||
| (6) | Whether the project is New or Expansion ofexisting enterprises or revival of sick enterprise | |||
| (7) | Date of commencement of commercial production | |||
| (8) | (a) Activity/process in value chain | |||
| (b) Item of production (manufacturing) | ||||
| (c) Investment in Plant & Machinery asspecified in TUF scheme | ||||
| (9) | Please give details of TotalTerm loanAmountInvestment & term loan Amount:For New UnitRs:For Expansion Unit Rs:For Revival of sickenterprise:(Whichever is applicable) | Total Investment | ||
| (10) | For the units going under Expansion (a) FixedCapital Investment of Existing Unit | Rs......................... (In lakh) | ||
| (b) Fixed Capital Investment of Expansion | Rs......................... (In lakh) | |||
| (c) Increase in Fixed Capital Investment | .........................................% | |||
| (11) | Cost of project as approved by Bank/financialInstitution (In figures & in words both) | |||
| (12) | (a) Whether any Subsidy benefits underRIPS-2003/RIPS-2010 applied or availed | Yes/No | ||
| (b) If yes, please give details thereof | ||||
| (13) | Eligible fixed investment Plant &Machinery/Equipment: (as specified in TUF scheme) | |||
| (14) | Status of Rajasthan State Pollution ControlBoard's approval | |||
| Approval No. | Approval Date | |||
| Consent to establish obtained | ||||
| Consent to Operate obtained | ||||
| (15) | Whether any Government dues are outstanding ornot? If Yes, give details thereof | |||
| (16) | In Case of Expansion: Details of amount ofpurchase of yarn, fibre, recycled fibre yarn, cotton and petbottles made by him for use in the manufacturing of goods withinthe State, for sale by him, in the three consecutive yearsimmediately preceding to the year of expansion. (In lakh Rupees) | In the Year Immediately preceding to the year ofexpansion | In the Second Year Immediately preceding to theyear of expansion | In the Third Year Immediately preceding to theyear of expansion |
| 1. | Name of the Enterprise | |
| 2. | VAT Registration No. (TIN) | |
| 3. | Address of the enterprise | |
| 4. | E-mail address | |
| 5. | Name, designation & contact details of theAuthorized Person | |
| 6. | Location of unit entitled for benefit under thiscertificate | |
| 7. | Eligible fixed investment(a) Purchase valueof Plant & Machinery specified under TUF Scheme | |
| (b) Purchase value of Machinery for effluenttreatment plant | ||
| Total [7 (a) + 7 (b)] | ||
| 8. | Date of commencement of Commercial production | |
| 9. | In case of expansion:Maximum amount ofPurchase of yarn, fibre, recycled fibre yarn, cotton and petbottles in the three consecutive years immediately preceding tothe year of expansion. |
2. This certificate may be revoked by the issuing authority in case the applicant violates any of the conditions of the Scheme.
Form-XXIX[See clause 12.5.1]Application for reimbursement of VAT paid by Manufacturing EnterprisePart-A (General Information)| 1. | Name of the Enterprise | |
| 2. | Registration No. (TIN), if any | |
| 3. | Address of the Enterprise | |
| 4. | E-mail address | |
| 5. | Mobile No. | |
| 6. | Details of Bank | |
| (a) Name of Bank in which reimbursement of taxis sought | ||
| (b) Name of the Branch | ||
| (c) Account Type | ||
| (d) Account Number | ||
| (e) IFSC Code of the Branch | ||
| (f) MICR of the Branch | ||
| 7. | Total amount of tax to be reimbursed |
| S.No. | Name the selling dealer | TIN | Name of Commodity | Detail of Invoice(s) | |||
| Number | Date | Amount | Tax | ||||
| 1. | Name of the beneficiary Enterprise | |
| 2. | Registration No. (TIN), if any | |
| 3. | Address of the Enterprise | |
| 4. | E-mail address | |
| 5. | Mobile No. | |
| 6. | Entitlement Certificate Number and date |
| S. No. | Financial Year | Quarter | Reimbursement of VAT made during the quarter | Reimbursement of VAT made up to the quarter |
| 1. | Name of the applicant Enterprise | |
| 2. | Address of the applicant Enterprise | |
| 3. | e-mail address | |
| 4. | TIN |
1. M/s .........................
2. Concerned Department
Member SecretaryForm - XXXII[See clause 11.7.6]Order for rejection of Claim of Capital Subsidy on zero liquid discharge based Effluent Treatment Plant(Under Rajasthan Investment Promotion Scheme - 2014New/Service sector/Expansion/Revival of Sick enterprise)Office of the Member Secretary State Level Screening CommitteeTo| 1. | Name of the applicant Enterprise | |
| 2. | Address of the applicant Enterprise | |
| 3. | e-mail address | |
| 4. | TIN |
1. M/s ......................
2. Concerned Department
Member SecretaryForm - XXXIII[See clause 11.8.5]Order for rejection of Claim of reimbursement of VAT paid by Manufacturing Enterprise(Under Rajasthan Investment Promotion Scheme -2014New/Service sector/Expansion/Revival of Sick enterprise)Office of the Member Secretary State Level Screening CommitteeTo| 1. | Name of the applicant Enterprise | |
| 2. | Address of the applicant Enterprise | |
| 3. | e-mail address | |
| 4. | TIN |
1. M/s ......................
2. Concerned Department
Member SecretaryForm - XXXIV[See clause 13A.6]Order for rejection of Remaining Benefits to the transferee Enterprise(Under Rajasthan Investment Promotion Scheme -2014)Office of the Member Secretary State/District Level Screening CommitteeTo| 1. | Name of the transferee Enterprise | |
| 2. | Address of the transferee Enterprise | |
| 3. | e-mail address | |
| 4. | TIN |
1. M/s ......................
2. Concerned Department
Member Secretary".Form VAT-37BChallan for Adjustment through TreasuryPart-I (Sanction order for subsidy)| Name and address of the Enterprise | TIN | Entitlement Certificate Number and Date | Period for which subsidy granted | Amount of Tax on which subsidy has beencalculated | Amount of subsidy granted | Period in which it would be adjusted |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| 1. | Name of the Department: | Commercial Taxes Department |
| 2. | Name of the Office: | |
| 3. | Designation of the Officer and Accepting details | |
| 4. | Receipt Budget Head: to which credit is to begiven (Give minor/sub head and detailed head also if any) | 0040 fcdzh O;kikj bR;kfn ij dj102 jkT; fodz; dj vf/kfu;e ds v/khu izkfIr;ka(001)dj laxzg.k(i)dj dk vfxze lank;(1)fodz; |
| 5. | Expenditure Budget Head to which chargeable withminor/sub head and detailed head of A/c | |
| Total |