State of Rajasthan - Act
Rajasthan Electricity Regulatory Commission (Transmission Licensee's Standards of Performance) Regulations, 2004
RAJASTHAN
India
India
Rajasthan Electricity Regulatory Commission (Transmission Licensee's Standards of Performance) Regulations, 2004
Rule RAJASTHAN-ELECTRICITY-REGULATORY-COMMISSION-TRANSMISSION-LICENSEE-S-STANDARDS-OF-PERFORMANCE-REGULATIONS-2004 of 2004
- Published on 20 April 2004
- Commenced on 20 April 2004
- [This is the version of this document from 20 April 2004.]
- [Note: The original publication document is not available and this content could not be verified.]
1. Short title, commencement and extent.
2. Definitions.
- In these regulations, unless the context otherwise requires;3. Objective.
- This standard shall serve as guidelines for transmission licensee to operate its' State Transmission System for providing an efficient, reliable, coordinated and economical system of electricity supply and transmission. These standards set the levels of operational security and quality of supply, which licencee shall be obliged to maintain in making power available for the purposes of supply to licencees and supply to/receipt from various generating stations, as laid down in the Transmission Licence. The objectives of the performance standards are:4. Implementation.
- The performance standards established herein shall be implemented in three stages:-5. System Availability.
- Licencee shall ensure weighted annual average system availability not less than the percentage given below:| Preliminary Stage-Level 1 | 95% |
| Transition Stage-Level 2 | 97% |
| Final Stage-Level 3 | 98% |
6. Voltage Management.
- (1) Voltage Profile. - Licencee shall make all possible efforts to ensure that the grid voltage remain within the following voltage levells at all EHV sub-stations of its Transmission System on real time basis at SLDC. Voltage profile at each interconnection point shall be maintained as under:-| Voltage (kV rms) | ||
| Nominal | Maximum | Minimum |
| 400 | 420 | 360 |
| 220 | 245 | 200 |
| 132 | 145 | 120 |
| 66 | 72.6 | 59.4 |
| 33 | 34.98 | 30.03 |
| 11 | 11.66 | 10.01 |
| (i) Voltage Unbalance =| Deviation between highest and lowest phase voltageAverage voltage of three phases.| |
| Voltage Level | Limit of voltage unbalance |
| 220 Kv and above | 2% |
| Below 220 Kv | 3% |
| | VVI =| 100Vs| x square root of| i=1N |
7. Frequency Management.
| Target range | |
| Upper Limit | 50.5Hz |
| Lower Limit | 49.0Hz |
| Statutory acceptable limit | |
| Upper Limit | 51.5Hz |
| Lower Limit | 48.5 Hz |
| | FVI =| 10050.0| x square root of| i=1N |
8. Reliability.
- System reliability includes three aspects:-| Implementation Stage | Nos. of days in year when system demand can befully met subject to generation availability | Nos. of days in year when system demand cannot be fully met even with generation availability | Loss of load expectation (LOLE) in % of days |
| Preliminary Stage-Level-1 | 325 | 40 | 11% |
| Transition Stage-Level-2 | 345 | 20 | 6% |
| Final Stage-Level-3 | 358 | 7 | 2% |
| Implementation Stage | SAIFI | SAIDI |
| Preliminary Stage-Level-1 | No limit | No limit |
| Transition Stage-Level-2 | 24 per year | 10 hrs/year |
| Final Stage-Level-3 | 18 per year | 8 hrs/year |
9. Harmonic Distortion.
- This standard shall be achieved during Final Stage (Level-3).| 40Vi2 | ||||||
| VTHD = | ∑ | x 100% | ||||
| V12 | ||||||
| i-1 | ||||||
| VTHD = | Vi | x 100% | ||||
| V1 |