State of Tamilnadu- Act
Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007
TAMILNADU
India
India
Central Electricity Authority (Furnishing of Statistics, Returns and Information) Regulations, 2007
Rule CENTRAL-ELECTRICITY-AUTHORITY-FURNISHING-OF-STATISTICS-RETURNS-AND-INFORMATION-REGULATIONS-2007 of 2007
- Published on 1 January 2007
- Commenced on 1 January 2007
- [This is the version of this document from 1 January 2007.]
- [Note: The original publication document is not available and this content could not be verified.]
1. Short title and commencement.
2. Definitions.
- Unless the context otherwise requires, in these regulations,-3. Applicability of the regulations.
- These regulations shall be applicable to all the licensees, generating companies, person(s) generating electricity for its or his own use and person(s) engaged in generation, transmission, distribution, trading and utilization of electricity.4. Sources of Statistics, returns and information.
- All licensees, generating companies and person(s) mentioned below, but not limited to, shall furnish to the Authority such statistics, returns or other information relating to generation, transmission, distribution, trading and utilization of electricity at such times and in such form and manner as specified under these regulations-5. Formats for furnishing of statistics, returns or information.
- The entities shall furnish the statistics, returns and information as per the formats annexed to these regulations and the list of format is as per Annexure-I titled "List of formats, frequency (ies) and target date(s)". These formats can also be obtained from the website of the Central Electricity Authority. The formats may be sent by mail or media, to the source (s) of the statistics, returns or information, as and when required.6. Time schedule for furnishing of statistics, return or information.
- The time schedule or targets for furnishing of statistics, return or information shall be as specified by the Authority on its prescribed formats. A consolidated list of time Schedule format-wise is given at Annexure-I titled "List of formats, frequency (ies) and target date (s)".7. Frequency of submission of statistics, returns or information.
- The frequency of submission i.e. daily, weekly, monthly, quarterly or annually shall be as specified by the Authority in its prescribed formats. A consolidated list of frequency of submission format-wise is given in Annexure-I titled "List of formats, frequency (ies) and target date(s)".8. Manner of furnishing the statistics, returns or information.
9. Addition and deletion in formats, time schedule, periodicity or furnishing method.
10. Right of access to records or documents.
- The Authority or any person authorized by it in writing on its behalf shall, for the purposes of the collection of any statistics under these regulations, have access to any relevant record or document in the possession of any person required to furnish any information or return under these regulations and may enter at any reasonable time any premises where he believes such record or documents to be available and may inspect or take copies of relevant records or documents or ask any question necessary for obtaining any information required to be furnished under these regulations.11. Restriction on publication of information and returns.
12. Non-compliance and penalty.
| Title of Format | Frequency of data furnishing | Format No. | Target Date (By) |
| Generation of Electricity | Annual | 1 | 30-Jun |
| Transmission of Electricity | Annual | 2 | 30-Jun |
| Distribution of Electricity | Annual | 3 | 30-Jun |
| Trading of Electricity | Annual | 4 | 30-Jun |
| Details of actual sale and purchase of GrossElectrical Energy. | Annual | 5 | 30-Jun |
| Installed Electricity Generating Capacity | Annual | 6 | 30-Jun |
| Details of electricity generating capacity added | Annual | 7 | 30-Jun |
| Details of electricity generating sets retiredfrom service | Annual | 8 | 30-Jun |
| Details of derations of electricity generatingsets | Annual | 9 | 30-Jun |
| Details of fuel consumption | Annual | 10 | 30-Jun |
| Details of step-up transformers in service atthe power stations and various sub-stations as on 31.03.20. | Annual | 11 | 30-Jun |
| Details of step-down transformers in service ason 31.03.20.. | Annual | 12 | 30-Jun |
| Details of distribution transformers in serviceas on 31.03.20...... | Annual | 13 | 30-Jun |
| Details of transmission and distribution linesas on 31.03.20.. | Annual | 14 | 30-Jun |
| Details of electricity consumers, connected loadand consumption | Annual | 15 | 30-Jun |
| Details of manpower | Annual | 16 | 30-Jun |
| Training Facilities/Training Capacity in thePower Sector (Man-days of year) | Annual | 17 | 30-Jun |
| Details of theft of electricity | Annual | 18 | 30-Jun |
| Statistics on electrical accidents | Annual | 19 | 30-Jun |
| Reasons for electrical accidents | Annual | 20 | 30-Jun |
| Annual data of HV/EHV industry havingelectricity demand of 1 MW or above | Annual | 21 | 30-Jun |
| Daily Operational Data of Thermal Power Stationsand Nuclear Power Stations | Daily | 22 | 1030 hrs |
| Daily Operational Data of Hydro Power Stations | Daily | 23 | 1030 hrs |
| Monthly Operational Data of Thermal PowerStations and Nuclear Power Stations | Monthly | 24 | 7th day |
| Monthly Operational Data of Hydro Power Stations | Monthly | 25 | 7th day |
| Data for Fixation of annual targets ofelectricity generation for year 20- 20- | Annual | 26 | 30-Nov |
| Regional Power Supply Position (Daily OperationReport) | Daily | 27 | 0900 hrs |
| Provisional Power Supply Position | Monthly | 28 | 5th day |
| Revised Power Supply Position | Monthly | 29 | 18th day |
| Daily data regarding loss of generation onaccount of shortage of coal, gas and unrequisitioned liquid firedcapacity | Daily | 30 | 0900 hrs |
| Monthly Data regarding Loss of Generation onaccount of shortage of coal, gas. unrequisitioned liquid firedcapacity & backing down due to system constraints | Monthly | 31 | 10th day |
| Data for load generation balance reporL (LGBR) | Annual | 32 | End February |
| Unscheduled Interchange (Ul) Status | Monthly | 33 | 10th day |
| Details of Power Traded by the Trading Company | Monthly | 34 | 10'h day |
| Progress of capacitor installation programme | Monthly | 35 | 20th day |
| Daily Coal Report | Daily | 36 | 1500 hrs. |
| Coal Report | Monthly | 37 | 15th day |
| Generation Loss due to fuel shortage | Nlonthly | 38 | 7th day |
| Report of Monthly Average Ash percentage | Monthly | 39 | 7th day |
| Report of Quarterly/Annual Average AshPercentage (by weight) in coal received | Quarterly | 40 | 30th day after the end of quarter |
| Proposed Coal Allocation for Short Term Linkagesfor Thermal Power Stations | Quarterly | 41 | 40 days before the commencement of the quarter |
| Monthly Fuel Supply Data of Gas Based ThermalPower Stations | Monthly | 42 | 15 th day |
| Monthly Fuel Supply Data of Liquid Fuel BasedThermal Power Stations | Monthly | 43 | 15 th day |
| Monthly Fuel Supply Data of DG Power Stations | Monthly | 44 | 15th day |
| Fuel-Oil Data | Monthly | 45 | 15th day |
| Status of Progress of Villages Electrificationand Irrigation Pump sets Energisation | Monthly | 46 | 3rd day |
| District wise status of progress of villageelectrification and energisation of Pump sets | Monthly | 47 | 3rd day |
| District wise Monthly Progress of InhabitedVillage Electrification | Monthly | 48 | 3rd day |
| District-Wise Monthly Progress of Energisationof Irrigation Pump sets | Monthly | 49 | 3rd day |
| Villages electrified in various populationgroups and the population covered as on..... | Monthly | 50 | 3rd day |
| Metering Status for the Month....year.... | Monthly | 51 | 3rd day |
| Details of Failure of Distribution & PowerTransformers in the Month.....Year 20....... | Monthly | 52 | 3rd day |
| Reliability Index at Customer Level for theMonth-year | Monthly | 53 | 3rd day |
| Reliability Indices (11KV Feeders) for theMonth-Year- | Monthly | 54 | 3rd day |
| Financial Turn Around of Power Distribution forthe Financial Year- | Annual | 55 | 30th April |
| Aggregate Technical & Commercial (A T &C) Losses for the Financial Year | Annual | 56 | 30th April |
| Fuel Data of Fossil Fuel Based Thermal PowerStations for the month 20 - | Monthly | 57 | 20th day |
| Heat Rate Data of Coal/Lignite Based ThermalPower Stations for Month-Year | Monthly | 58 | 20th day |
| Heat Rate Data of Combined Cycle Gas TurbinePower Stations for Month 20 | Monthly | 59 | 20th day |
| Monthly Environmental Data of Thermal PowerPlants | Monthly | 60 | 20th day |
| Monthly Peak Hours Generation Data byCoal/Lignite Based or Combined Cycle Gas Turbine (CCGT) PowerStations | Monthly | 61 | 7th day |
| Generating Company Data for Financial Study | Annually | 62 | 30th June |
| Transmission Company Data for Financial Study | Annually | 63 | 30th June |
| Power Distribution Company Data for FinancialStudy | Annually | 64 | 30th June |
| Monthly Abstract of Ash Generation andUtilisation | Monthly | 65 | 20th day |
| Title of Format | Format No. | Genco | Tran-sco | Dis-com | Traders | SEBs/ Licensees/Elecy. Deptts. | RLD Cs | SLDCs | RPCs | CPPs/ Industries |
| Generation of Electricity | 1 | Y | Y | |||||||
| Transmission of Electricity | 2 | Y | Y | |||||||
| Distribution of Electricity | 3 | Y | Y | |||||||
| Trading of Electricity | 4 | Y | ||||||||
| Details of actual sale and purchase of GrossElectrical Energy | 5 | Y | Y | Y | Y | |||||
| Installed Electricity Generating Capacity | 6 | Y | Y | |||||||
| Details of electricity generating capacity added | 7 | Y | Y | |||||||
| Details of electricity generating sets retiredfrom service | 8 | Y | Y | |||||||
| Details of derations of electricity generatingsets | 9 | Y | Y | |||||||
| Details of fuel consumption | 10 | Y | Y | |||||||
| Details of step-up transformers in service atthe power stations and various sub-stations as on 31.03.20.. | 11 | Y | Y | Y | Y | |||||
| Details of step-down transformers in service ason 31.03.20.. | 12 | Y | Y | Y | Y | |||||
| Details of distribution transformers in serviceas on 31.03.20...... | 13 | Y | Y | Y | ||||||
| Details of transmission and distribution linesas on 31.03.20..... | 14 | Y | Y | Y | Y | |||||
| Details of electricity consumers, connected loadand consumption | 15 | Y | Y | |||||||
| Details of manpower | 16 | Y | Y | Y | Y | |||||
| Training Facilities/Training Capacity in thePower Sector (Man-days of year) | 17 | Y | Y | Y | Y | |||||
| Details of theft of electricity | 18 | Y | Y | |||||||
| Statistics on electrical accidents | 19 | Y | Y | Y | Y | Y | Y | |||
| Reasons for electrical accidents | 20 | Y | Y | Y | Y | Y | Y | |||
| Annual data of HV/EHV industry havingelectricity demand of 1 MW or above | 21 | Y | ||||||||
| Daily Op, rational Data of Thermal PowerStations and Nuclear Power Stations | 22 | Y | Y | Y | Y | |||||
| Daily Operational Data of Hydro Power Stations | 23 | Y | Y | Y | Y | |||||
| Monthly Operational Data of Thermal PowerStations and Nuclear Power Stations | 24 | Y | Y | Y | Y | |||||
| Monthly Operational Data of Hydro Power Stations | 25 | Y | Y | Y | Y | |||||
| Data for fixation of annual targets ofelectricity generation for year 20 ... 20..... | 26 | Y | Y | Y | ||||||
| Regional Power Supply Position (Daily OperationReport) | 27 | Y | ||||||||
| Provisional Power Supply Position | 28 | Y | Y | |||||||
| Revised Power Supply Position | 29 | Y | Y | |||||||
| Daily data regarding loss of generation onaccount of shortage of coal, gas and unrequisitioned liquid firedcapacity | 30 | Y | Y | Y | Y | |||||
| Monthly Data regarding Loss of Generation onaccount of Shortage of Coal, Gas, Unrequisitoned Liquid FiredCapacity & Backing Down due to System Constraints | 31 | Y | Y | |||||||
| Data for load generation balance report (LGBR) | 32 | Y | Y | Y | ||||||
| Unscheduled Interchange (Ul) Status | 33 | Y | Y | |||||||
| Details of Power Traded by the Trading Company | 34 | Y | ||||||||
| Progress of capacitor installation programme | 35 | Y | ||||||||
| Daily Coal Report | 36 | Y | Y | |||||||
| Coal Report | 37 | Y | Y | |||||||
| Generation Loss due to fuel shortage | 38 | Y | Y | |||||||
| Report of Monthly Average Ash percentage | 39 | Y | Y | |||||||
| Report of Quarterly/Annual Average AshPercentaqe (by weight) in coal received | 40 | Y | Y | |||||||
| Proposed Coal Allocation for Short Term Linkagesfor Thermal Power Stations | 41 | Y | Y | |||||||
| Monthly Fuel Supply Data of Gas Based ThermaPower Stations | 42 | Y | Y | |||||||
| Monthly Fuel Supply Data of Liquid Fuel BasedThermal Power Stations | 43 | Y | Y | |||||||
| Monthly Fuel Supply Data of DG Power Stations | 44 | Y | Y | |||||||
| Fuel-Oil Data | 45 | Y | Y | |||||||
| Status of Progress of Villages Electrificationand Irrigation Pump sets Energisation | 46 | Y | Y | |||||||
| District wise status of progress of villageelectrification and energisation of Pump sets | 47 | Y | Y | |||||||
| : District wise Monthly Progress of InhabitedVillage Electrification | 48 | Y | Y | Y | ||||||
| District-Wise Monthly Progress of Energisationof Irrigation Pump sets | 49 | Y | Y | |||||||
| Villages efectrified in various peculationgroups am3 the population covered as on... | 50 | Y | Y | |||||||
| Metering Status for the Month.......year....... | 51 | Y | Y | |||||||
| Details of Failure of Distribution & PowerTransformers in the Month .... Year 20 .... | 52 | Y | Y | |||||||
| Reliability Index at Customer Level for theMonth......year .... | 53 | Y | Y | |||||||
| Reliability Indices (11KV Feeders) for the Month.... Year .... | 54 | Y | Y | |||||||
| Financial Turn Around of Power Distribution forthe Financial Year..... | 55 | Y | Y | |||||||
| Aggregate Technical & Commercial (A T &C) Losses for the Financial Year..... | 56 | Y | Y | |||||||
| Fuel Data of Fossil Fuel Based Thermal PowerStations for the month.....20.... | 57 | Y | Y | |||||||
| Heat Rate Data of Coal/Lignite Based ThermalPower Stations for Month.....Year..... | 58 | Y | Y | |||||||
| Heat Rate Data of Combined Cycle Gas TurbinePower Stations for Month.....20..... | 59 | Y | Y | |||||||
| Monthly Environmental Data of Thermal PowerPlants | 60 | Y | Y | |||||||
| Monthly Peak Hours Generation Data byCoal/Lignite Based or Combined Cycle Gas Turbine (CCGT) PowerStations | 61 | Y | Y | |||||||
| Generating Company Data for Financial Study | 62 | Y | Y | i | ||||||
| Transmission Company Data for Financial Study | 63 | Y | Y | |||||||
| Power Distribution Company Data for FinancialStudy | 64 | Y | Y | |||||||
| Monthly Abstract of Ash Generation andUtilisation | 65 | Y | Y |