State of Bihar - Act
Bihar Electricity Grid Code, 2010
BIHAR
India
India
Bihar Electricity Grid Code, 2010
Rule BIHAR-ELECTRICITY-GRID-CODE-2010 of 2010
- Published on 23 July 2010
- Commenced on 23 July 2010
- [This is the version of this document from 23 July 2010.]
- [Note: The original publication document is not available and this content could not be verified.]
1. Introduction.
- 1.1. (1) The Grid Code lays down the Rules, Guidelines and Standards to be followed by all Users of Grid in the State of Bihar to plan, develop, operate and maintain the power system in the State in the most efficient, reliable, economic and secure manner in integration with the Eastern Regional Grid as per the provisions of Indian Electricity Grid Code (IEGC) notified by the Central Electricity Regulatory Commission (CERC) from time to time.2. All Users that connect with and/or utilize the State Grid are required to abide by the principles and procedures as laid down in the Grid Code in so far as they apply to that User.
3. The Grid Code shall be enforced by STU. Users must provide STU reasonable rights of access, service and facilities necessary to discharge its responsibilities in the users premises and to comply with instructions as issued by STU to implement and enforce the Grid code.
2. SLDC shall bring the non-compliance to the notice of BERC.
3. Consistent failure to comply with the Grid Code provisions may lead to disconnection of the User's plant and /or facilities.
2. STU shall not be held responsible for any consequences that arise from its reasonable and prudent actions on the basis of such information.
2. STU shall not, other than as required by the Grid Code, disclose such information to any person other than Central or State Government and BERC without the prior written consent of the provider of the information.
2. In the event of any conflict between any provision of the Grid Code and any contract or agreement between STU and Users, the provision(s) of the Grid Code will prevail.
2. Glossary and Definition.
-In the Grid Code the following words and expressions shall, unless the subject matter or context otherwise requires or is inconsistent therewith, bear the following meanings:| ABT | Availability Based Tariff |
| Act | The Electricity Act, 2003 (Act No. 36 of 2003) |
| Active Energy | The electrical energy produced, flowing or supplied by anelectric circuit during a time interval, being the integral withrespect to time of the instantaneous power, measured in units ofwatt-hours or standard multiples thereof, |
| Active Power | The product of voltage and the in phase component of alternatingcurrent measured in units of watts and standard multiplesthereof, |
| Apparatus | All the electrical apparatus like machines, fittings, accessoriesand appliances in which electrical conductors are used. |
| Apparent Power | The product of voltage and alternating current measured in unitof volt-amperes and standard multiples thereof, |
| Area of Supply | Area within which a Distribution Licensee is authorized by hislicence to supply electricity. |
| Automatic VoltageRegulatory (AVR) | A continuously acting automatic excitation system to control aGenerating Unit terminal voltage. |
| Authority | Central Electricity Authority (CEA) |
| Auxiliaries | All the plant and machinery required for the generating unit'sfunctional operation that do not form part of the generatingunit. |
| Availability | "Fully Available" shall mean that the Generating Unitis available to its contracted capacity. In respect of theTransmission System, "Availability " shall mean thetime in hours the Transmission System is capable of transmittingelectricity at its rated voltage from the supply point to thedelivery point and expressed as a percentage of AnnualAvailability. |
| Bulk Power Transmission | Agreements made between the STU and its H.T customers and betweenthe Board and CTU. |
| Agreement Backing Down | Reduction of generation on instructions from SLDC / ERLDC by agenerating unit under abnormal conditions. |
| Black start procedure | The procedure necessary to recover from partial or totalblackout. |
| Black start capability | An ability in respect of a Black Start Station, for at least oneof its generating units or CCGT units to start up from shut downand to energize a part of the system and be synchronized to thesystem upon instruction from the State Load Dispatch Centre,within two hours, without any external supply. |
| Black start stations | Generating stations having Black Start Capability. |
| Captive Power Plant(CPP) | A Power Plant set up by any person to generate electricityprimarily for his own use and includes a power plant set up byany co-operative society or association of persons for generatingelectricity primarily for use of members of such co-operativesociety or association. |
| CEA | Central Electricity Authority |
| Central TransmissionUtility (CTU) | Any Government Company which the Central Government may notifyunder sub Section (1) of Section 38 of the Electricity Act, 2003. |
| CERC Central | Electricity Regulatory Commission. |
| Connection | The electric power lines and electrical equipment used to effecta connection of a user's system to the Transmission System. |
| Connection conditions | Those conditions mentioned in Section 5 ("connectionconditions") which have to be fulfilled before the User'sSystem is connected to the State Grid |
| Connection point | An electrical point of connection between the Transmission Systemand the User's System. |
| Consumer | Any person who is supplied with electricity for his own use by alicensee or the Government or by any other person engaged in thebusiness of supplying electricity to public under the ElectricityAct, 2003 or any other law for the time being in force andincludes any person whose premises are for the time beingconnected for the purpose of receiving electricity with the worksof a licensee, the Government or such other person, as case maybe and shall include a person whose electricity supply has beendisconnected. |
| Demand | The demand of Active Power in MW and Reactive Power in MVAR ofelectricity unless otherwise stated. |
| Demand control | Any of the following methods of achieving a load reduction: |
| (a) Consumer Load Management initiated by Users. | |
| (b) Consumer Load reduction by Disconnection initiated by Users(other than following an instruction from Load Despatch Centre). | |
| (c) Consumer Load reduction instructed by the Load DespatchCentre | |
| (d) Automatic under Frequency Load Disconnection | |
| (e) Emergency manual Load Disconnection | |
| Despatch | Operation control of an integrated electricity system involvingoperations such as: |
| (a) Assignment of levels of output to specific Generating Plantor Load control devices to effect the most reliable andeconomical supply as the load vary. | |
| (b) The control of the operation of Extra High Voltage lines,associated sub stations and equipment. | |
| (c) The scheduling of various types of transactions with theelectric utilities over the interconnecting Transmission Lines. | |
| De-synchronize | The act of taking a generating unit off a system to which it hasbeen synchronized. |
| Disconnection | The physical separation of Users or Consumers from the system. |
| Discrimination | The quality where a relay or protective system is enabled to pickout and cause to be disconnected only the faulty apparatus. |
| Distribution Licensees | A licensee authorized under Section 14 of the Act to operate andmaintain a distribution system for supplying electricity to theconsumers in his area of supply. |
| Distribution system | The system of wires and associated facilities between thedelivery points on the transmission lines or the generatingstation connection and the point of connection to theinstallation of the consumers. |
| Drawal | The import / export of electrical energy from / to the grid |
| Earthing | Connecting the conducting parts of an equipment or machinery withthe general mass of earth, in such a manner ensuring at all timesan immediate discharge of energy without danger, by maintainingthe same efficiently at earth's potential. |
| Earthing device | A means of providing connection between a conductor and earthbeing of adequate strength and capability. |
| EHV | Extra High Voltage equal to and greater than 66 kV |
| Frequency | The number of alternating current cycles per second (expressed inHertz) at which the system is operating. |
| Generating company | Any company or body corporate or association or body ofindividuals, whether incorporated or not, or artificial juridicalperson, which owns or operates or maintains a generating station. |
| Generating station | Any station for generating electricity, including any buildingand plant with step-up transformer, switch-yard, switch gear,cables or other appurtenant equipment, if any used for thatpurpose and the site thereof, a site intended to be used for agenerating station, and any building used for housing theoperating staff of a generating station and where electricity isgenerated by water - power, includes, penstocks, head and tailworks, main and regulatory reservoirs, dams and other hydraulicworks, but does not in any case include any sub station. |
| Generating unit | The combination of an electric power generator and its primemover and all of its associated equipment, which togetherconstitutes a single generating machine. |
| Generating schedule | The despatch schedule of a generating station |
| BERC | Bihar Electricity Regulatory Commission |
| Grid | High Voltage backbone system of inter-connected TransmissionLines, Sub Stations and Generating Stations. |
| Grid Code | " Bihar Electricity Grid Code", a document describingthe procedures and the responsibilities for planning andoperation of Bihar Grid. |
| Grid Code Review Panelor 'Panel' | The Panel with the functions set out in the Grid Code* |
| High Voltage or HV IEGC | Voltage greater than 440 V and lower than 33 kV. IndianElectricity Grid Code, a document describing the philosophy andthe responsibilities for planning and operation of Indian PowerSystem specified by the Central Electricity Regulatory Commission(CERC) in accordance with sub-section 1 (h) of Section 79 of theAct. |
| Indian Standards ("IS") | Those Standards and specifications approved by the Bureau ofIndian Standards. |
| Inter-State Transmission System (ISTS) | |
| Inter-State Transmission System includes : | |
| (a) Any system for the conveyance of electricity by means of amain Transmission Line from the territory of one State to anotherState; | |
| (b) the conveyance of electricity across the territory of anintervening State as well as conveyance within a State, which isincidental to such Inter-State transmission of electricity. | |
| (c) The transmission of electricity within the territory of aState built, owned, operated maintained or controlled by theCentral Transmission Utility. | |
| InterconnectingTransformer (ICT) | Transformer connecting EHV lines of different voltage systems. |
| Independent PowerProducer (IPP) | Power Station within the State owned by a generator who is notpart of BSEB. |
| Inter tripping | (a) The tripping of circuit - breaker(s) by commands initiatedfrom protection at a remote location independent of the state oflocal protection; or |
| (b) Operational intertripping. | |
| Intra-State TransmissionSystem | Any system for transmission of electricity other than an Inter -State Transmission System. |
| Isolation | The disconnection of EHV / HV Apparatus from the remainder of theSystem in which that EHV / HV Apparatus is situated. |
| Lean Period | That period in a day for a few hours when the electrical powerdemand remains less than the average demand. |
| Licence | Any licence granted by BERC under provisions of the relevant lawsin force |
| Load | The Active, Reactive or Apparent power as the context requires,generated, transmitted or distributed. |
| Load Factor | Load Factor is the ratio of the average power to the maximumdemand. The load factor depends on the interval of time of themaximum demand and the period over which the average is taken. |
| {| | |
| Load Factor =| Units consumed in a given periodMaximum demand X No. of hours in the period |
Part of – the distribution system.
|-| Under Frequency Relay| An electrical measuring relay intended to operate when itscharacteristic quantity reaches the relay settings by decrease infrequency.|-| User| A term utilized in various Sections of Grid Code to refer to thepersons using the Bihar Grid, as more particularly identified ineach Section of the Grid Code. In the general conditions the termmeans any person to whom the Grid Code applies.|}Words and expressions used and not defined in this code but defined in the Acts shall have the meanings assigned to them in the said Acts. Expressions used herein but not specifically defined in this Code or in the said Acts but defined under any law passed by a competent legislature and applicable to the electricity industry in the State shall have the meaning assigned to them in such law. Subject to the above, expressions used herein but not specifically defined in this Code or in the Acts or any law passed by a competent legislature shall have the meaning as is generally assigned in the electricity industry.3. Management of Grid Code.
- 3.1. Introduction.1. The State Transmission Utility (STU) is required to implement and comply with the Bihar Electricity Grid Code and to carry out periodic review and amendments of the same with the approval of Bihar Electricity Regulatory Commission (BERC). A Review Panel shall be constituted by STU, as required in this Section, comprising of the representatives of the Users of the Transmission System.
2. No change in this Grid Code, however small or large, shall be made without being deliberated and agreed by the Grid Code Review Panel and thereafter approved by BERC. However, in an unusual situation where normal day to day operation is not possible without revision of some clauses of Grid Code, a provisional revision may be implemented before approval of BERC is received, but only after discussion at a special Review Panel Meeting convened on emergency basis. BERC should promptly be intimated about the provisional revision. BERC may issue directions requiring STU to revise the Grid Code accordingly as may be specified in those directions and STU shall promptly comply with any such direction.
2. Any other member can be co-opted as a member of the panel when directed by BERC.
3. The functioning of the Committee shall be co-ordinated by STU. The Member Secretary nominated by STU shall be the convener.
4. STU shall inform all the Users, the names and addresses of the Review Panel, Chairperson and the Member Secretary at least 15 days before the first Review Panel meeting. Any subsequent changes shall also be informed to all the Users by STU. Similarly, each user shall inform the names and designations of their representatives to the Member Secretary of the Review Panel, at least three days before the first Review Panel meeting, and shall also inform the Member Secretary in writing regarding any subsequent changes.
2. All the comments received shall be scrutinized and compiled by STU.These along with STU's comments shall be sent to all the members for their response for the proposed change / modification. If necessary, STU shall convene a meeting of the Review Panel for deliberations. The Member Secretary shall present all the proposed revisions of the Grid Code to the Review Panel for its consideration.
3. Based on the response received, STU shall finalise its recommendation regarding the proposed modification / amendment and submit the same along with all the related correspondence to BERC for approval.
4. STU shall send the following reports to the BERC at the conclusion of each review meeting of the Committee:
5. All revisions to the Grid Code require the approval of BERC. STU shall publish revisions to the Grid Code, after the approval of BERC. STU may submit proposals for relaxation in such cases where Users have difficulties in meeting the requirements of the Grid Code.
6. Any change from the previous version shall be clearly marked in the margin. In addition, a revision sheet shall be placed at the front of the revised version noting the number of every changed sub-section, together with reasons for such change.
7. STU shall maintain copies of the Grid Code with the latest amendments and shall make it available at a reasonable cost to any person requiring it. This may also be made available on the website.The STU shall keep an up to date list of recipients of all the copies of the Grid Code, if found necessary to ensure that the latest version of Grid Code is reached to all the relevant recipients.
8. The Commission, may, on the application of the Users or otherwise, call the emergency meeting of the Review Panel as and when the situation so dictates and make such alterations or amendments in the Grid Code as it thinks fit.
Chapter 2
Planning Code
4. System Planning.
- 4.1. Introduction -1. This Section specifies the methods for data submission by Users to STU for planning and development of the State Transmission System. This Section also specifies the procedures to be adopted by STU in the planning and development of the State Transmission System.
2. Requirement for reinforcement or extension of the State Transmission system arise due to many reasons of which a few are mentioned below:
3. The reinforcement or extension of the State Transmission System may involve work at an entry or exit point (connection point) of a User to the State Transmission System. Since development of all User's systems must be planned well in advance to ensure consents and way leaves to be obtained and detailed engineering design / construction work to be completed, STU will require information from Users and vice versa. To this effect, the planning code imposes time scale for exchange of necessary information between STU and Users.
2. STU shall carry out network studies and review fault levels for planning system strengthening and augmentation.
3. STU shall follow the following steps in planning:
4. All Users shall supply to STU, the planning data prescribed in Appendix A and Appendix B of Data Registration Code within 3 months from the effective date of the Grid Code and thereafter such data shall be furnished by 31st March every year to enable STU to formulate/ finalise the updated plan by 30th September each year for the next 5 years.
2. The State Transmission System planning and generation expansion planning shall be in accordance with the provisions of the planning criterion as per IEGC Clause 3.5.
2. Generating stations shall provide their generation capacity to STU for evacuating power from their power stations for each of the succeeding 5 years along with their proposals for augmentation of transmission proposals and submit the same annually by 31st March to STU.
3. The planning for strengthening the State Transmission System for evacuation of power from outside State Stations shall be initiated by STU.
2. To enable the Users to co-ordinate planning design and operation of their plants and systems with the State Transmission System, they may seek certain data of transmission system as applicable to them, which the STU shall supply from time to time as detailed under Data Registration Section categorized as;
(a)Standard Planning Data (Transmission) as per Appendix A.(b)Detailed Planning Data (Transmission) as per Appendix B.5. Connection Conditions.
- 5.1. Introduction -This Section specifies the technical, design and operational criteria which shall be complied with by every User connected or seeking connection to the State Transmission System.Any user seeking connection to or connected with the Intra-State System shall comply with the CEA Regulations 2007 "Technical Standards for connectivity to the Grid".This applies to all users seeking connection or connected to the Intra-State System.1. The User shall meet all necessary conditions as specified in the State Grid Code and submit the application to STU containing all the information as may be specified.
2. STU shall make a formal offer within 60 days of the receipt of the application. The offer shall specify and take into account any work required for the extension or reinforcement of the State Transmission System necessitated by the applicant's proposal and for obtaining any consent necessary for the purpose. STU shall process the application in accordance with the CEA Regulations on Grid Connectivity
3. If the specified time limit for making the offer against any application is not adequate, STU shall make a preliminary offer within the specified time indicating the extent of further time required for detailed analysis.
4. Any offer made by STU shall remain valid for a period of 60 days and unless accepted before the expiry of such period, shall lapse thereafter.
5. In the event of offer becoming invalid or not accepted by the applicant, STU shall not be bound to consider any further application from the same applicant within 12 months unless the new application is substantially different from the original application.
6. The applicant shall furnish the Detailed Planning Data as per Appendix-B.
2. Model Connection agreement /-This shall be prepared by STU and submitted to the Commission for approval.
2. The format to be used in the preparation of Site Responsibility Schedule is given in Appendix - D.
2. Installation of all electrical equipment shall comply with IE Rules, 1956 which are in force for time being and will be replaced by new Rules made under Electricity Act, 2003.
3. For every new/modified connection sought the STU shall specify the connection point, technical requirements and the voltage to be used, along with metering, telemetering and protection requirements as specified in the Metering Code and Protection Code.
4. Insulation coordination of the User's equipment shall conform to the applicable values as specified by STU from time to time out of those applicable as per Indian Standards / Code of Practices. Rupturing capacity of the switch gear shall not be less than that specified by STU from time to time.
5. Protection schemes and metering schemes shall be as detailed in the Protection Code and Metering Code.
6. The State Transmission System rated frequency shall be 50.00 Hz and shall be regulated by the provisions of IEGC as given below:
| Target Range | ||
| Upper limit | - | 50.20 Hz |
| Lower limit | - | 49.50 Hz |
7. The Users shall be subject to the Grid discipline prescribed by SLDC and ERLDC.
8. The variation of voltage at the interconnected point should not be more than voltage range specified below:
| Nominal (KV) | % limit of variation | Maximum (KV) | Minimum (KV) |
| 400 | +5%/- 5% | 420 | 380 |
| 220 | +/-10% | 245 | 198 |
| 132 | +/-10% | 145 | 122 |
2. Distribution Licensee. - (i) Voltage may be LV side of power transformer i.e. 33 KV or 11 KV or a agreed with STU. For EHV consumers directly connected to transmission system, voltage may be 220 KV/132 KV
3. Eastern Regional Transmission System. - The Connection, protection scheme, metering scheme and the voltage shall be in accordance with the provisions of IEGC.
4. Independent Power Producers (IPPs), Captive Power Plants (CPPs), Extra High Voltage (EHV) Consumers and Open Access Customers. -
Chapter 3
System Operation Code
6. Operation Planning.
- 6.1. Introduction -This Section describes the process by which the SLDC carries out the operational planning and demand control procedures to permit reduction in demand for any reason.2. No part of the State Transmission System shall be isolated from the integrated grid except under the following conditions;
3. Complete synchronization shall be restored as soon as conditions permit. The restoration process shall be supervised by SLDC.
4. The 132 KV and above transmission lines (except radial lines which do not affect the operation of the Grid) and the inter connecting power transformers should not be opened or removed from service without instruction or prior clearance from the SLDC. Under emergencies where prior clearance from SLDC is not possible, it should be intimated to SLDC at the earliest possible time after the incident and get the clearance, while bringing back these lines into service.
5. Any tripping, whether manual or automatic of transmission lines by 132 KV and above or power transformers of 132 KV class and above and 50 MVA and above shall be promptly reported to the SLDC at the earliest along with the reasons for such tripping and the likely time required for restoration. The information / data including that down loaded from disturbance recorder, sequential event recorder etc. required for the purpose of analysis shall be sent to SLDC. For restoration of tripped equipment / line, SLDC shall be informed and get its clearance.
6. All generating units of 200 MW and above in case of thermal and 10 MW and above in case of hydro which are synchronized with the grid irrespective of their ownership shall have their governors in normal operation at all times. If any generating unit of over 50 MW size is required to be operated without its governor in normal operation, the ERLDC through SLDC shall be immediately intimated about the reason and duration of such operation. The exemption from free governor mode operation in respect of run of river hydro stations without any pondage, steam turbine of thermal and gas based power stations not having free governor mode facility shall be obtained from CERC under clause 1.6 of IEGC.
7. Facilities available with / in Load limiter, Automatic Turbine Run-up System (ATRS), Turbine Supervisory Coordinated Control System etc., shall not be used to bye pass the normal governor action in any manner. No dead bands and time delays shall be deliberately introduced.
8. All generating units operating in Free Governor Mode Operation (FGMO) at or upto 100% of their maximum continuous rating shall normally be capable of (and shall not be prevented from) picking upto 5% extra load, more than the declared maximum continuous rating, for atleast five minutes or within the technical limits specified by the manufacturers, when the frequency falls due to a system contingency. In case any generating unit of 50 MW and above size does not meet this requirement for any period, the generating company should intimate the same to SLDC along with reasons thereof. Any generating unit not capable of complying with above provisions either due to not having requisite facilities or otherwise shall seek exemption from Central Electricity Regulatory Commission (CERC) under clause 1.6 of IEGC.
9. In case frequency falls below 49.5 Hz, all partly loaded Generating Units shall pick up additional load at a faster rate, according to their capability. SLDC in consultation with ERLDC and Distribution Licensees shall prepare a plan for automatic load relief during the low frequency conditions. In case frequency rises to 50.5 Hz or higher, neither any generating unit shall be synchronized with the Grid nor shall generation at any generating station (irrespective of type or ownership) be increased without obtaining approval from SLDC.
10. Except under an emergency, or to prevent an imminent damage to costly equipment, no User shall suddenly decrease/increase its generation without prior intimation to the SLDC. Similarly, no User shall cause a sudden decrease/increase in its load due to imposition/lifting of power cuts etc., without prior intimation to and consent of SLDC, particularly when frequency is deteriorating.
11. All Generating Units shall normally have their Automatic Voltage Regulators (AVRs) in operation, with appropriate settings. In particular, if a Generating Unit of over 50 MW capacity is required to be operated without its AVR in service, the same should be operated only after prior concurrence of SLDC.
12. Each Generating Unit must be fitted with a turbine speed governor having an overall droop characteristic within the range of 3% to 6%, which shall always be in service.
13. State Generating Stations and other generating stations connected to the Grid shall follow the instructions of SLDC for backing down/boxing up (ramping-down) and shutting down the generating unit(s). SLDC shall provide the certificate for the period of the backing down/boxing up or shutting down for the purpose of computing the deemed generation, if required.
14. Various steps shall be taken for frequency management and voltage management so as to ensure system security from these considerations.
2. It shall be the responsibility of all Distribution Licensees to fully cooperate with STU in preparation of. demand forecast for the entire State.
3.
The long term demand estimation / load forecast (for more than 1 year) shall be done by STU and SLDC shall be provided with a copy of the same as and when it is finalized.SLDC shall inform its load projections (both peak and off - peak) in ERPC forum for three months, to be reviewed every month ahead.4. The Distribution Licensees shall provide to the STU and SLDC their estimates of demand for each inter connection point for the next financial year by 31st January of each year Distribution Licensees shall also provide daily demand for the month ahead at each inter connection point by 25th of the month.
5. Based on the data furnished by the Distribution Licensees, STU shall make monthly peak and lean period demand estimates for year ahead and daily peak and lean period demand estimates for the month ahead and furnish the same to SLDC.
6.
The Distribution Licensee shall provide to SLDC on day ahead basis, at 9.00 hrs, each day their estimated demand for each 15 minute block for the ensuing day. The Distribution Licensee shall also provide to SLDC estimates of loads that may be shed, when required, in discreet blocks with details of arrangement of such load shedding.7. The SLDC would update demand forecast (in MW as well as kWh) on quarterly, monthly, weekly and ultimately on daily basis which would be used in the day - ahead scheduling.
2. Whenever restoration of large portions of the total demand disconnection effected by the automatic load shedding is not possible within a reasonable time, the SLDC shall implement additional disconnection manually, to restore an equivalent amount of demand disconnected automatically.
Each Distribution Licensee shall help the SLDC in identifying such load blocks.Load shed by the operation of automatic load shedding devices shall not be restored without specific directions from the SLDC.3. Planned manual disconnections shall be implemented by the SLDC when there is a shortfall in generation, or constraints in Transmission System, or reduction of imports through external connection etc., requiring demand control to control the over-drawl of power from Inter State Generating State (ISGS) when the system frequency falls below 49.5 Hz. In such cases a rotational load shedding scheme shall be adopted to ensure equitable treatment for all consumers as far as practicable.
4. Emergency Manual Disconnection to deal with unacceptable voltage and frequency levels etc. shall be implemented by the SLDC when loss of generation, mismatch of generation with the demand, constraints in the transmission system, over-drawal from the grid in excess of respective schedule affecting the frequency of the regional grid below 49 Hz, requiring load shedding at short notice or no notice, to maintain a regulating margin.
5. These control measures shall not be withdrawn till the system frequency improves and when the SLDC issues such instructions after review of the situation.
2. While implementing the above, the system security aspects should not be violated as per provisions in Section 5.2 of IEGC and Section 6.3 of the Grid Code.
7. Outage Planning.
- 7.1. Introduction -This Section describes the procedure for preparation of outage schedules for the elements of the State Grid in a coordinated and optimal manner keeping in view the State Grid operating conditions and the balance of generation and load.2. SLDC is however authorised to defer the outage in case of any of the following events:
• Major grid disturbance• System Isolation• Black out in the State• Any other event in the system that may have an adverse impact on system security by the proposed outage3. Each User shall obtain approval of SLDC, prior to availing the Outage. SLDC while permitting any circuit for outage shall issue specific code. Similarly, no inter user boundary circuits shall be connected back to the State Transmission System without specific code/approval by SLDC.
This restriction shall however not be applicable to individual Generating Unit(s) of a CPP.2. Scheduled outage of power station of 50 MW and above and EHV lines as notified by ERLDC, will also be subject to annual planning of ERPC Secretariat in co-ordination with SLDC.
3. SGS (except CPPs) connected to the State Grid shall furnish their proposed Outage programme for the next financial year in writing by 15th November each year.
4. SGS Outage programme shall contain details like identification of unit, reason for outage, generation availability affected due to such outage, outage start date and duration of outage. SLDC shall review the outage programme received from SGS on monthly basis to chalk out the outage of the State Transmission System.
5. SLDC shall also obtain from STU, the proposed outage programme for Transmission lines, equipments and sub-stations etc. for next financial year by 15th November each year. STU outage programme shall contain identification of lines/ substations, reasons for outage, outage start date and duration of outage.
6. Scheduled outage of power stations and EHV transmission lines affecting regional power system shall be affected only with the approval of ERPC in coordination with SLDC.
7. Scheduled outage of power stations of capacity 25 MW and above, of all EHV lines and HV lines forming interconnection between two EHV substations (and those notified as such by SLDC) shall be approved by SLDC, 24 hours in advance based on prevalent operating conditions.
8. In respect of scheduled outage referred in this Section a calendar shall be formulated in respect of annual outage planning for the ensuing financial year. Such outage plan shall be deliberated and finalised in the meeting of the Operation and Co-ordination Committee (OCC). to be constituted by SLDC at the State level.
a. SLDC shall submit the proposed annual outage plan of the next financial year to ERPC Secretariat by 30th November of preceding year.b. Final annual outage plan shall be communicated to ERPC Secretariat by 15th January of each year.8. Contingency Planning.
- 8.1. Introduction -This Section describes the steps in the recovery process to be followed by all Users in the event of total or partial blackouts of the State Transmission System or Regional System.2. In case of partial black out in the system/State, priority is to be given for early restoration of power station units, which have tripped. Start up power for the power station shall be extended through shortest possible route and within shortest possible time from adjoining substation/ power station where the supply is available. Synchronising facility at all power stations and 220 kV sub-station having interconnection with ISTS shall be available.
3. In case of total regional black out, SLDC In-charge shall co-ordinate and follow the instructions of ERLDC for early restoration of the entire grid. Startup power to the thermal stations shall be given by the hydel stations or through interstate supply, if available. All possible efforts shall be made to extend the hydel supply to the thermal power stations through shortest transmission network so as to avoid high voltage problem due to low load conditions. For safe and fast restoration of supply, SLDC shall formulate the proper sequence of operation for major generating units, lines, transformers and load within the State in consultation with ERLDC.The sequence of operation shall include opening, closing/tripping of circuit breakers, isolators, on-load tap-changers etc.
2. The restoration process shall take into account the generator capabilities and the operational constraints of Regional and the State Transmission System with the object of achieving normalcy in the shortest possible time. All Users should be aware of the steps to be taken during major Grid Disturbance and system restoration process.
2. Distribution Licensees with essential loads shall separately identify non-essential components of such loads, which may be kept off during system contingencies. They shall also draw up an appropriate schedule with corresponding load blocks in each case. The nonessential loads can be put on only when system normalcy is restored, as advised by SLDC.
3. All Users shall pay special attention to carry out the procedures so that secondary collapse due to undue haste or inappropriate loading is avoided.
4. Despite the urgency of the situation, careful, prompt and complete logging of all operations and operational messages shall be ensured by all Users to facilitate subsequent investigation into the incident and the efficiency of the restoration process. Such investigation shall be conducted promptly after the incident and placed before the Grid Code Review Panel in its next meeting.
9. Cross Boundary Safety.
- 9.1. Introduction -This Section specifies the requirements for safe working practices for maintenance of equipment associated with cross boundary operations. It lays down the procedure to be followed when work is required to be carried out on electrical equipment that is connected to another User's system.2. All Users with a direct inter user boundary with STU or other User system shall issue a similar list of their Designated Officers to STU or other User(s), which shall be updated promptly whenever there is a change in the list.
3. Whenever work across a cross boundary / an inter-user boundary is to be carried, the Designated Officer of the User including STU itself, wishing to carry out work shall personally contact the other relevant Designated Officer. If the Permit to Work (PTW) cannot be obtained personally, the Designated Officers shall contact through telephone and exchange Code words to ensure correct identification of both agencies.
4. Should the work extend over more than one shift, the Designated Officer shall ensure that the relief Designated Officer is fully briefed on the nature of the work and the code words in operation.
5. The Designated Officer(s) shall co-operate to establish and maintain the precautions necessary for the required work to be carried out in a safe manner. Both the established isolation and the established earth shall be locked in position, where such facilities exist, and shall be clearly identified.
6. Work shall not commence until the Designated Officer of the User including STU itself, wishing to carry out the work, is satisfied that all the safety precautions have been established. This Designated Officer shall issue agreed safety documentation (PTW) to the working party to allow work to commence. The PTW in respect of specified EHV lines and other interconnections shall be issued with the consent of SLDC.
7. When work is completed and safety precautions are no longer required, the Designated Officer who has been responsible for the work being carried out shall make direct contact with the other Designated Officer to return the PTW and for removal of those safety precautions. Return of PTW in respect of specified EHV lines and interconnections shall be informed to SLDC.
8. The equipment shall only be considered as suitable for connecting back to service when all safety precautions are confirmed as removed, by direct communication using code word contact between the two Designated Officers, and after ensuring that the return of agreed safety documentation (PTW) from the working party has taken place.
9. STU shall develop an agreed written procedure for inter-user boundary safety and continually update it.
10. Any dispute concerning inter user Boundary Safety shall be resolved at the level of STU, if STU is not a party. In case STU is a party, the dispute shall be referred to BERC for resolution of the dispute.
2. Each Designated Officer shall maintain a legibly written safety logbook, in chronological order, of all operations and messages relating to safety co-ordination sent and received by him. All safety logs shall be retained for a period of not less than 10 years.
10. Operational Event/Accident Reporting.
- 10.1. Introduction -This Section describes the reporting procedure of reportable events in the State Transmission SystemThis Section applies to SLDC, STU and all entities embedded within State power system that are under the control and supervision of SLDC.2. SLDC shall call for a report from any User on any reportable incident affecting other Users and STU, in case the same is not reported by such User whose equipment might have been source of the reportable incident.
The above shall not relieve any User from the obligation to report events in accordance with IE Rules 1956 - (Language used in the Code to be used). The format of such a report shall be as agreed by the State Grid Code Review Panel, but will typically contain the following information:i. Location of incident.ii. Date and time of incident.iii. Plant or equipment involved.iv. Details of relay indications with nature of fault implications, Antecedent conditions like line flows, bus voltage, generation and demandv. Supplies and quantum interrupted and duration if applicable.vi. Amount of generation lost if applicable and its durationvii. Brief description of incident.viii. Estimate of time to return to service.ix. Name of Organisationx. Possibility of alternate arrangement of supplyChapter 4
Scheduling and Despatch Code
11. Scheduling and Despatch.
- 11.1. Introduction -This Section specifies the procedure to be adopted for the scheduling and despatch of State Generating Station (SGS) and Inter-State Generating Station (ISGS) to meet system demand and drawal allocation requirements of Distribution Licensees.1. SLDC will issue despatch instructions required to regulate all generation and imports from IPPs / CPPs according to the 15-minute day ahead generation schedule. In the absence of any despatch instruction by SLDC, SGS shall generate/ export according to the day ahead generation schedule.
2. The SLDC shall regulate the overall State generation in such a manner that generation from following types of power stations shall not be curtailed except under abnormal operating conditions.
3. Despatch instructions to SGS shall be in standard format to be finalized by SLDC.
4. The algebraic sum of scheduled drawals from ISGS, long term open access, and short term open access arrangements shall be the net drawal schedule for the control area of the utility.
2. Despatch instructions shall be issued by E-Mail /Fax/ telephone, confirmed by exchange of name of operators sending and receiving the same and logging the same at each end. All such oral instructions shall be complied with forthwith and written confirmation shall be issued promptly by FAX, tele-printer or otherwise
2. Generating Stations within the State shall follow the despatch instructions issued by SLDC.
3. Distribution Licensees and Open Access Customers shall comply with the instructions of SLDC for managing load & reactive power drawal as per system requirement.
12. Frequency and Voltage Management.
- 12.1. Introduction -This Section describes the method by which all Users of the State Transmission System shall co-operate with SLDC and STU in contributing towards effective control of the system frequency and managing the voltage of the State Transmission System. The State Transmission System normally operates in synchronism with the Eastern Region Grid and ERLDC has the overall responsibility of the integrated operation of the Eastern Regional Power System. The constituents of the Region are required to follow the instructions of ERLDC for backing down generation, regulating loads, MVAR drawal etc. to meet the objective. SLDC shall accordingly instruct Generating Units to regulate Generation/Export and adhere to active and reactive power generation within their respective declared parameters. SLDC shall also regulate the load as may be necessary to meet the objective. The State Transmission System voltage levels can be affected by Regional operation. The STU/SLDC shall optimize voltage management by adjusting transformer taps (On Line Tap Changers) to the extent available and switching of circuits/ capacitors/ reactors and other operational steps. SLDC will instruct SGS to regulate MVAr generation within their declared parameters. SLDC shall also instruct Distribution Licensees to regulate demand, if necessary by operating reactors/ capacitor banks nearest to load point in 33KV system.| Voltage (KV r ms) | ||
| Nominal | Maximum | Minimum |
| 400 | 420 | 380 |
| 220 | 245 | 198 |
| 132 | 145 | 122 |
13. Monitoring of Generation and Drawal.
- 13.1. Introduction - The monitoring of SGS output, active and reactive reserve capacity is important to evaluate the performance of generation plants.The monitoring of actual drawal against schedule is important to ensure that STU and Distribution Licensees contribute towards improving system performance and observe Grid discipline.Chapter 5
Protection Code
14. Protection.
- 14.1. introduction -In order to safeguard the State Transmission System and Users' system from faults occurring in other User's system, it is essential that certain minimum standards for protection be adopted. This Section describes these minimum standards.| Nominal Voltage | Minimum Short Circuit current rating &duration for Switchgear | Target Fault clearance Time | |
| KV | KA(rms) | Seconds | msec. |
| 220 KV | 40 | 1 | 160 |
| 132 KV | 40 | 1 | 160 |
Chapter 6
Metering Code
15. Metering Code.
- 15.1. Introduction -This code prescribes a uniform policy in respect of electricity metering in the State Transmission System amongst the utilities i.e. STU, Generating Companies, Distribution Licensees and for the Open Access Customers on the State Transmission system and EHV Consumers (of Distribution Licensees) directly connected to the State Transmission System.2. Right to Install Energy Meters. - Each User shall extend necessary assistance and make available the required space to the other User for installation of the metering equipment and provide required outputs of the specified current and voltage transformers to facilitate installation of Meters, RTUs and associated equipment in their premises.
3. Access to Equipment and Data. - Each User on request, shall grant full right to install metering equipments and RTUs to other User's employees, agents/duly authorized representative. The other Users shall also have access to metering locations for inspecting, testing, calibrating, sealing, replacing the damaged equipment, collecting the data, joint readings of meters and metering equipments, and other functions necessary jointly or otherwise as mutually agreed.
4. Operation and Maintenance of the Metering System. - The operation and maintenance of the metering system includes proper installation, regular maintenance of the metering system and RTUs, checking of errors of the CTs, VTs and meters, proper laying of cables and protection thereof, cleaning of connections/joints, checking of voltage drop in the CT/VT leads, condition of meter box and enclosure, condition of seals, regular/daily reading meters and regular data retrieved through CMRI, attending any breakdown/fault on the metering system etc.
5. Type of Meters and Metering Capability. - The meters shall be all electronic (static) poly phase tri-vector type having facility to measure active, reactive and apparent energy/power in all four quadrants i.e. a true import-export meter. All inter user meters shall be bi-directional while capacitor bank meters and substation aux. meters may be unidirectional. ABT compliant energy meters shall be provided at such interface points, wherever the energy exchange is based on Availability Based Tariff (ABT).
| SI. No. | Particulars | Meter Type | |||||
| Main & Check | Back up | Capacitor Bank | Sub-Station Auxiliary | Inter Distribution Licensees | Secondary Back up | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| (1) | Accuracy class | ||||||
| (a) Meter | 0.2 S | 0.2 S | 0.5 S | 1.0 | 0.2 S | 0.2 S | |
| (b) CTs | 0.2 | 0.2 | 0.2 | 0.2 | 0.2 | 0.2 | |
| (c) PTs / CVTs | 0.2 | 0.2 | 0.2 | 0.2 | 0.2 | 0.2 | |
| (d) CT-PT sets for 33 KV & 11 KV feeders | 0.2 | Existing | Existing | Existing | Existing | Existing | |
| (2) | Salient aspect of meters | ||||||
| (a) Phase angle and ratio error compensation ofCTs & PTs | No | No | No | No | No | No | |
| (b) Communication port | |||||||
| (i) Optical port | Yes | Yes | No | No | Yes | Yes | |
| (ii) For remote reading | Yes | Yes | No | No | Yes | Yes | |
| (c) Whether both Import & Export featuresrequired | Yes | Yes | No | No | Yes | Yes | |
| (d) Meter memory for 45 days | Yes | Yes | No | No | Yes | Yes |
Chapter 7
Data Registration Code
16. Data Registration.
- 16.1. Introduction -This Section specifies a list of all data required by STU and SLDC, which is to be provided by the Users, and data required by Users to be provided by STU at times specified in the Grid Code. Other Sections of the Grid Code contain the obligation to submit the data and define the times when data is to be supplied by the Users.2. All Users shall provide STU and SLDC with the name, address and telephone number of the person responsible for sending the data.
3. STU shall inform all Users and SLDC of the name, address and telephone number of the person responsible for receiving data.
4. STU shall provide up-to-date data to Users as provided in the relevant Sections of the Grid Code.
5. Responsibility for the correctness of data rests with the concerned User providing the data.
2. Changes to Users Data. - Whenever any User becomes aware of a change to any items of data that is registered with STU, the User must promptly notify STU of the changes. STU on receipt of intimation of the changes shall promptly correct the database accordingly. This shall also apply to any data compiled by STU regarding its own system.
3. Methods of Submitting Data. - a. The data shall be furnished in the standard formats for data submission and such formats must be used for the written submission of data to SLDC and STU.
Where standard formats are not appended they would be developed by SLDC or STU in consultation with Users.b. All data to be submitted under the Schedule(s) must be submitted to SLDC / STU or to such other department and/or entity as STU may from time to time notify to Users. The name of the person who is submitting each schedule of data shall be indicated.c. Where a computer data link exists between a User and SLDC/ STU, data may be submitted via this link. The data shall be in the same format as specified for paper transmission except for electronic encoding for which some other format may be more suited. The User shall specify the method to be used in consultation with the SLDC/ STU and resolve issues such as protocols, transmission speeds etc. at the time of transmission.4. Data not supplied. - All Users are obliged to supply data as referred to in the individual Sections of the State Grid Code and listed out in the Data Registration Section Appendices. In case any data is not supplied by any User or is not available, STU or SLDC may, acting reasonably, if and when necessary, estimate such data depending upon the urgency of the situation. Similarly, in case any data is not supplied by STU, the concerned User may, acting reasonably, if and when necessary, estimate such data depending upon urgency of the situation. Such estimates will in each case, be based upon corresponding data for similar Plant or Apparatus or upon such other information, the User or STU or SLDC, as the case may be, deems appropriate.
| i | Site | Furnish location map to scale showing roads,railway lines, Transmission lines, canals, pondage and reservoirsif any. |
| ii | Coal linkage/ Fuel (Like Liquefied Natural Gas,Naphtha etc.) linkage | Give information on means of coaltransport/carriage. In case of other fuels, give details ofsource of fuel and their transport. |
| iii | Water Sources | Give information on availability of water foroperation of the Power Station. |
| iv | Environmental | State whether forest or other land areas areaffected. |
| v | Site Map (To Scale) | Showing area required for Power Station coallinkage, coal yard, water pipe lines, ash disposal area, colonyetc. |
| vi | Approximate period of construction | |
| (2) Connection | ||
| i | Point of Connection | Furnish single line diagram of the proposedConnection with the system. |
| ii | Step up voltage for Connection (kV) | |
| (3) Station Capacity | ||
| i | Total Generating Station capacity (MW) | State whether development will be carried out inphases and if so, furnish details. |
| ii | No. of units & unit size (MW) | |
| (4) Generating Unit Data | ||
| i | Steam Generating Unit | State type, capacity, steam pressure, streamtemperature etc. |
| ii | Steam turbine | State type, capacity. |
| iii | Generator | TypeRating (MVA)Speed (RPM)Terminal voltage (KV)Rated Power FactorReactive PowerCapability(MVAr) in the range0.95 of leading and 0.85 lagging Short Circuit RatioDirect axis(saturated) transient reactance (% on MVA rating)Direct axis(saturated) sub-transient reactance (% on MVA rating)Auxiliary PowerRequirementMW and MVArCapability curveRamp-up and ramp-downrateGenerator Characteristic curve |
| iv | Generator | TransformerTypeRated capacity (MVA)Voltage Ratio (HV/LV)Tap change Range (+ %to - %)Percentage Impedance (Positive Sequence at Fullload) |
| i | Site | Give location map to scale showing roads,railway lines, and transmission lines. |
| ii | Site map (To scale) | Showing proposed canal, reservoir area, waterconductor system, fore-bay, power house etc. |
| iii | Submerged Area | Give information on area submerged, villagessubmerged, submerged forest land, agricultural land etc |
| iv | Whether storage type or run of river type | |
| v | Whether catchment receiving discharges fromother reservoir or power plant. | |
| vi | Full reservoir level | |
| vii | Minimum draw down level. | |
| viii | Tail race level | |
| ix | Design Head | |
| x | Reservoir level v/s energy potential curve | |
| xi | Restraint, if any, in water discharges | |
| xii | Approximate period of construction. | |
| (2) Connection | ||
| i | Point of Connection | Give single line diagram proposed Connectionwith the Transmission System. |
| ii | Step up voltage for Connection (kV) | |
| (3) Station Capacity | ||
| i | Total Power Station capacity (MW) | State whether development is carried out inphases and if so furnish details. |
| ii | No. of units & unit size (MW) | |
| (4) Generating Unit Data | ||
| i | Operating Head (in Metres) | a. Maximumb. Minimumc. Average |
| Hydro Unit | Capability to operate as synchronous condenserWater head versus discharges curve (at full and part load) Powerrequirement or water discharge while operating as synchronouscondenser | |
| i | Turbine | State Type and capacity |
| iii | Generator | TypeRating (MVA)Speed (RPM)Terminal voltage (KV)Rated Power FactorReactive PowerCapability (MVAr) in the range 0.95 of leading and 0.85 oflagging MW & MVAr capability curve of generating unitShort Circuit RatioDirect axis transient(saturated) reactance (% on rated MVA)Direct axissub-transient (saturated) reactance (% on rated MVA)Auxiliary Power Requirement (MW) |
| iv | Generator-Transformer | a.Typeb. Rated Capacity(MVA)c. Voltage RatioHV/LVd. Tap change Range(+% to -%)e. Percentage Impedance (Positive Sequence atFull Load). |
| STU shall make arrangements for getting therequired data from different Departments of STU/othertransmission licensees (if any) to update its Standard PlanningData in the format given below: |
| i. Name of line (Indicating Power Stations and substations to beconnected). |
| ii. Voltage of line (KV). |
| iii. No. of circuits. |
| iv. Route length (km). |
| v. Conductor sizes. |
| vi. Line parameters (PU values). |
| (a) Resistance/km |
| (b) Inductance/km |
| (c) Susceptance/ km |
| vii. Approximate power flow expected- MW & MVAr. |
| viii. Terrain of the route- Give information regarding nature ofterrain i.e. forest land, fallow land, agricultural and riverbasin, hill slope etc. |
| ix. Route map (to scale) - Furnish topographical map showing theproposed route showing existing power lines and telecommunicationlines. |
| x. Purpose of Connection- Reference to Scheme, wheeling to otherStates etc. |
| xi. Approximate period of Construction. |
| (1) General | ||
| i | Area Map (to scale) Furnish map of Bihar dulymarked with the area of supply relevant for the DistributionLicence. | |
| ii | Consumer Data Furnish categories of consumers,their numbers and connected loads. | |
| iii | Reference to Electrical Divisions presently incharge of the Distribution. | |
| (2) Connection | ||
| i | Points of Connection Furnish single line diagramshowing points of Connection | |
| ii | Voltage of supply at points of Connection | |
| iii | Names of Grid Sub-Station feeding the points ofConnection | |
| (3) Lines and Substations | ||
| i | Line Data Furnish lengths of line and voltageswithin the Area. ' | |
| ii | Sub-station Data Furnish details of 132/11 KVsub-stations, 33/11 KV sub-station, capacitor installations | |
| (4) Loads | ||
| i | Loads drawn at points of Connection. | |
| ii | Details of loads fed at EHV, if any. Give nameof consumer, voltage of supply, contract demand/load and name ofGrid Substation from which line is drawn, length of EHV line fromGrid Sub-station to consumer's premises. | |
| iii | Reactive Power compensation installed | |
| (5) Demand Data (for All Loads 1 Mw andAbove) | ||
| i | Type of load State whether furnace loads,rolling mills, traction loads, other industrial loads, pumpingloads etc. | |
| ii | Rated voltage and phase | |
| iii | Electrical loading of equipment State number andsize of motors, types of drive and control arrangements. | |
| iv | Sensitivity of load to voltage and frequency ofsupply. | |
| v | Maximum Harmonic content of load. | |
| vi | Average and maximum phase unbalance of load. | |
| vii | Nearest sub-station from which load is to befed. | |
| viii | Location map to scale Showing location of loadwith reference to lines and sub-stations in the vicinity. | |
| (6) Load Forecast Data | ||
| i | Peak load and energy forecast for each categoryof loads for each of the succeeding 5 years. | |
| ii | Details of methodology and assumptions on whichforecasts are based. | |
| iii | Details of loads 1 MWand above.a. Name ofprospective consumer.b. Location andnature of load.c. Sub-Station fromwhich to be fed.d. Voltage of supply.e. Phasing of load. |
1. Rated MVA.
2. Voltage Ratio.
3. Vector Group.
4. Positive sequence reactance for maximum, minimum, normal Tap. (% on MVA).
5. Positive sequence resistance for maximum, minimum, normal Tap. (% on MVA).
6. Zero sequence reactance (% on MVA).
7. Tap changer Range (+% to -%) and steps.
8. Type of Tap changer, (off/on load).
ii. In relation to switchgear including circuit breakers, isolators on all circuits connected to the points of Connection:1. Rated voltage (kV).
2. Type of circuit breaker (MOCB/ABCB/SF6).
3. Rated short circuit breaking current (kA) 3 phase.
4. Rated short circuit breaking current (kA) 1 phase.
5. Rated short circuit making current (kA) 3 phase.
6. Rated short circuit making current (kA) 1 -phase.
7. Provisions of auto reclosing with details.
iii. In relation to the Lightning Arresters -Technical dataiv. In relation to the Communication - Details of communication equipment installed at points of connections.v. In relation to the Basic Insulation Level (kV) -1. Busbar.
2. Switchgear.
3. Transformer bushings.
4. Transformer windings.
1. Hot
2. Warm
3. Cold
iv. Maximum Generating Unit loading rates for the following conditions:1. Hot
2. Warm
3. Cold
v. (v) Minimum load without oil support (MW).1. Land
2. Coal
3. Water
4. Environmental clearance
5. Rehabilitation of displaced persons
iii. Techno-economic approval by Central Electricity Authority (CEA).iv. Approval of State Government/Government of India.v. Financial Tie-up.1. Multipurpose
2. For Power
c. Operating Table with1. Area capacity curves and
2. Unit capability at different net heads
1. Rated MVA
2. Voltage Ratio
3. Vector Group
4. Positive sequence reactance for maximum, minimum and normal Tap.(% on MVA).
5. Positive sequence resistance for maximum, minimum and normal Tap.(% on MVA).
6. Zero sequence reactance (% on MVA)
7. Tap changer range (+% to -%) and steps.
8. Type of Tap changer (off/on load).
9. Neutral grounding details.
ii. Switchgear (including circuit breakers, Isolators on all circuits connected to the points of Connection).1. Rated voltage (KV).
2. Type of Breaker (MOCB/ABCB/SF6).
3. Rated short circuit breaking current (KA) 3 phase.
4. Rated short circuit breaking current (KA) 1 phase.
5. Rated short circuit making current (KA) 3 phase.
6. Rated short circuit making current (KA) 1 phase.
7. Provisions of auto re-closing with details.
iii. Lightning ArrestersTechnical dataiv. CommunicationsDetails of Communications equipment installed at points of connections.v. Basic Insulation Level (KV)1. Bus bar.
2. Switchgear.
3. Transformer Bushings
4. Transformer windings.
1. Rated terminal voltage (KV).
2. Rated MVA.
3. Rated MW
4. Speed (rpm) or number of poles.
5. Inertia constant H (MW sec./MVA).
6. Short circuit ratio.
7. Direct axis synchronous reactance Xd (% on MVA).
8. Direct axis (saturated) transient reactance (% on MVA) X'd.
9. Direct axis (saturated) sub-transient reactance (% on MVA) X"d.
10. Quadrature axis synchronous reactance (% on MVA) Xq.
11. Quadrature axis (saturated) transient reactance (% on MVA) X'q.
12. Quadrature axis (saturated) sub-transient reactance (% on MVA) X"q.
13. Direct axis transient open circuit time constant (sec) T'do.
14. Direct axis sub-transient open circuit time constant (sec) T"do.
15. Quadrature axis transient open circuit time content (sec) T'qo.
16. Quadrature axis transient open circuit time constant (sec) T"qo.
17. Stator Resistance (Ohm) Ra.
18. Stator leakage reactance (Ohm) X1.
19. Stator time constant (Sec).
20. Rated Field current (A).
21. Neutral grounding details.
22. Open Circuit saturation characteristics of the Generator for various terminal voltages giving the compounding current to achieve this.
23. Type of Turbine.
24. Operating Head (Metres)
25. Discharge with full gate opening (cumecs)
26. Speed Rise on total Load throw off(%).
27. MW and MVAr Capability curve
ii. Parameters of excitation control system:iii. Parameters of governor:iv. Operational parameter:1. Minimum notice required to Synchronise a Generating Unit from desynchronisation.
2. Minimum time between Synchronising different Generating Units in a Power Station.
3. Minimum block load requirements on Synchronising.
1. Topographical survey
2. Geological survey
3. Land
4. Environmental Clearance
5. Rehabilitation of displaced persons.
iii. Techno-economic approval by Central Electricity Authority.iv. Approval of State Government/Government of India.v. Financial Tie-up.1. Short Circuit studies
2. Stability Studies.
3. Load Flow Studies.
ii. Proposed Connection with the State Transmission System.1. Voltage
2. No. of circuits
3. Point of Connection.
1. Name of Sub-station.
2. Power Station connected.
3. Number and length of circuits.
4. Interconnecting transformers.
5. Sub-station bus layouts.
6. Power transformers.
7. Reactive compensation equipment.
ii. Sub-station layout diagrams showing:1. Bus bar layouts.
2. Electrical circuitry, lines, cables, transformers, switchgear etc.
3. Phasing arrangements.
4. Earthing arrangements.
5. Switching facilities and interlocking arrangements.
6. Operating voltages.
7. Numbering and nomenclature:
8. Transformers.
9. Circuits.
10. Circuit breakers.
11. Isolating switches.
1. Length of line (km).
2. Number of circuits.Per Circuit values.
3. Operating voltage (KV).
4. Positive Phase sequence reactance (pu on 100 MVA) X1
5. Positive Phase sequence resistance (pu on 100 MVA) R1
6. Positive Phase sequence susceptance (pu on 100 MVA) B1
7. Zero Phase sequence reactance (pu on 100 MVA) X0
8. Zero Phase sequence resistance (pu on 100 MVA) R0
9. Zero Phase sequence susceptance (pu on 100 MVA) B0
| Item | Due date/Time | |
| (a) | Estimated aggregate month-wise annual sales ofEnergy in Million Units and peak and lean demand in MW & MVArat each Connection point for the next financial year. | 15th November of current year |
| (b) | Estimated aggregate day-wise monthly sales ofEnergy in million Units and peak and lean demand in MW & MVArat each Connection point for the next month. | 25th of current month |
| (c) | 15 Minute block-wise demand estimates for theday ahead. | 9.00 Hours every day. |
| (2) Estimates of Load Shedding for DistributionLicensee | ||
| Item | Due date/Time | |
| (a) | Details of discrete load blocks that may beshed to comply with instructions issued by SLDC when required,from each connection point. | Soon after connection is made. |
| (3) Year ahead outageprogramme (For the financial year)(i) Generation outage programme for (SGS) | ||
| Item | Due date/Time | |
| (a) | Identification of Generating Unit. | 15th November each year |
| (b) | MW, Which will not be available as a result ofOutage. | |
| (c) | Preferred start date and start-time or rangesof start dates and start times and period of outage. | |
| (d) | If outages are required to meet statutoryrequirement, then the latest - date by which outage must betaken. | |
| (ii) Year ahead outage programme (Affecting Transmission System) | ||
| Item | Due date /Time | |
| (a) | MW, which will not be available as a result ofOutage from Imports through external connections. | 1st November each year |
| (b) | Start date and start time and period of Outage. | |
| (iii) Year ahead CPP's outage programme (Affecting TransmissionSystem) | ||
| Item | Due date/Time | |
| (a) | MW, which will not be available as a result ofOutage from Imports through external connections. | 30th November each year |
| (b) | Start date and start time and period of Outage. | |
| (iv) Year ahead Distribution Licensees outage programme(Affecting Transmission System) | ||
| Item | Due date/Time | |
| (a) | Loads in MW not available from any connectionpoint. Identification of connection point. | 15th November each year |
| (b) | Period of suspension of drawal with start dateand start time. | |
| (v) STU's Overall outage programme | ||
| Item | Due date/Time | |
| (a) | Report on proposed outage programme to ERPC | 15th February each year |
| (b) | Release of finally agreed outage plan | 15th February each year |
| Item | Due date/ Time | |
| (a) | Day ahead 15-minute block-wise MW/MVAravailability (00.00 - 24.00 Hours) of SGS. | 9.00 hrs |
| (b) | Day ahead 15-minute block-wise MW import/exportfrom CPP's. | 9.00 hrs |
| (c) | Status of Generating Unit Excitation AVR inservice (Yes/No). | 9.00 hrs |
| (d) | Status of Generating Unit Speed Control System.Governor in service (Yes/No). | 9.00 hrs |
| (e) | Spinning reserve capability (MW). | 9.00 hrs |
| (f) | Backing down capability with/without oilsupport (MW). | 9.00 hrs |
| (g) | Hydro reservoir levels and restrictions. | 9.00 hrs |
| (h) | Generating Units 15-minute block-wise summationoutputs (MW) | 9.00 hrs |
| (i) | Day ahead 15-minute block-wise MW entitlementsfrom Central Sector Generation Power Stations from ERLDC. | 10.00 hrs |
| Item | ||
| (a) | Generators and IPPs shall submit to STUup-to-date capability curves for all Generating Unit. | On receipt of request from STU/SLDC. |
| (b) | CPPs shall submit to STU net return capabilitythat shall be available for export /import from TransmissionSystem | On receipt of request from STU/SLDC. |
| Item | ||
| (a) | Primary Response in MW at different levels ofloads ranging from minimum generation to registered capacity forfrequency changes resulting in fully opening of governor valve. | On receipt of request from STU/SLDC. |
| (b) | Secondary response in MW to frequency changes | On receipt of request from STU /SLDC. |
| Item | |
| (a) SGS shall provide 15-minute block-wisegeneration summation to SLDC. | Real time basis |
| (b) CPPs shall provide 15-minute block-wiseexport / import MW to SLDC. | Real time basis |
| (c) Logged readings of Generators to SLDC. | As required |
| (d) Detailed report of generating unit trippingon monthly basis. | In the first week of the succeeding month |
| Item | Due date/Time | |
| (a) | Schedule of essential and non-essential loadson each discrete load block for purposes of load shedding. | As soon as possible after connection |
| Item of Plant / Apparatus | Plant Owner | Safety responsibility | Control responsibility | Operation responsibility | Maintenance responsibility | Remarks |
| ________KV Switch-yard | ||||||
| All equipment including bus bars | ||||||
| feeders | ||||||
| Generating units | ||||||
| S.No. | Item | Details |
| 1 | Date and time of incident | |
| 2 | Location of incident | |
| 3 | Type of incident | |
| 4 | System parameters before the incident (voltage, frequency, flows,generation etc.) | |
| 5 | Relay indications received and performance of protection | |
| 6 | Damage to equipment | |
| 7 | Supplies interrupted and duration, if applicable | |
| 8 | Amount of generation lost, if applicable | |
| 9 | Possibility of alternate supply arrangement | |
| 10 | Estimate of time to return to service | |
| 11 | Cause of incident | |
| 12 | Any other relevant information and remedial action taken | |
| 13 | Recommendations for future improvement / repeat incident | |
| 14 | Name of the organization |