NCT Delhi - Act
The Delhi Electricity Regulatory Commission (Terms and Conditions for Determination of Wheeling Tariff and Retail Supply Tariff) Regulations, 2011
DELHI
India
India
The Delhi Electricity Regulatory Commission (Terms and Conditions for Determination of Wheeling Tariff and Retail Supply Tariff) Regulations, 2011
Rule THE-DELHI-ELECTRICITY-REGULATORY-COMMISSION-TERMS-AND-CONDITIONS-FOR-DETERMINATION-OF-WHEELING-TARIFF-AND-RETAIL-SUPPLY-TARIFF-REGULATIONS-2011 of 2011
- Published on 19 January 2011
- Commenced on 19 January 2011
- [This is the version of this document from 19 January 2011.]
- [Note: The original publication document is not available and this content could not be verified.]
1. Short Title, Commencement And Extent.
- These Regulations shall be called the Delhi Electricity Regulatory Commission (Terms and Conditions for Determination of Wheeling Tariff and Retail Supply Tariff) Regulations, 2011.2. Definitions And Interpretation.
3. Scope Of Regulations And Extent Of Application.
4. General Approach And Guiding Principles.
5. Principles For Determination Of ARR.
-Arr For Wheeling Business| WACC= | [ | D/E | ] | * | rd + | [ | 1 | ] | * | re | ||||||||
| 1+D/E | 1+D/E |
6. Quality Of Supply And Services.
7. Multi Year Tariff Process.
8. Government Support For Social Causes.
9. Disposal Of Application.
10. Periodic Reviews.
11. Truing Up For The Previous Control Period.
12. Miscellaneous.
-Issue of Orders and Practice Directions| S. No | Asset Class | Useful Life (Years) | Rate (%) |
| (1) | (2) | (3) | (4) |
| 1. | Land owned under full title | Infinity | 0 |
| 2. | Land held under lease | ||
| (A) | For investment in land | The period of lease or the period remainingunexpired on the Assignment of the lease | 0 |
| (B) | For cost of clearing site | The period of lease remaining unexpired at thedate of clearing the site | 0 |
| 3. | Assets Purchased New | ||
| (A) | Plant and machinery in generating stations including plantfoundations | ||
| (i) | Hydro-electric | 35 | 2.57 |
| (ii) | Steam-electric NHRS & Waste Heat Recovery Boilers / Plants | 25 | 3.60 |
| (iii) | Diesel electric & gas plant | 15 | 6.00 |
| (B) | Cooling towers and circulating water systems | 25 | 3.60 |
| (C) | Hydraulic works forming part of hydro-electric systemincluding: | ||
| (i) | Dams, spillways weirs, canals, reinforced concrete flumes &siphons | 50 | 1.80 |
| (ii) | Reinforced concrete pipelines and surge tanks, steelpipelines, sluice gates, steel surge (tanks) hydraulic controlvalves and other hydraulic works | 35 | 2.57 |
| (D) | Building & civil engineering works of a permanentcharacter, not mentioned above: | ||
| (i) | Offices & showrooms | 50 | 1.80 |
| (ii) | Containing thermo-electric generating plant | 25 | 3.60 |
| (iii) | Containing hydro-electric generating plant | 35 | 2.57 |
| (iv) | Temporary erection such as wooden structures | 5 | 18.00 |
| (v) | Roads other than kutcha roads | 50 | 1.80 |
| (vi) | Others | 50 | 1.80 |
| (E) | Transformers, transformer (kiosk) sub-station equipment &other fixed apparatus (including plant foundations) | ||
| (i) | Transformers (including foundations) having a rating of 100kilo volt amperes and over | 25 | 3.60 |
| (ii) | Others | 25 | 3.60 |
| (F) | Switchgear, including cable connections | 25 | 3.60 |
| (G) | Lightning arrestors: | ||
| (i) | Station type | 25 | 3.60 |
| (ii) | Pole type | 15 | 6.00 |
| (iii) | Synchronous condenser | 35 | 2.57 |
| (H) | Batteries | 5 | 18.00 |
| (I) | Underground cable including joint boxes and disconnected boxes | 35 | 2.57 |
| (J) | Cable duct system | 50 | 1.80 |
| (K) | Overhead lines including supports: | ||
| (i) | Lines on fabricated steel operating at nominal voltages higherthan 66 kV | 35 | 2.57 |
| (ii) | Lines on steel supports operating at nominal voltages higherthan 13.2 kV but not exceeding 66 kV | 25 | 3.60 |
| (iii) | Lines on steel or reinforced concrete supports | 25 | 3.60 |
| (iv) | Lines on treated wood supports | 25 | 3.60 |
| (L) | Meters | 15 | 6.00 |
| (M) | Self propelled vehicles | 5 | 18.00 |
| (N) | Air conditioning plants: | ||
| (i) | Static | 15 | 6.00 |
| (ii) | Portable | 5 | 18.00 |
| (O) | |||
| (i) | Office furniture and fittings | 15 | 6.00 |
| (ii) | Office equipments | 15 | 6.00 |
| (iii) | Internal wirings including fittings and apparatus | 15 | 36.00 |
| (iv) | Street Light fittings | 15 | 36.00 |
| (P) | Apparatus let on hire: | ||
| (i) | Other than motors | 5 | 18.00 |
| (ii) | Motors | 15 | 6.00 |
| (Q) | Communication equipment | ||
| (i) | Radio and higher frequency carrier systems | 15 | 6.00 |
| (ii) | Telephone lines and telephones | 15 | 6.00 |
| (R) | Assets purchased in second hand and assets not otherwiseprovided for in the schedule | Such reasonable period as the Commissiondetermines in each case having regard to the nature, age andconditions of assets at the time of its acquisition by the owner |