State of Jammu-Kashmir - Act
Jammu and Kashmir State Electricity Regulatory Commission (Terms and Conditions for Determination of Multi Year Generation Tariff) Regulations, 2016
JAMMU & KASHMIR
India
India
Jammu and Kashmir State Electricity Regulatory Commission (Terms and Conditions for Determination of Multi Year Generation Tariff) Regulations, 2016
Rule JAMMU-AND-KASHMIR-STATE-ELECTRICITY-REGULATORY-COMMISSION-TERMS-AND-CONDITIONS-FOR-DETERMINATION-OF-MULTI-YEAR-GENERATION-TARIFF-REGULATIONS-2016 of 2016
- Published on 19 December 2016
- Commenced on 19 December 2016
- [This is the version of this document from 19 December 2016.]
- [Note: The original publication document is not available and this content could not be verified.]
1. Short title and commencement.
- 1.1 These Regulations may be called the Jammu and Kashmir State Electricity Regulatory Commission (Terms and Conditions for Determination of Multi Year Generation Tariff) Regulations, 2016.2. Scope and extent of application.
- 2.1. These Regulations shall apply in the following cases :-(a)Where tariff for a generating station or a unit thereof is required to be determined by the Commission under section 56 of the J&K Electricity Act, 2010 ;(b)Where tariff has been determined bilaterally between the State Government and the Utility prior to the allotment of the project to the Utility for construction, operation and maintenance and for which power purchase agreement has been approved by the Commission based upon such tariff, the Commission shall adopt such tariff together with the terms and conditions of such approved power purchase agreement ;(c)Where the Government of J&K notifies a policy to encourage investment in the State by allowing setting up of generating plants, out of which certain percentage of installed capacity as decided by the GoJK from time to time, can be procured by the Distribution Licensees of the State of J&K for which the tariff may be determined under Section 56 of the Electricity Act, 2010.(d)Where tariff may be determined by the Commission for hydroelectric projects which meet the following criteria :-(i)The Commission is satisfied that the project site has been allotted to the developer by the Government of J&K after following a transparent two stage process. The first stage should be for prequalification on the basis of criteria of financial strength, past experience of developing infrastructure projects of similar size, past track record of developing projects on time and within estimated costs, turnover and ability to meet performance guarantee etc. In the second stage, bids are to be called on the basis of quantifiable parameter, such as, additional free power in excess of percentage of free power, as notified by the State Government, equity participation offered to the Government of J&K, or any other parameter to be notified by the State Government from time to time.(ii)Concurrence of CEA (if required under Section 8 of the Act), financial closure, award of work and long term Power Purchase Agreement (PPA) (of the duration of 35 years or more) of the capacity specified in (iii) below with distribution licensees are completed by 15-08-2022.(iii)Long term PPA is firmed up for 60% or more of the total saleable design energy, balance being allowed for merchant sale :Provided that distribution licensees can extend the duration of long term PPA beyond 35 years for a further period of 15 years at the existing terms and conditions subject to the approval of Appropriate Commission :Provided further that nothing contained in this Regulation shall apply to Pumped Storage Plants (PSP).(iv)The time period for commissioning of all the units of the project shall ordinarily be fixed at four years from the date of approval of the commissioning schedule by the Commission. However, the Commission may, after recording reasons in writing, fix longer time period for hydroelectric projects (reservoir as well as run-of- river projects) of more than 100 MW capacity. Agreed timelines to achieve the fixed commissioning schedule along with penalty for delay shall be decided by the Commission. The Commission shall allow pass through the Interest During Construction (IDC) and Financing Cost (FC) only up to the period of delay not attributable to the developer. The approval of CEA, wherever required under Section 8 of the Act, shall be sought.(v)Award of contracts for supply of equipment and construction of the project, either through a turnkey or through well defined packages, are done on the basis of international competitive bidding.Notwithstanding anything contained in Regulation 2.1 (d) above, the developers of hydroelectric projects of more than 100 MW design capacity for which sites have been awarded earlier by following a transparent process and on the basis of pre-determined set of criteria would have the option of getting the tariff determined by the Commission for the power to be sold through long term PPA on the basis of cost plus under Section 56 of the Act.3. Definitions.
2. In case of purely run-of-river hydro generating station if the unit or the generating station is declared under commercial operation during lean inflows period when the water is not sufficient for such demonstration, it shall be mandatory for such hydro generating station or unit to demonstrate peaking capability equivalent to installed capacity as and when sufficient inflow is available.
| PLF| =10000 ∑ SGi/{NxICx(100-AUXn}%| x 100 = 88.436% |
4.
Words or expressions used in these regulations and not defined herein but defined in the Jammu and Kashmir Electricity Act, 2010 shall have the meaning assigned to them in the Act.5.
All proceedings under these regulations shall be governed by the Conduct of Business Regulations.6. Tariff determination for associated transmission network/ lines.
- 6.1 The tariff for the associated transmission network/lines of the generating stations shall be governed by the JKSERC (Terms and Conditions for Determination of Transmission Tariff) Regulations, 2012.7. Norms of operation to be threshold norms.
- 7.1 For removal of doubts, it is clarified that the norms of operation specified under these Regulations are the threshold norms and this shall not preclude the generating company and Beneficiaries from agreeing to improved norms of operation and in such case the improved norms shall be applicable for the determination of tariff :Provided if Power Purchase Agreement between generating company and the beneficiary stipulates better norms of operation, then such norms provided in the Power Purchase Agreement shall be considered for the determination of tariffPart-II Tariff Framework and Guiding Principles for Multi Year Tariff (MYT) Framework8. Tariff framework.
- 8.1 The Commission shall adopt Multi Year Tariff framework for approval of ARR and Tariff during the Control Period.9. Guiding Principles for MYT framework.
- 9.1 The Commission in specifying these Regulations shall be guided by the principles contained in Sections 55 and 56 of the Act to encourage competition, efficiency, economical use of resources, good performance and optimum investments.10. Principles for determination of tariff.
- Existing Generating Station :11. Thermal Power Generating Stations
- Components of tariff :| Pressure Rating (Kg/cm2) | 150 | 170 | 170 | 247 | 247 |
| SHT/RHT (0C) | 535/535 | 537/537 | 537/565 | 537/565 | 565/593 |
| Type of BFP | Electrical | Turbine | Turbine | Turbine | Turbine |
| Driven | Driven | Driven | Driven | Driven | |
| Max. Turbine CycleHeatrate (KCal/kWh) | 1955 | 1950 | 1935 | 1900 | 1850 |
| Min. Boiler Efficiency | |||||
| Sub-Bituminous Indian Coal | 0.85 | 0.85 | 0.85 | 0.85 | 0.85 |
| Bituminous Imported Coal | 0.89 | 0.89 | 0.89 | 0.89 | 0.89 |
| Max. Design Unit Heat rate (KCal/kWh) | |||||
| Sub-Bituminous Indian Coal | 2300 | 2294 | 2276 | 2235 | 2176 |
| Bituminous Imported Coal | 2197 | 2191 | 2174 | 2135 | 2079 |
| (i) Coal-based generating stations | ||
| 200 MW series | With Natural Draft cooling Toweror without cooling towers | 8.5% |
| 300/330/350/500 MW and above series-Steam Driven Boiler Feed Pumps | With Natural Draft cooling Toweror without cooling towers | 5.25% |
| 300/330/350/500 MW series-Electrically Driven Boiler Feed Pumps : | With Natural Draft cooling Toweror without cooling towers | 7.75% |
| Provided further that for thermal generating stations withinduced draft cooling towers, the norms shall be furtherincreased by 0.5%. | ||
| (ii) Gas-based and Naphtha-based generatingstations : | ||
| Combined cycle | 2.5% | |
| Open cycle | 1.0% |
| A=| 10(100-ACn)| *SFCn* (Pom- Pos) |
| B=| 10(100-ACn)| *[SFCn* {(Pcm/Kcm) - (Pcs/Kcs)}- |
| FPA| 10* SHRn* (Pm/Km)-(Ps/Ks)| |
12. Hydro power generating station.
- Components of tariff :Part IV – Procedure of Filling of ARR and Tariff
13. Multi year tariff filing procedure. - 13.1 The filing under MYT by the generating company shall be done as per the timelines specified in these Regulations and in compliance with the principles for determination of ARR as specified in these Regulations, in such form as may be prescribed by the Commission from time to time.
14. Disposal of application. - 14.1 The Commission shall process the filings made by the Generating Company in accordance with these Regulations and the Conduct of Business Regulations.
15. Annual performance review. - 15.1 To ensure smooth implementation of the Multi Year Tariff (MYT) framework, the Commission may undertake periodic reviews of generating company's performance during the Control Period, to address any practical issues, concerns or unexpected outcomes that may arise.
16. Truing up. - 16.1 The True-Up for the Control Period shall be as per Regulations 9.12 .
Part V – Miscellaneous
Foreign Exchange Rate Variation :17.
1. The generating company may hedge foreign exchange exposure in respect of the interest on foreign currency loan and repayment of foreign loan acquired for the generating station or the transmission or distribution system, in part or full in the discretion of the generating company or the licensee.
18. Summary of timelines. -
| S. No. | Description | Filing of theDocument by | Obtaining additionalinformation andacceptance bythe Commission | Approval of theDocument |
| 1 | 2 | 3 | 4 | 5 |
| 1. | Business Plan for the FirstControl Period | 1st August, 2017 | Within 15 days of filing ofdocument | Within 60 days ofacceptance of the filing |
| 2.. | Filing of MYT Petition for ExistingStations forthe Control PeriodFY 2018-2019 to FY 2020-21 | 30th November,2017 | Within 30 days offiling of document | Within 120 days ofacceptance of the filing |
| 3.. | Filing of MYT Petition for NewStations for theControl PeriodFY 2018-19 to FY 2020-21 | Within 180 days ofanticipated CoD | Within 30 days offiling of document | Within 120 days ofacceptance of the filing |
| 4. | Annual PerformanceReview/True-up | 30th November ofeach year of theControl Period | Within 30 days offiling of document | Within 120 days ofacceptance of the filing |
| Appendix-I : Depreciation Schedule | ||
| S. No. | Asset Particulars | Depreciation Rate(Salvage value=10%) |
| 1 | 2 | 3 |
| SLM | ||
| A | Land owned under full ownership | 0.00% |
| B | Land under lease : | |
| (a) | For investment in the land | 3.34% |
| (b) | For cost of clearing the site | 3.34% |
| (c) | Land for reservoir in case of hydro generatingstation | 3.34% |
| C | Assets Purchased New : | |
| (a) | PI and machinery in generating stations: | |
| (i) Hydroelectric | 5.28% | |
| (ii) Steamelectric NHRB and Waste Heat Recovery Boilers | 5.28% | |
| (iii) Diesel electric and gas plant | 5.28% | |
| (b) | Cooling towers and circulating water systems | 5.28% |
| (c) | Hydraulic works forming part of hydroelectricsystem including : | |
| (i) Dams, spillways weirs, canals, reinforced concrete flumesand siphons | 5.28% | |
| (ii) Reinforced concrete pipelines and surge tanks, steelpipelines, sluice gates, steel surge (tanks) hydraulic controlvalves and hydraulic works | 5.28% | |
| (d) | Building and civil engineering works of apermanent character, not mentioned above : | |
| (i) Offices and showrooms | 3.34% | |
| (ii) Containing thermoelectric generating plant | 3.34% | |
| (iii) Containing hydroelectric generating plant | 3.34% | |
| (iv) Temporary erection such as wooden structures | 100.00% | |
| (v) Roads other than kutcha roads | 3.34% | |
| (vi) Others | 3.34% | |
| (e) | Transformers, kiosk sub-station equipment andother fixed apparatus (including plant foundations) : | |
| (i) Transformers (including foundations) having a rating of 100kilo volt amperes and over | 5.28% | |
| (ii) Others | 5.28% | |
| (f) | Switchgear, including cable connections | 5.28% |
| (g) | Lightning arrestors : | |
| (i) Station type | 5.28% | |
| (ii) Pole type | 5.28% | |
| (iii) Synchronous condenser | 5.28% | |
| (h) | Batteries : | 5.28% |
| (i) Underground cable including joint boxes and disconnectedboxes | 5.28% | |
| (ii) Cable duct system | 5.28% | |
| (i) | Overhead lines including cable support : | |
| (i) Lines on fabricated steel operating at terminals voltageshigher than 66 kV | 5.28% | |
| (ii) Lines on steel supports operating at terminal voltageshigher than 13.2 kV but not exceeding 66 kV | 5.28% | |
| (iii) Lines on steel or reinforced concrete 5.28% | ||
| (iv) Lines on treated wood supports supports | 5.28% | |
| (j) | Meters | 5.28% |
| (k) | Self propelled vehicles 9.50% | |
| (l) | Air conditioning plants : | |
| (i) Static | 5.28% | |
| (ii) Portable | 9.50% | |
| (m) | (i) Office furniture and furnishings | 6.33% |
| (ii) Office equipment 6.33% | ||
| (iii) Internal wirings including fittings and apparatus | 6.33% | |
| (iv) Street Light fittings | 5.28% | |
| (n) | Apparatus let on hire : | |
| (i) Other than motors | 9.50% | |
| (ii) Motors | 6.33% | |
| (o) | Communication equipment : | |
| (i) Radio and higher frequency carrier systems | 6.33% | |
| (ii) Telephone lines and telephones | 6.33% | |
| (p) | IT Equipments | 15.00% |
| (q) | Fiber Optic | 6.33% |
| (r) | Any other assets not covered above | 5.28% |