| Service area |
Compensation payable to affected consumer |
Manner of payment |
| Normal Fuse-of |
| Urban Areas |
Rs. 100 in each case of default |
Automatic |
| Other Areas |
| Line Breakdowns |
| Urban Areas |
Rs. 100 to each affected consumer |
To be claimed |
| Other Areas |
| Distribution Transformer failure |
| Urban Areas |
Rs. 200 to each affected consumer |
To be claimed |
| Other Areas |
| Period of Scheduled outages |
| Maximum duration in a single stretch |
Rs. 200 to each affected consumer |
To be claimed |
| Restoration of supply |
| Voltage Variations |
| No expansion/ enhancement of network is involved |
Rs. 200 in each case of default |
Automatic |
| Up-gradation of distribution system is required |
Rs. 500 in each case of default |
| Harmonics |
| EHT connections |
To be decided by the Commission at appropriatetime
|
|
| HT connections |
| Meter Complaints |
| Inspect and check correctness |
Rs. 100 in each case of default |
To be Claimed |
| Replace slow, creeping or stuck up meters |
Rs. 100 in each case of default |
Automatic |
| Replace burnt meters if cause not attributable to consumer |
Rs. 200 in each case of default |
Automatic |
| Replace burnt meters in all other cases |
|
|
| Application for new connection/additional load |
| Connection feasible from existing network |
| Release of supply |
Rs. 100 for each day of default |
Automatic |
|
Network expansion/enhancement required for providingconnection
|
| Release of supply - Low Tension (including agriculture) |
Rs. 100 for each day of default |
To be Claimed |
| Release of Supply - High Tension 11KV supply |
Rs. 500 for each day of default |
To be Claimed |
| Release of Supply - High Tension 33KV supply |
Rs. 500 for each day of default |
Automatic |
| Release of supply - Extra High Tension services |
| Erection of Substation required for release of supply |
Rs. 1000 in each day of default |
Automatic |
| Transfer of ownership and conversion of service |
| Title transfer of ownership |
Rs. 100 for each day of default |
Automatic |
| Change of category |
Rs. 100 for each day of default |
Automatic |
| Conversion from LT 1-Ph to LT 3-ph |
| Conversion from LT to HT and vice-versa |
Rs. 200 in each day of default |
Automatic |
| Resolution of complaints on consumer’s bills |
| Resolution of complaint |
Rs. 50 for each day of default |
Automatic |
| Reconnection of supply following disconnection |
| Urban Areas |
Rs. 100 for each day of default |
Automatic |
| Other Areas |