State of Kerala - Act
Kerala Electricity Supply Code, 2005
KERALA
India
India
Kerala Electricity Supply Code, 2005
Rule KERALA-ELECTRICITY-SUPPLY-CODE-2005 of 2005
- Published on 2 March 2005
- Commenced on 2 March 2005
- [This is the version of this document from 2 March 2005.]
- [Note: The original publication document is not available and this content could not be verified.]
Chapter I
General
1. Short title and commencement.
2. Definitions.
3. Code Review Panel.
1. A Chairman, not below the rank of a Chief Engineer or equivalent level of the Board or its successor body engaged in distribution;
2. One member from SLDC;
3. One member representing each of other Distribution Licensees;
4. One member from Rural Electricity Cooperative Societies, if any;
5. One member representing each of Domestic, LT Industry and Agricultural Consumer Sectors;
6. One member representing HT/EHT consumer sector;
7. One member representing captive generation/non conventional energy sectors;
8. One member representing legal profession;
9. One member representing Officers / Engineers' Associations.
10. One member representing Electricity Workers' Unions;
11. An additional member representing the Board shall act as member secretary of the Review Panel and coordinate its activities till such time the State Transmission Utility is formed.
Chapter II
System Of Supply
4. Point of Supply.
| Supply Voltage | Maximum Connected Load | Maximum Contract Demand |
| 240 V | 5 kW | - |
| 415V | 100 KVA- | - |
| 11 KV | - | 3000 KVA |
| 22 KV/33 KV | - | 6000 KVA |
| 66 KV | - | 8000 KVA |
| 110 KV | - | 20000 KVA |
| 220 KV | - | >20000kVA |
Chapter III
Supply Of Energy
5. Application for supply.
| System of supply | Application fee (Rs.) |
| LT supply | Rs. 25 |
| HT supply | Rs. 1000 |
| EHT supply | Rs. 5000 |
6. Duty of the Licensee to supply electricity.
7. Power to recover expenditure.
8. Time frame for providing supply.
| Sl.No. | Type of work | Unit | Time frame |
| 1 | LT Line | Per kM | 30 days |
| 2 | 11 KV line | Per kM | 4 months |
| 3 | 66 KV / 110 | Upto first 5 kM Next 5 km each | 1 year 3 months |
| 4 | 220 KV line | Upto first 5 kM Next 5 kM each | 2 years 6 months |
| Type of work | Time frame | |
| 1 | 11/0.4 KV Substation alone | 2 months |
| 2 | 33/11 KV Substation alone | 9 months |
| 3 | 66/11 KV Substation alone | 12 months |
| 4 | Extension of bay at 66 KV Substation | 6 months |
| 5 | 110/66 KV Substation | 12 months |
| 6 | Extension of bay at 110 KV Substation | 6 months |
| 7 | 220 KV Substation | 12 months |
| 8 | Extension of bay at 220 KV Substation | 6 months |