State of Odisha - Act
The Orissa State Electricity Board (General Conditions of Supply) Regulations, 1995
ODISHA
India
India
The Orissa State Electricity Board (General Conditions of Supply) Regulations, 1995
Rule THE-ORISSA-STATE-ELECTRICITY-BOARD-GENERAL-CONDITIONS-OF-SUPPLY-REGULATIONS-1995 of 1995
- Published on 1 January 1995
- Commenced on 1 January 1995
- [This is the version of this document from 1 January 1995.]
- [Note: The original publication document is not available and this content could not be verified.]
1. Short title.
- These Regulations shall be called The Orissa State Electricity Board (General Conditions of Supply) Regulations, 1995.2. Commencement.
- These Regulations shall come into force from the date notified for the purpose in the Orissa Gazette in which they are published.3. Definitions.
| Load Factor =| Actual units consumed during a given periodContract Demand or Maximum Demand X Number of Hrs. in the period| X 100; |
4. Application for supply.
5. Supply subject to availability.
- The supply of power required, shall be subject to its availability in the system, technical feasibility of supply, the scheme of supply being remunerative as per the norms fixed by the Board from time to time, the consumer bearing the proportionate charges as required by the Board in case of non-remunerative schemes and the consumer executing agreement in the standard agreement form prescribed by the Board accepting the terms relating to tariff and other conditions of supply of the Board.No additional power shall be supplied by the Board unless all arrear charges for the existing power supply have either been paid in full or the consumer has obtained instalments facility from the Board for unconditionally paying the arrears within the stipulated time.6. Agreement.
7. Security.
8. Service-Line.
9. Point of supply.
- Unless otherwise agreed to, the supply shall be at a single point at the out-going terminals of the Board, i.e.,-10. Wiring on consumer's premises.
- The wiring on the consumer's premises including additions and alterations, if any, should conform to the Indian Electricity Rules, 1956 and be carried out by a licensed Electrical Contractor. As soon as the consumer's installation or modifications thereof, as the case may be, is completed in all respects, the consumer shall submit to the Engineer, the wiring contractor's completion report and test report in the forms prescribed for approval.11. Consumer's apparatus.
12. Installation of equipments and apparatus.
- In case power is required by any prospective consumer, OSES may ask the prospective consumer to provide accommodation to instal Board's equipments and apparatus which may be considered necessary by the Engineer for effecting power supply to the intending consumer. After permission or authority for fixing the equipments and apparatus is given, the consumer shall continue to allow aforesaid installation to continue on his premises, with full control vested in the Board. The installation shall remain in the premises for a reasonable period even after the termination of the agreement to enable the Engineer to ensure the supply of power to other consumers having the benefit from the said installations, without payment of any compensation to the owner of the premises.13. Inspection and testing.
14. Approval of consumer's installations.
15. Commencement of supply.
- After the applicant has executed the agreement and deposited the preliminary installation cost, security and other dues and installed his own installations as provided in these Regulations and the application is finally approved by the Engineer, the said Engineer shall within a reasonable time make arrangements for supply of power to the applicant and after the arrangements are completed at his end and he is in a position to make such supply, the Engineer shall intimate the applicant that power may be availed by him within ninety days from the date of receipt of intimation. If the applicant fails to avail of the power within the period of ninety days, he would be liable to pay the demand charges and minimum energy charges irrespective of not availing the power. The meter when supplied by the Board, shall be fixed only at the time of taking power supply :Provided further that the Chairman may in special circumstances extend the time beyond the period of ninety days, for availing power supply.Chapter-III16. Board's supply mains and apparatus.
17. Meters.
| 730 x rating of the transformer in KVA100| = Transformer loss in units per month. |