State of Rajasthan - Act
Rajasthan Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 2016
RAJASTHAN
India
India
Rajasthan Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 2016
Rule RAJASTHAN-ELECTRICITY-REGULATORY-COMMISSION-TERMS-AND-CONDITIONS-FOR-OPEN-ACCESS-REGULATIONS-2016 of 2016
- Published on 27 January 2016
- Commenced on 27 January 2016
- [This is the version of this document from 27 January 2016.]
- [Note: The original publication document is not available and this content could not be verified.]
1. Short Title and Commencement.
2. Definitions.
- In these Regulations, unless the context otherwise requires -3. Extent of Application.
- These Regulations shall apply to open access for use of intra-State transmission system and / or the distribution systems of licensees in the State, including when such system is used in conjunction with inter-State transmission system.4. Eligibility for Open Access and Conditions to be satisfied.
5. Special Provisions for existing Distribution Licensees.
- The Distribution Licensees, using intra-State transmission system and the distribution system in the State under an existing agreement or arrangement on the date of coming into force of the RERC (Terms and Conditions for Open Access) Regulations, 2004, shall be entitled to continue to avail open access to such transmission and distribution system on the same terms and conditions for the term of the existing agreement or arrangement on payment of transmission charges and wheeling charges as may be determined by the Commission.6. Provisions for existing consumers and generating companies.
- The existing consumer or an existing generating company other than the licensees availing open access under government policy or under agreements entered on the date of coming into force of RERC (Terms and Conditions for Open Access) Regulations, 2004 may continue to avail open access on terms and conditions laid down under these Regulations to the extent they are not covered by any policy directive by the State Government to the Commission.7. Categorisation of Intra-State Open Access Customers.
- Subject to the provisions of regulations 5 and 6, the open access customers shall be classified into the following categories:8. Allotment Priority.
- The priority for allowing open access to persons other than those covered by regulations 5 and 6 shall be decided on the following criteria:9. Detailed Procedure and Criteria for allowing Open Access.
10. Procedure for Long Term Open Access.
11. Procedure for Medium Term Open Access.
12. Procedure for Short Term Open Access.
- (1) Open Access in advance:(i)An application for seeking intra-State short term open access in advance, may be submitted to the Nodal Agency for a period upto fourth month, considering the month in which the application is made being the first month;Provided that separate application shall be made for each month and each transaction.(ii)The application shall be submitted in the format prescribed in the detailed procedure;(iii)The application shall contain details such as capacity required, generation planned or power purchase contracted, point of injection, point of drawal, duration of availing open access, details of other open access approved/applied if any during the period for which open access is applied alongwith requisite undertaking and such other additional information as may be required by the Nodal Agency. The application shall be accompanied by a certificate from STU/Distribution Licensee, as the case may be, to the effect that ABT compliant meters are installed as per relevant Regulations along with non-refundable application fee amounting to Rs 5000/- (Rs. Five Thousand Only) through demand draft;Provided that if the open access is sought for the first time or quantum of open access is changed from the previously approved quantum, the application shall also be accompanied by a No Objection Certificate from the concerned Distribution Licensee(s) in the proforma prescribed in the detailed procedure.(iv)An application for grant of short term open access commencing in any month including the request for extension of existing open access accompanied with application fee as above may be submitted in a cover marked "Application for Short Term Open Access in advance for the month(--)" up to 15th day of the preceding month to SLDC.For example, application for grant of open access commencing in the month of July shall be submitted up to 15th day of June;(v)Nodal Agency shall acknowledge receipt of the application by indicating time and date on "Acknowledgement" to the applicant;(vi)A customer intending to avail intra-State short term open access shall furnish a copy of the application to the Transmission and Distribution Licensee of his area of supply;(vii)The Nodal Agency shall take a decision on the applications for intra-State short term open access in the manner provided below;(a)All applications received up to 15th day of the month shall be taken up for consideration together and processed as per allotment priority criteria specified in these Regulations;(b)The Nodal Agency, before granting intra-State open access, shall take into consideration the resultant congestion of any element, line or transformer of the transmission and distribution system involved in the proposed short term transaction;Provided that no system augmentation shall be done in order to allow short term open access to a customer. However, the customer may at his own cost augment the distribution/ transmission system in order to avail open access.(c)The Nodal Agency shall, after satisfying itself that the application is complete in all respects, convey grant of open access in prescribed format along with schedule of payments to the applicant latest by 22nd day of the month in which applications were received or otherwise the Nodal Agency shall record the reasons in writing in case open access is denied to any applicant.13. Open Access Agreement/Undertaking.
14. Non-Utilisation of Open Access Capacity.
- In case an open access customer is unable to utilize full or part of the capacity allotted to him, he shall inform the State Transmission Utility and State Load Despatch Centre and may surrender the capacity allotted to him by serving a notice as detailed below:15. Charges for Open Access.
16. Cross Subsidy Surcharge.
17. Additional Surcharge.
18. Metering.
19. Communication Facility.
20. State Load Despatch Centre (SLDC) fee and charges.
- SLDC fee and charges including scheduling and operating charges shall be payable as specified in the Rajasthan Electricity Regulatory Commission (Levy of fee and charges by SLDC) Regulations, 2004 as amended from time to time.21. Unscheduled Interchange Pricing.
- The payment settlement for mismatch between the schedule and the actual drawal/ injection in both intra-State and inter-State transactions by customers connected to transmission/ distribution network of the State licensees shall be governed by the pricing mechanism as specified below:22. Reactive Energy Charges.
23. Energy Losses.
24. Payment Security and Other Commercial Conditions.
- (1) For Long Term & Medium Term Open Access Customer(a)As a payment security towards transmission charges, open access customer shall deposit an amount equal to 3 months of the transmission charges for allotted open access capacity with the State Transmission Utility;(b)As a payment security towards SLDC charges, open access customer shall deposit an amount equal to 3 months of the SLDC fee and charges including scheduling and operating charges for allotted open access capacity with the State Load Dispatch Centre;(c)As a payment security towards wheeling charges, cross subsidy surcharge and additional surcharge, a deposit equal to 3 months of billing for these charges for allotted open access capacity shall be maintained with the Distribution Licensee of the area of supply;Provided that unity power factor shall be considered for the purpose of unit conversion from MVA/kVA to MW/kW or vice versa.Provided further that, in case of an existing open access customer availing open access for more than a financial year, security shall be revised on the basis of average monthly open access charges of the previous financial year.Provided further that, the IPPs/ CPPs selling power outside the State, shall also deposit a security towards under injection, if any, with the Distribution Licensee, equivalent to 10% of the proposed monthly contracted generation for sale, at the energy charge rate of HT Industrial tariff, the amount of which shall be recalculated after the actual sale of the previous quarter of the financial year.(d)Such security may be in the form of cash deposit/ demand draft.25. Adjustment of Energy.
26. Compliance and Grid Discipline.
27. Collection and Disbursement of Charges.
28. Curtailment Priority.
29. Information System.
- The State Load Despatch Centre shall post following information on its website in a separate web page titled "Open Access Information" and also issue monthly and annual reports containing such information periodically.30. Redressal Mechanism.
31. Powers to Remove Difficulties.
- If any difficulty arises in giving effect to or implementation of any of the provisions of these Regulations, the Commission may by general or special order, direct the State Transmission Utility, State Load Dispatch Centre, Licensees and the Open Access Customers to take such action as may be deemed appropriate by the Commission for removal of the difficulties.32. Repeal and Savings.
| ABT | Availability Based Tariff |
| CEA | Central Electricity Authority |
| CERC | Central Electricity Regulatory Commission |
| CPP | Captive Power Plant |
| Discom | Distribution Company |
| DD | Demand Draft |
| EHV | Extra High Voltage |
| GSS | Grid Sub Station |
| HT | High Tension |
| IEGC | Indian Electricity Grid Code |
| IEX | Indian Energy Exchange |
| IPP | Independent Power Producer |
| KV | Kilo Volt |
| kWh | Kilo Watt Hour |
| LTOA | Long Term Open Access |
| MTOA | Medium Term Open Access |
| MVA | Mega Volt Ampere |
| MW | Mega Watt |
| OA | Open Access |
| PXIL | Power Exchange of India Limited |
| RDPPC | Rajasthan Discoms Power Procurement Centre |
| RERC | Rajasthan Electricity Regulatory Commission |
| REGC | Rajasthan Electricity Grid Code |
| Rs. | Indian Rupees |
| RVPN | Rajasthan Vidyut Prasaran Nigam Limited |
| SEM | Special Energy Meter |
| SLDC | State Load Despatch Centre |
| STU | State Transmission Utility |
| STOA | Short Term Open Access |
| SPC | State Power Committee |
| UI | Unscheduled Interchange |