State of West Bengal - Act
West Bengal Electrical Licensing Rules, 2017
WEST BENGAL
India
India
West Bengal Electrical Licensing Rules, 2017
Rule WEST-BENGAL-ELECTRICAL-LICENSING-RULES-2017 of 2017
- Published on 1 November 2017
- Commenced on 1 November 2017
- [This is the version of this document from 1 November 2017.]
- [Note: The original publication document is not available and this content could not be verified.]
Part I – Preliminary
1. Title, extent and commencement.
2. Definitions.
Part II – Constitution of Board and its meeting
3. Constitution of the Board.
| (a) Officer nominated by the Additional ChiefSecretary Secretary/Principal Secretary to the Government of WestBengal (ex officio), Department of Power & NES, not below therank of Joint Secretary. | President |
| (b) Chief Electrical Inspector to the Governmentof West Bengal. | Member |
| (c) A Deputy Chief Electrical Inspector/JointChief Electrical Inspector to the Government of West ex-officioBengal to be appointed by the State Government. | Member Secretary & Convener |
| (d) Director of Mines Safety (Electrical), DGMS,Eastern zone, Dhanbad, Government of India or his representativewho shall be a graduate in Electrical Engineering. | Member |
| (e) A representative of the Faculty ofElectrical Engineering of Jadavpur University/Indian Instituteof Engineering, Science & Technology (Shibpur)/JalpaiguriGovernment Engineering College, College. | Member |
| (f) A representative from Department ofTechnical Education, Government of West Bengal, not below therank of Deputy Secretary. | Member |
| (g) A representative of West Bengal StateElectricity Distribution Company Limited. | Member |
| (h) A representative of West Bengal StateElectricity Transmission Company Limited. | Member |
| (i) A representative of Calcutta Electric SupplyCompany Ltd. | Member |
4. Term of office.
- The term of office of members other than ex officio members of the Board, shall be for a period of three years.5. Filling up of casual vacancies.
6. Functions of the Board.
- The functions of the Board shall be as follows, namely:-7. Meetings of the Board.
8. Quorum.
- The President and or the Secretary together with 1Ard members shall form a quorum at any meeting of the Board.9. Chairman of the meeting.
- The President or, in his absence, such one of the members present and elected at the meeting, shall be the Chairman of the meeting.10. Duties of the President.
11. Duties of the Member Secretary.
Part III – Examination conducted by Board
12. Examinations, qualification of examiners for Workmen's Permit (W.P) or Certificate of Competency of Supervisors (S.C.C). or National Certificate of Supervisors (N.C.S.) examination and honorarium or remuneration of examiners.
13. Application for admission to the examination.
Part IV – Permits to Electrical Workmen
14. Examination for permits to electrical workmen.
- The examination for permits to Electrical Workmen is intended for operative electrical workmen as distinct from Supervising Electrical Workmen.15. Qualifications.
16. Syllabus for examination for permits to electrical workmen.
17. Grant of Permits to Electrical Workman.
18. Production of Workmen's Permits (W.P.) for inspection and verification.
- The Secretary may require production of permits for inspection and verification and in case of mutilation and/or defacement of or un-authorised entry therein, the same may be placed before the Board with a report for action as the Board may deem fit.19. Renewal.
- Certificates of Workman Permit (W.P.) shall be renewed after every ten years. The fee for renewal shall be such as mentioned in Annexure IV and shall not be refunded in any case:Provided that when the application for renewal together with the certificate and the prescribed fee is not received before the date of expiry of the certificate, a penalty as mentioned in Annexure IV shall be charged for renewal. Renewal of certificates shall be done online once notified by the Board.20. Grant of duplicate Certificate or Permit.
Part V – Certificate of Competency of Supervisors
21. Certificate of Competency of Supervisors.
- The examination for certificates of competency of supervisors is intended for electrical workman who will directly supervise installation work.22. Qualifications for Certificate of Competency of Supervisors.
23. Examination for Certificate of Competency of Supervisors.
| Certificate for | Parts Compulsory |
| (See Annexure II) | |
| Wiring for systems not-exceeding 650 volts. | 1 & 2 |
| Direct Current (D.C.) Apparatus upto 650 volts | 1, 2 & 3 |
| Alternating Current (A.C.) Apparatus upto 650volts. | 1.2 & 4 |
| Installations exceeding 650 volts | 1,2,3,4,5,6A, 6B, |
| Overhead Lines exceeding 250 volts | 7A & 7B |
| For (A) Voltages upto 650 volts | 1 & 6A |
| For (B) Voltages upto 33,000 volts | 1, 6A & 6B |
| For (C) Voltages exceeding 33,000 voltsUnderground cables. | 1, 6A, 6B & 6C |
| For (A) Voltages upto 1100 volts | 1 & 7 A |
| For (B) Voltages upto 33,000 volts | 1, 7A & 7B |
| For (C) Voltages exceeding 33,000 volts | 1, 7A, 7B & 7C |
| Mining installation | 1, 2, 4, 6A, 7A & 8 |
| Electric Lifts & Escalators | 1, 2, 3, 4 & 9 |
| Electric signs, Electronic devices &Conservation of Electrical Energy | 1,2, 3, 4 & 10 |
| Wiring for systems not-exceeding 250 volts | 1 & 11 only |
| Installation of Transformer exceeding 650 voltsbut rating upto 125 KVA | 1,2, 6A, 6B, 7A, 7B & 12 only. |
24. Syllabus for examination for Certificate of Competency of Supervisors.
25. Grant of Certificates of Competency to Supervisors.
26. Production of Supervisor's Certificates of Competency for inspection and verification.
- The Secretary may require production of certificates for inspection and verification in case of mutilation and defacement of or unauthorized entry therein and in such case the same may be placed before the Board with a report for action as may be deemed fit.27. Renewal of Certificate of Competency of Supervisors.
- Certificates of Competency shall be renewed in every ten years and where the same is not revalidated at all even within six months from the date of its expiry, the said license shall be treated as cancelled. The licence shall be deemed to be in suspension from the date of expiry till revalidation and the same will be treated as invalid on expiry. The fees for renewal shall be such as mentioned in Annexure IV and shall not be refunded on any account:Provided that where the application for renewal together with the certificate and the prescribed fees has not been received before the date of expiry of such Certificate, a penalty as mentioned in Annexure IV shall be charged for renewal/revalidation.28. Grant of duplicate for Certificate of Competency of Supervisors.
- On being satisfied that an original certificate or permit granted under the regulations has been lost or destroyed; the Secretary may on application grant a duplicate. The charge for such duplicate shall be as in Annexure-IV. and shall not be refunded on any account.Part VI – National Certificate of Supervisors
29. Application for admission to or exemption from examination for National Certificate of Supervisors (N.C.S.).
30. Qualifications for National Certificate of Supervisors.
31. Examination for National Certificate of Supervisors.
32. Exemptions.
33. Grant of National Certificate of Supervisors.
34. Renewal.
- National Certificate of Supervisor shall be renewed after every ten years. The fee for renewal shall be such as mentioned in Annexure IV and shall not be refunded on any case and when the application for renewal together with the certificate and the prescribed fee is not received before the date of expiry of the certificate, a penalty as mentioned in Annexure IV shall be charged for renewal.35. Grant of duplicate National Certificate of Supervisor.
- Where an original certificate has been lost or destroyed, the Secretary may, on application, grant a duplicate certificate. The charge for such duplicate shall be such as mentioned in Annexure IV and shall not be refunded on any case.Part VII – Licence to Electrical Contractors
36. Grant and issue of licence to Electrical Contractors.
37. Production of Electrical Contractor's Licenses for inspection and verification.
- The Secretary may require production of certificates for inspection and verification in case of mutilation and defacement of or unauthorized entry therein and in such case the same may be placed before the Board with a report for action as may be deemed fit.38. Application for Contractor's License.
39. Form of Contractor's License.
40. Register of Contractors.
41. Renewal of Contractor's License.
42. Grant of duplicate Contractor's License.
- A duplicate Licence of an Electrical Contractor granted under this rule shall be issued only upon payment of fees as mentioned in Annexure IV on certification of the loss of the original license by the applicant to the satisfaction of the Secretary of the Board.Part VIII – Miscellaneous
43. On-line Services of West Bengal Electrical Licencing Board.
- All Applications related to any Service(s) of the West Bengal Electrical Licencing Board are to be submitted through on-line system, once it is notified by the Govt, of West Bengal.44. Procedure for authorization of Chartered Electrical Safety Engineers (CESE).
- Procedure for authorization of Chartered Electrical Safety Engineers will be detailed in the subsequent Rules soon after the Guidelines along with the eligibility conditions for authorizing the Chartered Electrical Safety Engineer is framed and issued by the Central Electricity Authority (CEA), Government of India.45. Report of negligence.
46. Malpractice or infringement of Rules to be reported.
- If any person holding an electrical workman's permit or a supervisor's certificate of competency or National Certificate of Supervisor or Certificate of Authorization of Chartered Electrical Safety Engineer or an electrical contractor's license is found by the Board to be guilty of negligence, misrepresentation or deliberate suppression of facts, incompetence or a breach of these rules or of the conditions of his license, the Board may suspend or cancel such permit, certificate, authorization or license. The decision of the Board shall be final.47. Unauthorized entries, mutilations or defacements of Workmen's permits. Supervisor's certificates of Competency and Electrical Contractor's Licenses.
- Any mutilation or defacement of any unauthorized entry in, any workman's pemrit or Supervisor's Certificate of competency or National Certificate of Supervisors or Certificate of Authorization of Chartered Electrical Safety Engineer electrical Contractor's license shall make the permit, certificate, authorization or license as the case may be, liable to cancellation by the Board. The decision of the Board in this regard shall be final.48. Electric License to obtain contractor's license.
- No electrical installation work shall be carried out by a person licensed under Part II of the Electricity Act, 2003 on a consumer's premises beyond the point of commencement of supply unless he has obtained an electrical contractor's license and employs a staff of supervisors and electrical workmen in compliance with these rules.49. Release of Contractor or Supervisor or Workman.
- A Contractor or Supervisor or Workman's Permit holder may disengage himself or herself from any company on the fulfillment of the following steps:-50. Appeal.
51. Savings.
- Notwithstanding the supersession of the regulations made by the Government of West Bengal under Commerce and Industries Department notification No. 3560 MP/IR-4/56 dated the 25th October,1956 and notification No. 2588 MP, dated the 29th July, 1959,-(a)all licences or permits granted under the repealed regulations shall be deemed to be valid till the date of Expiry, the renewal of which is subject to fulfilling of the conditions of licenses under these rules;(b)all the candidates declared to have been passed the examination conducted by the Board under the repealed regulations shall be deemed to have passed the examination under these rule.Annexure-ISyllabus For Workman Permit (W.P)(See rule 16)Candidates for examination for permits to electrical workmen shall comply with Rule 13 and be examined practically in installation work and by an oral & practical test covering any or all of the following subject and the permits of successful candidates will contain a reference to one or more of the classes of wiring referred to in clause (a) to (g) below:-(a)Ascertaining the sizes of wires of solid and stranded conductors.(b)Use of test lamps.(c)Use of bell and battery for sorting out circuits.(d)Methods of testing polarity and phasing out circuits.(e)Connections and diagrams for distribution boards, ceiling roses, plugs and sockets, lamp holders, Alternating (A.C) and Direct Current (D.C) fans with regulators, and switches (including two-way).(f)Wiring of fittings and other domestic consuming devices.(g)Installation work of the classes and with the kinds of cables and wires set out below :-| Part/Class | Description |
| For Voltages not exceeding 650 volts:- | |
| (i) | Wiring of buildings (for lights, fans and small motors) |
| (a) Cleat, Wood/Polyvinyl Chloride (P. V.C) casing and cappingsystems, employing wires and cables | |
| (b) Metal sheathed, tough rubber, Polyvinyl Chloride (P.V.C)and conduit systems, (also any other system as permitted underthe Electricity Act 2003 and Central Electricity Authority(Measures relating to Safety and Electric supply) Regulatons,2010 as amended up to date using wires and cables other thanpaper insulated cables. | |
| (ii) | Motor wirings (including generator), in conduit or leadsheathed, with wires and cables, other than armoured cables. |
| (iii) | Motor wirings with cables (laying and jointing). |
| (iv) | Overhead line work with cable connections. |
| (v) | Cable connections (laying and jointing) |
| For "High Pressure" Voltages exceeding 650 volts | |
| (vi) | Overhead lines only. |
| (vii) | Overhead lines with cable connections. |
| (viii) | Cable laying and jointing. |
Part 1 – is compulsory for Part-2 (i.e. For appearing in Part-2 it is compulsory to pass Part-1 or to appear at both Part-1 & 2 at a time).
Part-3 Direct Current (D.C) Apparatus Upto 650 Volts| Generators upto 650 volts | : | Series, Shunt, Compound wound types. Elementarytheory, installation, operation and maintenance. Paralleloperation and balancing of loads. |
| Motors upto 650 volts | : | Series, Shunt, Compound wound types. Elementarytheory, installation, operation and maintenance. Various methodsof speed control. |
| Cells and Batteries | : | Lead acid cell/battery (container, plates,separators, cover, electrolyte) Chemical reaction; Ratings;charging of batteries; Float, Boost & Trickle charging;Checking of charged battery; Sulphation; Internal shortcircuiting; Installation and maintenance of Battery & Batterycharger. |
| Generator, Motor | : | Types of Enclosures, Earthing. |
| Generators upto 650 volts | : | Alternating (AC) single and three phase,Elementary theory; Installation, Operation and Maintenance.Parallel running; Control Panels and Sychronising Panels. |
| Motors upto 650 volts | : | Akemating (A.C) single and three phase,Induction & Synchronous Machines, Elementary theory.Installation, operation and maintenance. Various methods of speedcontrol and application of variable speed drive. |
| Generators & Motors above | : | Elementary theory, Installation, operation &maintenance. 650 volts including H .V. Protective devices. |
| Transformers above | : | Types, Methods of cooling, Vector Groups,Parallel operation,650 volts (including High Voltage Installation(indoor & outdoor). Substation layout; Selection of HighVoltage & Extra High Voltage) Cables; Neutral Earthing. Codeof practice for selection, installation, maintenance &protection of Transformers. |
| Circuit Breakers above 650 Volts | : | Types, operation, Marking & Breaking |
| (Including High Voltage & Extra High Voltage | current, Selection, Maintenance, Various typesof Control gears. | |
| Other High Voltage/Extra High Voltage equipments | : | Installation & maintenance in Plants andSwitch yards |
| Power factor improvement | : | Capacitor bank, reactors; Installation,maintenance & protection of such equipment. |
| Testing/Voltage | : | of High Voltage/Extra High Voltage equipmentsprior to commissioning; Current transformers; Potentialtransformers; various types of protective relays. |
| Electronic Components | : | Resistor, Capacitor, Inductor; Colour Codes. |
| Semi-conductor devices | : | Diode, Transistor, Thyrislors/Silicon ControlledRectifier (SCR); Behaviour of diode, p-n- p & n-p-ntransistors, SCR; Diac. Triac, Testing & applications. |
| Assembly and Testing of Electronic Apparatus | : | Electronic ballasts, Electric fan regulatory,Full wave bridge rectifies and Filter circuits. Poly phaseAlternating Current (A.C.) to Direct Current (D.C.) bridgerectifier, inverter. Voltage stabilizer. |
| U. P. S. | : | Components and Applications. |
| Computer | : | Installation & special earthing requirement. |
| Transformer | : | General Principle, elementary calculations, nameplate details as per Indian Standard (I.S) Codes of practice,winding connections, parallel operations, off-load tap changing,installation & maintenance of outdoor & indoor typetransformer including load break switch fuse unit, isolator andlightning arresters, safety precautions, equipment & neutralEarthing. |
Part I – (Paper-1) Electricity. - Theory (Elementary knowledge).
Principles of Electricity. - Electric pressure, current and resistance, Ohm's Law, Specific resistance, Laws of resistance and their application for calculating voltage drop. Series and parallel circuits, Practical units of voltage, current, resistance, power and energy. Relation between electrical power unit Kilo Watt (K W) and mechanical power unit Horse Power (H. P.).Electromagnetism. - Production of Electromotive Force (E.M.F) and Fleming's hand rule. Magnetic, chemical and heating effects of electric current, Magnetic properties of material, Electromagnets and their applications.Material. - Conductors, non-conductors and insulators, Insulating materials and their relative merits, Transformer oil, Effect of heat and moisture on insulation, Lubricants and their uses.Different types of wires, cables, switches, circuit-breakers, cut-outs, etc., and their safe-current carrying capacity. Use of tables and data sheets generally given in electrical hand books.Generation of Electricity. - Natural sources of energy. Types of prime movers, Methods of producing Electro Motive Force, alternating current and direct current.Alternating Current (A. C) Generators (Alternators). - Essential components and constructional features. Methods of voltage and frequency control. Conditions and methods for synchronizing, Simple associated snitch board and its accessories.Direct Current (D.C.) Generators. - Essential components and constructional features. Shunt, series and compound dynamos and their characteristics. Causes of sparking.Interpoles. - Commutators and their maintenance. Carbon brushes - their adjustment and care. Methods of voltage regulation. Conditions for parallel operation, simple associated switch board and its accessories.Batteries. - Primary cells, Dry cells, Storage or secondary batteries or accumulators and their installation, Lead acid cells, Nickel iron or alkaline cells, Initial and subsequent charging of batteries. Charging circuits and their calculations: Series and parallel circuits, Maintenance of batteries, Use of hydro-meters.Alternating Current (A.C.) Motors. - Theory of Induction, (squirrel cage and slip ring type) synchronous and commutated motors, their uses, installation method of starting and speed control and reversal of direction.Direct Current (D.C.) Motor. - Theory of series, shunt and compound would type motors, their uses, installation, method of starting and speed control and reversal of direction.Alternating Current (AC) circuits. - Knowledge of vectors. Phase and phase difference, resistance. Inductance and Capacitance in an A.C. circuit Periodicity or frequency, Power and Power factor, Single phase and three phase system, Star and delta connections. Phase sequence.Controlling and Regulating Gear. - Knowledge of various types of switches and circuit breakers and cut-outs, starters, regulators, protective devices for both A.C. and D.C. motors and their wiring with the motors.Transformation. - Knowledge of single phase and three phase transformers, their construction, maintenance, Phasing out, Parallel working, Auto-transformer. Transformer-tappings, Temperature rise, Instrument transformer.Transmission & Distribution-Part II – (Paper-II) Electricity-Utilization
Domestic Installations-Wiring. - Wiring layouts of different types such as cleat, metal sheathed, wood casing and capping. Cab Type Sheathed, conduit and armoured cable for lighting and power installations in residential premises together with the necessary switch gear, Estimates of materials and cost of different types of installations, Wiring of temporary installations and portable appliances.Circuit Diagrams. - Electrical connections of various circuits for-(i)house wiring including those for main and sub-distribution Boards, switches and cut-out etc., together with the load statement for each circuit.and(ii)Lifts with their safety devices.Apparatus. - Installation and maintenance of heaters, cookers, refrigerators, and other domestic appliances electric bells and indicators, small motors for pumps and electric lifts.Energy Measurement and Charges. - Energy meters both Direct Current. (D.C.) and Alternating Current (A.C.) for house service. Simple calculations relating to cost of energy, Elementary knowledge of methods of charging for energy.Testing and Fault Attendance. - Detection and location of faults in domestic appliance and wiring installations, Insulation and continuity tests, rectification of faults. Tests for insulation resistance to earth. Earth testing.Protective Devices. - Elementary knowledge of the use of fuses and cut-outs, Earthing of domestic appliances, motors etc.. Use of Lightning arrestors.Industrial installations,-Wiring. - Wiring layouts of different types such as cleat, wood casing and capping. Metal sheathed, Cab Tyre Sheathed, Conduit and armoured cable for lighting and power installations in industrial premises together with the necessary switch gear. Estimates of materials and cost of different types of installations. Wiring of temporary installations and portable appliances.Circuit Diagrams. - Electrical Connections for-(i)Direct Current (D.C.) and Alternating Current (A.C.) Generators, Switch-Boards, transformers etc.;(ii)Main and sub-distributing boards with circuit breakers, Switch-fuse units, with load statement for each circuit;(iii)Direct Current (D.C.) and Alternating Current (A.C.) motors, their starters, regulators;(iv)Battery charging equipment;(v)Converting machinery;(vi)Lifts with their safety devices.Pump installations. - General principles and elementary calculations of head, power and energy requirements.Apparatus. - Installation and maintenance of generators, electric motors, electric lifts, electric furnaces, electric welding plants, haulage and winding machines, cooling and heating appliances. Power and Energy measurement and Charges - Measurement of Power, Watt-Meters, Energy Meters, both Direct Current (D.C.) and Alternating Current (A.C), Power factor correction by capacitors.Simple calculations relating to cost of power and energy, Elementary knowledge of methods of charging for demand and energy.Testing and Fault Attendance. - Detection and location of faults in Direct Current (D.C.) and Alternating Current (A.C.) Generators, Motors, Overhead distribution lines and underground cables, electric instruments and apparatus and wiring installations; Rectification of faults, Insulation and continuity tests. Test for insulation resistance to earth, Earth testing.Protective Devices. - Elementary knowledge of earthing of Generators, Motors, Machines, installations and appliances. Use of lightning arresters, fuses, including higher rupturing capacity fuses, cut-outs, circuit breakers, Overload and no-volt protection, thermal trips. Field breaking switches and over-speed protection.Paper IIIMine InstallationsWiring. - Wiring layouts of different types such as cleat, lead covered, cab type sheathed for lighting purposes and armoured cables for power installations. Different types of trailing cables and their use.Circuit Diagrams. - Electrical connections for -(i)Direct Current (D.C.) and Alternating Current (A.C.) generators, switch boards, transformers etc.,(i)Distribution boards with circuit breakers, switch fuse units and gate-end switches.(iii)Direct Current (D.C.) and Alternating Current (A.C.) Motors, their starters and regulators.Apparatus - (i) Installation and maintenance of -(a)Electrical, winders, haulages and pump units, their control gears and starters.(b)Rectifiers, rotary convertors and electric locomotives.(c)Portable and transportable machineries-Coal cutting machines, loaders, conveyers. Gate-end switches, drill panels with drill units and their control systems.(ii)General principles and elementary calculations of load. Power and energy consumption in pumping, hauling and winding installations and other working face machineries.Power and Energy Measurement and Charges. - Measurement of Power, Watt Meters, energy meters both Direct Current (D.C.) and Alternating Current (A.C.) Power factor correction by capacitors. Simple calculations relating to cost of power and energy. Elementary knowledge of methods of charging for demand and energy.Testing and Fault Attendance. - Detection and location of earth or other faults in electrical apparatus and cables. Insulation and continuity test, Rectification of faults, Test for insulation resistance to earth, Testing of leakage protective device, Earth testing.Protective Devices. - Elementary knowledge of earthing of metal frames of Machineries. Use of Fuses, Overload, no-volt and earth leakage protection of circuit breakers.Electricity Regulations. - Working knowledge of-The Central Electricity Authority (Measures relating to safety and power supply) Regulation, 2010 with particulars reference to Chapter IX.Notes: Candidates desiring to qualify only for electrical installations in Mines need not appear for compulsory section under part - II, however, Part -1 is compulsory for such candidates also:Annexure - IVFees| Sl. No | Particulars | Rules Applicable | Fees in INR |
| A | New | ||
| 1. | Licence to Electrical Contractor (For 5 years) | Rule 38 | 10,000/- |
| ElectricalSupervisor's Certificate of Competency (For 10 years)(a) For 2 parts at atime -(b) For each additional part - | Rule 13 | 800/-400/- | |
| 2. | National Certificate of Supervisor (For 10years) | Rule 29(2) | 5,000/- |
| 3. | Workman's Permit (For 10 years) for each part | Rule 13 | 200/- |
| B | Renewal | ||
| 1. | Licence to Electrical Contractor (For 5 years) | Rule 41 | 5,000/- |
| 2. | Electrical Supervisor's Certificate ofCompetency (For 10 years) | Rule 27 | 500/- |
| 3. | National Certificate of Supervisor (For 10years) | Rule 34 | 4,000/- |
| 4. | Workman's Permit(For 10 years) | Rule 19 | 200/- |
| Sl. No | Particulars | Rules Applicable | Fees in INR | |
| C | Penalty for late submission (For Renewal) | |||
| 1. | Licence to Electrical Contractor | Upto one month | Rule 41 | No extra charge |
| After one month, upto six months | Rule 41 | 5,000/- | ||
| 2 | Electrical Supervisor's Certificate ofCompetency | Upto one month | Rule 27 | No extra charge |
| After one month, upto six months | Rule 27 | 200/- | ||
| 3. | National Certificate of Supervisor | Upto one month | Rule 34 | No extra charge |
| After one month, upto six months | Rule 34 | 3000/- | ||
| 4. | Workman's Permit | Upto one month | Rule 19 | No extra charge |
| After one month, upto six months | Rule 19 | 200/- | ||
| D. | Others | |||
| 1. | For duplicate Contractor's Licence | Rule 42 | 1000/- | |
| 2. | For duplicate Supervisor, National Supervisor,workman Permit. | Rule28, 35&20 | 100/- | |
| 3. | For endorsement of any kind/updation/entry oflegacy records | 200/- | ||
| 4. | For induction of new supervisor/intermediatechange of supervisors | Rule 40(3) | 500/- | |
| 5. | IR Tester/Meggar(500V/2.5 KV or above) | Rule 41(1)(d) | 500/- | |
| 6. | Earth Tester(1-10 ohms) | Rule 41(I)(d) | 500/- |
2. Initially copy of purchase invoice and manufacturer's test certificate of the meggar to be submitted while applying for Contractor Licence. In case of induction of old meggar that should be tested from National Accreditation Board for Testing and Calibration Laboratories (NA BL) accredited Laboratory.
3. In case any license is not at all renewed beyond six months from the date of its expiry, then the licence will be treated as cancelled.
Should a passed candidate desire to qualify, subsequently fora class other than that for which a certificate or permit has been granted, he will be permitted to appear in the examination for the parts concerned and will be charged the additional fee or fees.Similarly, those who apply for exemption from the Supervisors' examination and who have been granted a certificate for one class, or more classes may apply with the requisite fee for examination in any other additional class or classes.(ii)Candidates will be supplied with a copy of the pass list as soon as it is available. No reply will be issued to applications made before hand, as the information will be available in the website of the Department www.wbpower.gov.in.(iii)Apart from the issue of the pass list no correspondence will be entered into in respect of the results of the examination(iv)All fees for examinations, permits, certificates, contractors' licenses and the annual renewal thereof, and any other fees leviable under these regulations shall be paid through GRIPS into a Government Treasury in the State of West Bengal.Annexure-VExaminer's Fee| Sl. No. | Examinations | Rules Applicable | Honorarium/Remuneration |
| 1. | Oral & practical test for Workman Permit(W.P.) Examination | Rule 12(6) | Rs 25.00 per candidate in aboard of minimum oneexaminer |
| 2. | Oral & practical test for Supervisor'sCertificate of Competency(S.C.C) Examination | Rule 12(6) | Rs 50.00 per candidate in a board of minimum oneexaminer |
| Sl. No. | Appearance at Licensing Board meeting | Rules Applicable | Honorarium/Remuneration |
| 1. | Board Members/President | Rule 7(2) | Rs. 800.00 per appearance |
| 1. | Full name and address of the applicant (in blockletters)including Mobile No. | : | |
| 2. | Date of birth and age in completed years on thedate of application | : | |
| 3. | Details of technical qualifications | : | |
| 4. | Details of past and present services (date ofcommencement and termination of each appointment to be given) | : | |
| 5. | Examination for which applicant offers himself | : | |
| 6. | Venue where the applicant desires to be examined | : | Kolkata/Durgapur/N.B |
| 7. | Language which the candidate desires in to be(For S.C.C. candiates examined only) | : | Bengali/Hindi/English |
| 8. | Have you made any previous application in form"A" If so, state the date | ||
| (i) Date of last exam.....................................Roll No......................................... | : | ||
| (ii) S.C.C./W.P.No.........................................(if any)......................................... | : |
| Class of certificate | Qualifying Parts(Compulsory) | Qualifying Date | Secretary's initials |
| Wiring for systems not-exceeding 650 volts. | 1 & 2 | ||
| D.C. Apparatus upto 650 volts | 1, 2 & 3 | ||
| A.C. Apparatus upto 650 volts. | l,2&4 | ||
| Installations exceeding 650 volts | 1,2,3, 4,5,6A, 613, 7A & 7B | ||
| Overhead Lines exceeding 250 volts | |||
| For (A) Voltages upto 650 volts | 1 & 6A | ||
| For (B) Voltages upto 33.000 volts | 1, 6A & 61B | ||
| For (C) Voltages exceeding 33,000 volts | 1, 6A, 613 & 6C | ||
| Underground cables. | |||
| For (A) Voltages upto 1100 volts | 1 & 7A | ||
| For (B) Voltages upto 33,000 volts | I, 7A & 713 | ||
| For (C) Voltages exceeding 33,000 volts | 1, 7A, 713 & 7C | ||
| Mining installation | 1,2,4,6A,7A&8 | ||
| Electric Lifts & Escalators | 1,2,3,4 & 9 | ||
| Electric signs, Electronic devices &Conservation of Electrical Energy | 1,2,3,4 & 10 | ||
| Wiring for systems not exceeding 250 volts | 1 & 11 only | ||
| Installation of Transformer exceeding 650 voltsbut rating upto 125 kVA | 1,2,6A, 613, 7A, 7B & 12 only. |
| Date of renewal | Date of expiry | Secretary's initial |
| Date of renewal | Date of expiry | Secretary's initial |
| Endorsement | |
| Employer | Secretary's initial |
| Date of renewal | Date of expiry | Secretary's initial |
| Part/Class | Description | Qualifying Date | Secretary's Initials |
| For Voltages not exceeding 650 Volts | |||
| (i) | Wiring of buildings (for light, fans and smallmotors)(a) Cleat, wood casing and capping systems, employingwires and cables other than paper insulated cables.(b) Metalsheathed, tough rubber and conduit systems (also any other systemas permitted under the electricity Act, 2003, and CEA (Measuresrelating to Safety and Electric supply) Regulation, 2010 usingwires and cables other than paper insulated cables. | ||
| (ii) | Motor wirings (including generators), in conduitor lead sheathed, with wires and cables other than armoured cable | ||
| (iii) | Motor wirings with cables (laying and jointing) | ||
| (iv) | Overhead line work with cable connections. | ||
| (v) | Cable connections (laying & Jointing)*** | ||
| For "High pressure" Voltageexceeding 650 Volts | |
| vi(a)vi(b)vii(a)vii(b)viii(a)viii(b) | Overhead lines up to 33000 volts only,Overhead lines exceeding 33000 voltsOverhead lines with cables connections up to33000 voltsOverhead lines with cable connections exceeding33000 voltsCable laying and jointing up to 33000 voltsCable laying and jointing exceeding 33000volts |
| Endorsements |
| Photograph |
| 1. Name in which Electrical Contractor's:License is applied for | : | |
| 2. Business Address including Mobile No. &Pin | : | |
| 3. Full name and home address of Proprietor orPartner including Mobile No. & Pin No. | : | |
| 4. Full name of agent or manager (in the case ofa limited company) | : | |
| 5. If a contractor's license has been previouslygranted in the same name, details must be given | : | |
| 6. Names of all Supervisors holding validcertificates of competency in the sole and whole-time employ ofthe applicant. | : |
| Name of Supervisor | Registered No. of Certificate |
| Description. | Maker's | |
| Name | Sl.No. | |
| (a) | .................................................................................................................................................. | |
| (b) | .................................................................................................................................................. | |
| (c) | .................................................................................................................................................. | |
| (d) | .................................................................................................................................................. | |
| (e) | .................................................................................................................................................. |
| (1) | Trade Licence | : |
| (2) | Supervisor's Declaration | : |
| (3) | Supervisor's Appointment | : |
| (4) | Meggar Purchased Voucher | : |
| (5) | Bank Certificate in current | : |
| (6) | Pan Card | : |
| (7) | Earth Tester Voucher | : |
| Date of renewal | Date of expiry | Secretary's initial |
1. All electrical installation work coming within the purview of Regulation 29( I) & 3(3) of the Central Electricity Authority (Measures relating to Safety and Electric supply) Regulations, 2010 as amended undertaken by the holder of this license shall be carried out under the direct super-vision of a person holding a valid certificate of competency and at least 50 percent of the electrical workmen employed on any such work shall be in possession of valid permits issued under Rules 25 & 17 of these Rules.
2. The holder of this license shall maintain a register of supervisors and workmen in the form below and shall produce the register for inspection on demand by an Electric Inspector or other person authorised in this behalf by the Licensing Board.
3. Every contract for electrical installation work coming within the purview of Regulation 29 (1) of the Central Electricity Authority (Measures relating to Safety and Electric supply) Regulations, 2010 as amended undertaken by the holder of this license shall be in writing and he shall be held responsible for the suitability of materials used. Before commencing any work the value of which exceeds Rs. 20000/- inclusive of cost of materials and labour charges, he shall notify the Secretary.
4. On the completion of any electrical install work coming within the purview of Regulation 29 (1) of the Central Electricity Authority (Measures relating to Safety and Electric supply) Regulations, 2010 as amended a test report in the form prescribed by the Board shall be submitted by the holder of this license to the Secretary. The report shall be signed by the supervisor under whose supervision the work has been carried out, and countersigned by the holder of this license who shall be wholly responsible for the due execution of the work.
5. If the holder of this license ceases to be in possession of a valid supervisor's certificate of competency, or ceases to retain in his sole employ at least on supervisor holding a valid certificate of competency, this license shall be invalid and if within one month of the license becoming so invalid the certificate of competency concerned is not revalidated or at least one supervisor holding a valid certificate of competency is not engaged, the license shall be deemed to have been cancelled and the holder shall return the same to the Secretary for cancellation.
6. If the holder of this license accepts an employment under any other firm or person for the purpose of carrying out or supervising any electrical installation work coming within the purview of Regulation 29(1) of the Central Electricity Authority (Measures relating to Safety and Electric supply) Regulations, 2010 as amended this license shall be invalid and the holder shall return the same to the Secretary for cancellation.
7. This license shall be invalid if the holder thereof ceases to have in his possession the instruments necessary for carrying out the tests prescribed for the class or classes of work upon which he is engaged.
8. The holder of this license shall send intimation to the Secretary of the Licensing Board in writing within the periods specified below as to every change of- (1) address of the place of business within two months of such change; (2) proprietor within seven days of such change; or (3) agent or manager (in case of a limited company) within seven days of such change and shall also send similar intimation as to dissolution of partnership within seven days of the date of such dissolution.
Form of Register of Supervisors and Workmen in the employ of holding contractor'sLicense No. of (See Rule 42)| Serial No. | Name of Employee | Wiring staff | Date of | Signature of Secretary | Remarks | ||
| Supervisor's Certificate No. & Date ofvalidity | Electrical Workmen Permit& Date of validity | Employment | Discharge | ||||
| 1. | Full name and address of the applicant (in blockletters) including Mobile No.& Pin No. | : | |
| 2. | Date of birth and age on the date of application | : | |
| 3. | Details of technical qualifications | : | |
| 4. | Details of past and present services-Nate ofcommencement and termination of each appointment to be given) | : | |
| 5. | Parts of Syllabus for which applicant offershimself | : | |
| 6. | Any exemption claimed by the applicant underRegulation 6 and grants here for | : | |
| 7. | Language in which the candidate desires to beexamined | : | English/Hindi/Bengali |
| 8. | Venue where the applicant desires to be examined | : | Kolkata/Durgapur/N.B |
| 9. | Have you made any previous application in form"P" or in Form 'A' referred to in the Rule published withNotification No. dated, if so, state the date or particulars ofany certificate or permit granted to you by this Board. | : |
| Date of renewal | Date of expiry | Change of address | Secretary's initial |
| Class of Certificate | Qualifying date | Secretary's initial |
| General utilization covering Domesticinstallations and Industrial installations | ||
| Mines installations |